Contract 35813: 200200300 EXP SECURE & RESTORE F&W HABITA
Project Number:
Title:
Secure and Restore Fish and Wildlife Habitat in Montana
Stage:
Implementation
Area:
Province Subbasin %
Mountain Columbia Flathead 100.00%
Contract Number:
35813
Contract Title:
200200300 EXP SECURE & RESTORE F&W HABITA
Contract Continuation:
Previous: Next:
n/a
  • 39495: 200200300 EXP SECURE & RESTORE F&W HABITAT
Contract Status:
Closed
Contract Description:
The construction of Hungry Horse Dam inundated 125 km of adfluvial trout habitat in the South Fork of the Flathead River and its tributaries, impacting natural fish reproduction and rearing.  Rapid residential and commercial growth in the Flathead Watershed now threaten the best remaining habitats and restrict our opportunities to offset losses. Hydropower development and other land disturbances caused severe declines in the range and abundance of our focal resident fish species, bull trout and westslope cutthroat trout. Bull trout were listed as threatened in 1998 under the Endangered Species Act and westslope cutthroat were petitioned for listing under ESA.  Westslope cutthroat are a species of special concern in Montana and a species of special consideration by the Confederated Salish and Kootenai Tribes.  Consistent with the 2000 Fish and Wildlife Program, this project follows the logical progression towards habitat restoration outlined in the Hungry Horse Dam Fisheries Mitigation Implementation Plan approved by the NWPPC in 1993.  The Flathead River Subbasin Plan identifies the protection of habitats for these populations as one of the most critical needs in the subbasin and directs actions to offset these losses.  This project facilitates efforts by the Confederated Salish and Kootenai Tribes (CSKT) and Montana Fish, Wildlife & Parks (MFWP) to protect and enhance critical fish habitat within the Flathead River watershed.  We seek to rebuild to sustainable levels weak, but recoverable, native populations injured by the hydropower system.  We propose to (1) secure habitats through land acquisition and conservation easements; (2) enhance existing and newly acquired habitats to maximize their value to fish; and (3) utilize a balanced, watershed-wide approach to reverse the downward trends in native species and protect healthy populations.
Account Type(s):
Expense
Contract Start Date:
10/01/2007
Contract End Date:
09/30/2008
Current Contract Value:
$50,519
Expenditures:
$50,519

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Cecilia Brown Bonneville Power Administration Yes COR ckbrown@bpa.gov (503) 230-3462
Lynn DuCharme Salish and Kootenai Confederated Tribes Yes Technical Contact lynn.ducharme@cskt.org (406) 883-2888x7279
Les Evarts Salish and Kootenai Confederated Tribes No Supervisor les.evarts@cskt.org (406) 675-2700
Barry Hansen Salish and Kootenai Confederated Tribes Yes Contract Manager barry.hansen@cskt.org (406) 883-2888
Paul Krueger Bonneville Power Administration Yes F&W Approver pqkrueger@bpa.gov (503) 230-5723
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Completed NEPA documentation A: 165. Work with BPA staff to complete NEPA and public involvement requirements 09/30/2008 09/30/2008
Final realty package submitted to BPA B: 172. Conduct all pre-acquisition activities for lands purchased under the FY07 MOA 09/30/2008 09/30/2008
Funding Package - Submit draft to COTR C: 119. Complete necessary BPA contracting requirements 06/30/2008 06/30/2008
Annual report D: 132. Submit Progress Report for the period 10/1/2007 to 9/30/2008 09/30/2008 09/30/2008

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Work with BPA staff to complete NEPA and public involvement requirements 02/09/2007
B 172 Conduct all pre-acquisition activities for lands purchased under the FY07 MOA 02/09/2007
C 119 Complete necessary BPA contracting requirements 02/09/2007
D 132 Submit Progress Report for the period 10/1/2007 to 9/30/2008 02/09/2007
E 185 Periodic Status Reports for BPA 02/09/2007