| ESA/NEPA/NHPA Compliance complete |
A: 165. ESA/NEPA/NHPA Compliance for Implementation Projects |
|
10/31/2009 |
03/31/2009 |
| Completed NRAMP Step 1 on 10 Tribal Properties |
B: 115. Inventory, Assess and Develop Restoration Plans using NRAMP |
|
04/30/2009 |
03/31/2009 |
| Project Designs for Areas Prioritized by the 10-year Plan and NRAMP Step 1 |
C: 114. Select, Prioritize, and Obtain Permission for Projects Recommended by NRAMP |
|
04/30/2009 |
03/31/2009 |
| 14 Miles of Previously Constructed Fence Maintained |
D: 186. Maintain 14 Miles of Previously Constructed Fence |
|
04/30/2009 |
07/31/2008 |
| 500 feet of Stream/Riparian Fence Constructed |
E: 40. Construct Riparian Protection Fence on TA 350, TA 352, and adjacent private land |
|
04/30/2009 |
03/31/2009 |
| 3.34 Acres of Invasive Plant Management |
F: 53. Treat Exotic Invasive Plant Species on TA 350, TA 352, and adjacent private land |
|
11/01/2008 |
11/01/2008 |
| 2.5 Acres of Native Vegetation Planted |
G: 47. Plant native trees and shrubs on TA 350, TA 352 and adjacent private land |
|
04/30/2009 |
03/31/2009 |
| 0.84 Acres of Wetland Restored |
H: 181. Restore wetland on TA 350, TA 352, and adjacent private land |
|
04/30/2009 |
03/31/2009 |
| Vegetation maintained on TU 3125 |
I: 22. Maintain vegetation on TU 3125 |
|
12/11/2008 |
09/30/2008 |
| 40 Acres of Invasive Plant Species Controlled |
J: 53. Treat Exotic Invasive Plant Species on TU 3125 |
|
11/01/2008 |
09/30/2008 |
| 2,000 feet of Riparian Protection Fence Constructed |
K: 40. Construct Riparian Protection Fence on TU 3123 |
|
10/31/2009 |
10/31/2009 |
| 13.5 Acres of Wetland Restored |
L: 181. Restore wetland on TU 3123 |
|
10/31/2009 |
10/31/2009 |
| 100 feet of eroded streambank stabilized |
M: 29. Stabilize eroded stream bank on TU 3123 |
|
10/31/2009 |
03/31/2009 |
| Fish passage barrier removed and bridge installed over Lapwai Creek |
N: 184. Install bridge over Lapwai Creek at Herndon site |
|
12/01/2008 |
09/30/2008 |
| Native vegetation planted on 0.5 acres at bridge replacement site |
O: 47. Plant native trees and shrubs at Herndon bridge replacement site |
|
04/30/2009 |
12/31/2008 |
| 20 Acres of Invasive Plant Management |
P: 53. Treat Exotic Invasive Plant Species on TA 365 |
|
11/01/2008 |
09/30/2008 |
| Vegetation maintained on Tribal Allotment 365 |
Q: 22. Maintain vegetation on TA 365 |
|
11/01/2008 |
09/30/2008 |
| Lapwai Creek Education and Outreach |
R: 99. Lapwai Creek Project Area Education and Outreach |
|
04/30/2009 |
03/31/2009 |
| FY 09 SOW Package and FY 08 Accrual Estimate |
S: 119. Management, Coordination and Communication |
|
02/21/2009 |
03/31/2009 |
| Final FY 07 annual report attached to this contract |
T: 132. Produce (Annual) Progress Report for Period 3/1/07-4/30/08 |
|
02/28/2009 |
|