Close Message
CBFish website will be offline for approximately one hour starting at 5 PM today for maintenance. Thank you for your patience.
Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 36484: 1995-011-00 EXP CHIEF JO. KOK. ENHANCEMENT PROJECT
Project Number:
Title:
Chief Joseph Kokanee Enhancement
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Intermountain Columbia Upper 100.00%
Contract Number:
36484
Contract Title:
1995-011-00 EXP CHIEF JO. KOK. ENHANCEMENT PROJECT
Contract Continuation:
Previous: Next:
31101: 1995-011-00 CHIEF JOSEPH KOKANEE ENHANCEMENT
  • 41540: 199501100 EXP CHIEF JO. KOK. ENHANCEMENT PROJECT
Contract Status:
History
Contract Description:
The Chief Joseph Kokanee Enhancement project began in 1995 with the intent of protecting and enhancing natural origin kokanee in the blocked area (Lake Roosevelt and Rufus Woods). Objectives included enumeration of adult tributary spawning kokanee, genetic evaluation of kokanee populations and determination of egg to fry survival.  In 1996 the project switched directions and focused primarily on assessing entrainment at Grand Coulee Dam while minimally assessing kokanee escapement.  Entrainment was determined to be substantial and could severely impact BPA funded programs related to resident fish.  With the recommendation of Independent Scientific Review Panel (ISRP) this project shifted its focus towards conducting a strobe light efficacy test using hydrophones and sonic tags to determine and reinforce the effect strobe lights had on fish behavior.  It was determined that strobe lights were not a good method for deterring fish from entering the forebay of the third powerhouse and the project ended.

As part of the 07-09 BPA funding cycle, the project redirected its focus towards kokanee supplementation/restoration and habitat enhancement work within major tributaries within the blocked area that included both the San Poil and Nespelem Rivers and Barnaby and Big Sheep Creeks with the main focus towards natural origin kokanee.  The project withdrew objectives and work elements related to spawning channel feasibility and construction and shifted those actions towards developing a master plan based on ISRP review and the Councils recommendation.  The Chief Joseph Kokanee Enhancement project proposes using an artificial production program to reintroduce kokanee back into the San Poil River (possibly beyond).  The current plan proposes using an in basin stock (Meadow Cr.) released at fingerling state in the fall in hopes that it will increase imprinting and homing fidelity thereby increasing swim performance allowing for better escapement from predators and entrainment.  However, this project and others associated with hatchery production came under critical review by the ISRP.  Based on a series of reviews and meetings, the NPCC recommended  that the Colville Tribes begin the Three-Step Process for artificial production associated with natural origin kokanee restoration in the San Poil River. The budget for the Three-Step Process is $85,000 for fiscal years 2008 and 2009.  Funds need to be reallocated from the current budget to begin the process.   The Council anticipates that the step submittal will be received by the first quarter of 2009.  The project anticipates contracting this service with the RFP posted by February 2008.  Since this work was not submitted in the original proposal there may be a need to conduct a scope change.  In addition to this work, it was required that the Lake Roosevelt group finalize their joint guidance document for review by the ISRP and Council by September 2008.

A fish passage restoration effort is currently underway that would allow adult migrating kokanee access to approximately .5 miles of habitat above a highway culvert at  Barnaby Cr. Currently this culvert is impassable during specific water elevations associated with Lake Roosevelt drawndown.  This tributary was stocked in the early to mid 1990's for three consecutive years with returns in subsequent years  Preliminary analysis at this point in time suggests that the feasibility of conducting such an action is favorable.  The final report due to the project is expected January, 2008.  The design and engineering portion of the project would be conducted during FY08 and construction in FY09.

The project will continue to monitor adult escapement in the San Poil and Nespelem Rivers and Big Sheep Creek and Barnaby Creek.  Big Sheep Creek was stocked with approximately 500,000 fry in 2005 and it is expected that a percentage of these fish will return this year (08).  San Poil was stocked in 2005 and 2006 with approximately 50,000 fingerlings each year.  Their expected return begins in 2008.

A new study plan was developed in 2007 to determine the origin of "at large" kokanee found in Lake Roosevelt.  Past genetic studies have shown that the "at large" kokanee are a mixed population of upper basin stocks and the San Poil River but escapement numbers have been extremely low indicating that there may have been problems with stock origin assignments.  The new study plan will eliminate the stock assignment issues within Lake Roosevelt and the San Poil River while also assessing new stocks from Canada that may contribute to this population.
Account Type(s):
Expense
Contract Start Date:
01/01/2008
Contract End Date:
12/31/2008
Current Contract Value:
$351,195
Expenditures:
$351,195

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Collection Permit A: 165. NEPA 03/31/2008 03/31/2008
Spawning Escapement Enumeration and Juvenile Production B: 70. Spawning Escapement Enumeration and Juvenile Production 11/29/2008 11/28/2008
Juvenile Kokanee Trapping Survey C: 157. Monitor and Evaluate Screw Traps 11/29/2008 06/06/2008
Adult Kokanee Trapping and Monitoring Survey. D: 157. Adult Kokanee Monitoring 11/29/2008 12/08/2008
Collection of Kokanee Tissue Samples E: 157. Genetic Tissue sampling 12/31/2008 12/31/2008
Genetic Evaluation of Kokanee Salmon Within the Blocked Area F: 162. Genetic Evaluation of Kokanee Salmon Within the Blocked Area 12/31/2008 12/31/2008
Barnaby Creek Fish Passage G: 174. Fish passage 09/30/2008
Develop Master Plan H: 168. Develop Master Plan for San Poil River 12/31/2008 12/31/2008
Coordination I: 191. Coordination with other BPA projects and hatcheries 12/31/2008 12/31/2008
Funding Package - Submit draft to COTR J: 119. Project Administration 11/28/2008 11/28/2008
Attach Progress Report in Pisces K: 132. Submit Progress Report for the period (Feb 2007) to (Dec 2007) 04/15/2008 04/15/2008
Habitat Enhancement M: 98. Move and install root wads to San Poil River/Lake interface 12/31/2008

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Kokanee (Oncorhynchus nerka)
  • 1 instance of WE 98 Other
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 70 Install Fish Monitoring Equipment
  • 3 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 162 Analyze/Interpret Data
  • 1 instance of WE 168 Council 3-step Process: Step 1

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 NEPA 02/09/2007
B 70 Spawning Escapement Enumeration and Juvenile Production 07/24/2008
C 157 Monitor and Evaluate Screw Traps 05/16/2007
D 157 Adult Kokanee Monitoring 05/16/2007
E 157 Genetic Tissue sampling 05/16/2007
F 162 Genetic Evaluation of Kokanee Salmon Within the Blocked Area 02/09/2007
G 174 Fish passage 02/09/2007
H 168 Develop Master Plan for San Poil River 02/09/2007
I 191 Coordination with other BPA projects and hatcheries 02/09/2007
J 119 Project Administration 02/09/2007
K 132 Submit Progress Report for the period (Feb 2007) to (Dec 2007) 02/09/2007
L 185 Periodic Status Reports for BPA 02/09/2007
M 98 Move and install root wads to San Poil River/Lake interface 02/09/2007