Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 36825: 2007-224-00 EXP IMPLMNT OKANOGAN SUBBASIN PLAN
Project Number:
Title:
Okanogan Subbasin Habitat Implementation Program (OSHIP)
Stage:
Complete
Area:
Province Subbasin %
Columbia Cascade Okanogan 100.00%
Contract Number:
36825
Contract Title:
2007-224-00 EXP IMPLMNT OKANOGAN SUBBASIN PLAN
Contract Continuation:
Previous: Next:
n/a
  • 41542: 2007-224-00 EXP IMPLEMENT OKANOGAN SUBBASIN PLAN
Contract Status:
Closed
Contract Description:
The goal of this project is to implement the Okanogan Sub-Basin Plan.  The Sub-Basin Plan was developed to describe in detail the current state of the Okanogan Basin and then describe what are the limiting factors for anadromous salmonid production and survival.  Implementing the Sub-Basin Plan will require a sequenced set of key habitat restoration and protective actions.  The Okanogan River, Similkameen River and associated tributaries have several factors that limit salmonid production and rearing.  These factors include but are not limited to:  temperature, flow, habitat complexity, sedimentation and substrate.  We will be looking at limiting factors throughout the Okanogan River Basin, in the main-stem and tributary portions of the basin to assemble a list of potential projects and then assess their feasibility.  We will update the Okanogan Initiative as we identify and complete habitat restoration projects.

The overall idea is to develop a prioritized project list for implementation of habitat projects in future years.  In the first year we will be doing some projects on the ground that we have already developed as well as developing our prioritized list.
Account Type(s):
Expense
Contract Start Date:
02/01/2008
Contract End Date:
01/31/2009
Current Contract Value:
$396,232
Expenditures:
$396,232

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
A prioritized list of potential habitat rehabilitation projects A: 114. Assess and Prioritize projects 01/31/2009 01/31/2009
Develop Landowner contacts and participation B: 191. Contact Landowners and interested Public parties, attend meetings 01/31/2009 01/31/2009
Designs and specifications for future habitat projects throughout the Okanogan Basin C: 175. Design future habitat projects throughout the basin 01/31/2009 01/31/2009
Applicable permits and other environmental clearances received D: 165. Environmental Compliance 01/31/2009 01/31/2009
Alternative water developments (Wanacut, Wildhorse Spring and Ninemile creeks) E: 34. Alternative water developments (Wanacut, Wildhorse Spring and Ninemile creeks) 01/31/2009 12/24/2008
Wildhorse Spring Creek vegetation planting F: 47. Wildhorse Spring Creek native planting 07/15/2008 11/01/2008
Design for Wildhorse Spring Creek Culvert Replacement G: 175. Wildhorse Spring Creek Culvert Replacement 01/30/2009 01/30/2009
Wildhorse Spring Creek noxious weed treatment completed H: 53. Wildhorse Spring Creek noxious weed treatment 07/15/2008 07/15/2008
Wildhorse Spring Creek Livestock fencing completed I: 40. Wildhorse Spring Creek Livestock fencing 12/15/2008 12/15/2008
Develop project tracking system through an Access database J: 160. Develop project tracking system through an Access database 01/31/2009 01/31/2009
Manage and Administer Project M: 119. Manage and Administer Project 01/31/2009 01/31/2009

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 1 instance of WE 34 Develop Alternative Water Source
  • 1 instance of WE 40 Install Fence
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 53 Remove Vegetation
  • 2 instances of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 114 Assess and Prioritize projects 02/09/2007
B 191 Contact Landowners and interested Public parties, attend meetings 02/09/2007
C 175 Design future habitat projects throughout the basin 02/09/2007
D 165 Environmental Compliance 02/09/2007
E 34 Alternative water developments (Wanacut, Wildhorse Spring and Ninemile creeks) 01/15/2009
F 47 Wildhorse Spring Creek native planting 01/15/2009
G 175 Wildhorse Spring Creek Culvert Replacement 02/09/2007
H 53 Wildhorse Spring Creek noxious weed treatment 01/15/2009
I 40 Wildhorse Spring Creek Livestock fencing 01/15/2009
J 160 Develop project tracking system through an Access database 02/09/2007
K 185 Periodic Status Reports for BPA 02/09/2007
L 132 Begin preparing annual report for the period (Feb 2008) to (Jan 2009) 02/09/2007
M 119 Manage and Administer Project 02/09/2007