Contract 33564: 2007-077-00 EXP HEMLOCK DAM REMOVAL
Project Number:
Title:
Hemlock Dam Removal
Stage:
Closed
Area:
Province Subbasin %
Columbia Gorge Wind 100.00%
Contract Number:
33564
Contract Title:
2007-077-00 EXP HEMLOCK DAM REMOVAL
Contract Continuation:
Previous: Next:
n/a
Contract Status:
Closed
Contract Description:
Hemlock Dam is scheduled for removal during the summer of 2008.  Removal of the dam will improve migration, water quality, and habitat for Lower Columbia River steelhead, and will restore important watershed processes in Trout Creek, a tributary to the Wind River in southwest Washington.  This contract initially provided support to acquire engineering services for designing the dam removal and construction of a channel in the area occupied by the reservoir.  The contract is being amended in March 2008 to provide additional funds that will be contributed toward the construction contract that will remove the dam, excavate and dispose of sediments, and construct a channel through the impacted reach.  This contract is more than one year in length to allow continued support from engineering designs through the major construction period of the project.

3-10-10
This request for a NCTE contract amendment comes about as a result of some followup actions we intend to take at the Hemlock site.   The follow up work is focused on revegetation and construction follow up around the site.  The complexity of the project and delays brought about by the permitting process and legal challenges complicated our timelines.  There are existing funds available without tapping additional, non-obligated BPA funds because we were successful in acquiring additional cost share late in the process of design/implementation.
Account Type(s):
Expense
Contract Start Date:
06/15/2007
Contract End Date:
04/30/2011
Current Contract Value:
$2,053,676
Expenditures:
$2,053,676

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
John Baugher Bonneville Power Administration Yes COR jrbaugher@bpa.gov (503) 230-4512
Erin Black US Forest Service (USFS) No Supervisor ekblack@fs.fed.us (509) 395-3411
Bengt Coffin (USFS) US Forest Service (USFS) Yes Contract Manager bcoffin@fs.fed.us (509) 395-3425
Carl Keller Bonneville Power Administration No Interested Party cjkeller@bpa.gov (503) 230-7692
Rosemary Mazaika Bonneville Power Administration Yes F&W Approver rxmazaika@bpa.gov (503) 230-5869
Khanida Mote Bonneville Power Administration Yes Contracting Officer kpmote@bpa.gov (503) 230-4599
Gloria Perez US Forest Service (USFS) No Administrative Contact gperez@fs.fed.us (360) 891-5168
Donald Rose Bonneville Power Administration No Env. Compliance Lead dlrose@bpa.gov (503) 230-3796


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Funding Package - Submit draft to COTR A: 119. Manage the Hemlock Dam Project 01/31/2009 12/31/2008
Final plans for dam removal and deconstruction oversight B: 175. Produce Designs for Removal of Hemlock Dam 11/15/2009 09/15/2009
Final construction and as-built plans for the channel work C: 175. Produce Designs for Channel Recontour and Excavation of Sediments 01/31/2010 09/15/2009
Complete A&E contract COR work D: 119. Administer A&E Contract 12/31/2009 12/31/2009
Final Monitoring Plan E: 174. Produce Monitoring Plan 02/01/2011 02/01/2011
Complete project monitoring in 2007 F: 157. Conduct Project Monitoring 09/30/2007 09/30/2007
Final report uploaded to the BPA website H: 132. Submit Annual Report for the period June 2007 to Jan 2009 04/01/2011 04/30/2011
Restored Dam Site I: 85. Remove Hemlock Dam 04/04/2011 04/04/2011
Dam Removal Contract Prepared and Administered J: 119. Manage Implementation Contract for Hemlock Dam Removal 09/30/2010 09/30/2010
Recontour Channel K: 30. Recontour Trout Creek through reservoir reach 10/31/2009 08/31/2009
Revegetated Project Area L: 47. Plant vegetation at Hemlock Dam site 04/30/2011 04/30/2011
Invasive Weed Removal M: 53. Remove and Dispose of Invasive Plants from Project Site 08/15/2009 08/14/2009
Log Acquisition Contract Prepared and Administered N: 119. Manage Contract for Log Acquisition 08/15/2009 06/26/2009
Logs and Whole Trees for Constructed Channel O: 53. Forest Thinning for Log Acquisition 08/15/2009 06/15/2009
Complete project monitoring in 2008 P: 157. Conduct Project Monitoring 04/04/2011 04/04/2011
Documentation of Environmental Compliance Q: 165. Document completion of environmental compliance 06/30/2009 06/30/2009
Final report uploaded to the BPA website R: 132. Submit Annual Report for the period Feb 2009 to Apr 2010 04/01/2011 04/30/2011
Attach Progress Report in Pisces S: 132. Submit Progress Report for the period Feb 2009 to Apr2011 04/30/2011 04/30/2011

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Lower Columbia River DPS (Threatened)
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 47 Plant Vegetation
  • 2 instances of WE 53 Remove Vegetation
  • 1 instance of WE 85 Remove/Breach Fish Passage Barrier
  • 1 instance of WE 174 Produce Plan
  • 2 instances of WE 175 Produce Design
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Manage the Hemlock Dam Project 02/09/2007
B 175 Produce Designs for Removal of Hemlock Dam 02/09/2007
C 175 Produce Designs for Channel Recontour and Excavation of Sediments 02/09/2007
D 119 Administer A&E Contract 02/09/2007
E 174 Produce Monitoring Plan 02/09/2007
F 157 Conduct Project Monitoring 02/09/2007
G 185 Periodic Status Reports for BPA 02/09/2007
H 132 Submit Annual Report for the period June 2007 to Jan 2009 02/09/2007
I 85 Remove Hemlock Dam 03/27/2009
J 119 Manage Implementation Contract for Hemlock Dam Removal 02/09/2007
K 30 Recontour Trout Creek through reservoir reach 09/05/2007
L 47 Plant vegetation at Hemlock Dam site 02/09/2007
M 53 Remove and Dispose of Invasive Plants from Project Site 06/05/2009
N 119 Manage Contract for Log Acquisition 02/09/2007
O 53 Forest Thinning for Log Acquisition 06/05/2009
P 157 Conduct Project Monitoring 02/09/2007
Q 165 Document completion of environmental compliance 02/09/2007
R 132 Submit Annual Report for the period Feb 2009 to Apr 2010 02/09/2007
S 132 Submit Progress Report for the period Feb 2009 to Apr2011 06/15/2007