| Blue Mountain | Grande Ronde | 100.00% |
* Expenditures data includes accruals and are based on data through 30-Nov-2025.
| Full Name | Organization | Write Permission | Contact Role | Work Phone | |
|---|---|---|---|---|---|
| Michael (ODFW) Arredondo | Oregon Department of Fish and Wildlife | No | Administrative Contact | michael.p.arredondo@state.or.us | (503) 947-6137 |
| Joe Deherrera | Bonneville Power Administration | Yes | COR | jldeherrera@bpa.gov | (503) 230-3442 |
| Bruce Eddy | Oregon Department of Fish and Wildlife | No | Administrative Contact | bruce.r.eddy@state.or.us | (541) 962-1825 |
| Brenda Heister | Bonneville Power Administration | Yes | Contracting Officer | bsheister@bpa.gov | (503) 230-3531 |
| Dave Larson | Oregon Department of Fish and Wildlife | No | Supervisor | david.c.larson@state.or.us | (541) 963-4954 |
| Cathy Nowak | Oregon Department of Fish and Wildlife | Yes | Contract Manager | cathy.nowak@state.or.us | (541) 963-4954 |
| Nancy Weintraub | Bonneville Power Administration | No | Env. Compliance Lead | nhweintraub@bpa.gov | (503) 230-5373 |
| Benjamin Zelinsky | Bonneville Power Administration | Yes | F&W Approver | bdzelinsky@bpa.gov | (503) 230-4737 |
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Environmental Compliance Documentation | A: 165. Produce Environmental Compliance Documentation | 09/30/2008 | 01/16/2008 | |
| Summary of O&E activities in Progress Reports and Annual Report | B: 99. Respond to requests for project tours and information | 09/30/2009 | 09/30/2009 | |
| Diverse vegetation communities in the project area | C: 22. Management activities to encourage native vegetation and control non-native vegetation. | 09/30/2009 | 09/30/2009 | |
| Vegetation and wildlife survey data collected | D: 157. Conduct field monitoring activities throughout the project | 09/30/2009 | 09/30/2009 | |
| Summary data and photographs of project area | E: 162. Compile, analyze and interpret monitoring data | 09/30/2009 | ||
| Operate and maintain water control structures | F: 186. Operate and maintain water control structures | 09/30/2009 | 09/30/2009 | |
| Maintain Fences and Gates | G: 186. Maintain Fences and Gates | 09/30/2009 | 09/30/2009 | |
| Access and other information available to the public | H: 188. Update and maintain access and information signs | 09/30/2009 | 09/30/2009 | |
| FY 09 Funding Package (SOW, budget, Property inventory), plus September accrual estimate. | I: 119. Manage and Administer Ladd Marsh Wildlife Area Additions Project | 09/10/2008 | 09/22/2008 | |
| Annual Report | J: 132. Submit Progress Report for the period October 2007 to September 2008 | 09/30/2009 | ||
| Attach Progress Report in Pisces | L: 132. Submit Progress Report for the period October 2008 to September 2009 | 09/30/2009 | ||
| Environmental Compliance Documentation | M: 165. Produce Environmental Compliance Documentation for FY 2009 activities | 09/30/2008 | 09/30/2008 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened) |
|
| Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
| Trout, Rainbow (Oncorhynchus mykiss) |
|
| Trout, Interior Redband (O. mykiss gairdnerii) |
|
| Wildlife |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 165 | Produce Environmental Compliance Documentation | 02/09/2007 | ||||||
| B | 99 | Respond to requests for project tours and information | 02/09/2007 | ||||||
| C | 22 | Management activities to encourage native vegetation and control non-native vegetation. | 02/09/2007 | ||||||
| D | 157 | Conduct field monitoring activities throughout the project | 08/30/2007 | ||||||
| E | 162 | Compile, analyze and interpret monitoring data | 02/09/2007 | ||||||
| F | 186 | Operate and maintain water control structures | 02/09/2007 | ||||||
| G | 186 | Maintain Fences and Gates | 09/26/2007 | ||||||
| H | 188 | Update and maintain access and information signs | 02/09/2007 | ||||||
| I | 119 | Manage and Administer Ladd Marsh Wildlife Area Additions Project | 02/09/2007 | ||||||
| J | 132 | Submit Progress Report for the period October 2007 to September 2008 | 02/09/2007 | ||||||
| K | 185 | Periodic Status Reports for BPA | 02/09/2007 | ||||||
| L | 132 | Submit Progress Report for the period October 2008 to September 2009 | 02/09/2007 | ||||||
| M | 165 | Produce Environmental Compliance Documentation for FY 2009 activities | 02/09/2007 |