Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 37494: 2001-021-00 EXP FIFTEEN MILE CREEK RIPARIAN BUFFERS
Project Number:
Title:
15 Mile Creek Riparian Buffers
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Gorge Fifteenmile 100.00%
Contract Number:
37494
Contract Title:
2001-021-00 EXP FIFTEEN MILE CREEK RIPARIAN BUFFERS
Contract Continuation:
Previous: Next:
32383: 2001-021-00 EXP FIFTEEN-MILE CREEK RIPARIAN BUFFERS
  • 46807: 2001-021-00 EXP FIFTEEN MILE CREEK RIPARIAN BUFFERS
Contract Status:
Closed
Contract Description:
Wasco County Soil and Water Conservation District (SWCD) provides local leadership in implementation of several full-scale watershed enhancement projects focused on improving watershed health.  Working in close partnership with Natural Resources Conservation Service (NRCS) our team's strength is our ability to develop and implement scientifically sound, economically feasible resource management plans for private landowners.

The two year goal is to establish Fifteen to Thirty (15-30) CCRP/CREP agreements which will be signed by landowners annually, committing desired property to CCRP/CREP rules, i.e. shrub/tree/grass planting, weed control, livestock exclusion.  Wasco SWCD staff will track contracts to ensure a smooth process between landowners and partner agencies. This tracking entails monitoring the approval process on completed plans through SWCD, NRCS, and FSA County Committee sign-off and Farm Service Agency (FSA) contracting.  Work elements reflecting this quantity of agreements include 15 regular plus 6 placeholders.  If the actual quantity of agreements exceeds 21, then additional work elements will need to be added by amendment.

This program meets a critical need in Fifteenmile Watershed in particular where existing Oregon Department of Fish and Wildlife (ODFW) riparian lease agreements are expiring.  This project fills a critical staffing need to conduct assessments and develop plans to address the growing backlog of potential projects.  Plans developed under this project are used for federal contracts to implement riparian buffers.  The SWCD uses the USDA NRCS Nine step planning process to develop these plans: (1) Identify problems and opportunities, (2) Determine Objectives, (3) Inventory resources, (4) Analyze resource inventory, (5) Formulate alternatives, (6) Evaluate alternatives, (7) Decision - Select Alternative, (8) Implement the Plan, (9) Evaluate plan (monitor).

Notes:
Operation and Maintenance (O&M) are not required in this project:
Actual O&M is a funded item in the CRP/CREP contracts whereby the landowner receives a small fee per acre to cover maintenance costs.  The landowner is responsible under the contract for the maintenance.  O&M is funded by USDA.

Monitoring and Evaluation (M&E) is included as a cost item.  This is accomplished through visual inspections.  Additionally, records of stream miles, acreage and number of plans completed will be tracked for reporting purposes:
Farm Service Agency (FSA) has programmatic responsibility for spot-checking contracts to ensure terms are being met.  NRCS has responsibility for technical supervision.  The SWCD will use the NRCS Stream Visual Assessment Protocol as the principal monitoring and evaluation tool to evaluate and describe both pre- and post-project conditions.
Account Type(s):
Expense
Contract Start Date:
04/01/2008
Contract End Date:
03/31/2010
Current Contract Value:
$120,929
Expenditures:
$120,929

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Coordinate With (270 total) Private Landowners & Partner Agencies A: 99. Outreach & Education to the Private Landowners 03/31/2010 03/31/2010
Prepare & Submit (15-30 total) NRCS Environmental Checklist B: 165. Prepare & Submit NRCS Environmental Checklist 03/31/2010 03/31/2010
Produce (15-30 total) Conservation Plan For Landowners C: 174. Produce Conservation Plan for Landowners 03/31/2010 03/31/2010
Provide Technical Review On Implementation Of (15-30 total) Conservation Plans D: 122. Provide Technical Review on Implementation of Conservation Plans 03/31/2010 03/31/2010
Sign CCRP/CREP Agreement Signed With Private Landowner E: 92. Sign CCRP/CREP Agreements with Landowners, NRCS, SWCD & FSA 03/31/2010 06/30/2008
Sign CCRP/CREP Agreement Signed With Private Landowner F: 92. Sign CCRP/CREP Agreements with Landowners, NRCS, SWCD & FSA 03/31/2010 12/01/2008
Sign CCRP/CREP Agreement Signed With Private Landowner G: 92. Sign CCRP/CREP Agreements with Landowners, NRCS, SWCD & FSA 03/31/2010 03/31/2009
Sign CCRP/CREP Agreement Signed With Private Landowner H: 92. Sign CCRP/CREP Agreements with Landowners, NRCS, SWCD & FSA 03/31/2010 03/31/2009
Sign CCRP/CREP Agreement Signed With Private Landowner I: 92. Sign CCRP/CREP Agreements with Landowners, NRCS, SWCD & FSA 03/31/2010 03/31/2009
Sign CCRP/CREP Agreement Signed With Private Landowner J: 92. Sign CCRP/CREP Agreements with Landowners, NRCS, SWCD & FSA 03/31/2010 01/01/2009
Sign CCRP/CREP Agreement Signed With Private Landowner K: 92. Sign CCRP/CREP Agreements with Landowners, NRCS, SWCD & FSA 03/31/2010 09/30/2009
Sign CCRP/CREP Agreement Signed With Private Landowner L: 92. Sign CCRP/CREP Agreements with Landowners, NRCS, SWCD & FSA 03/31/2010 03/31/2010
Sign CCRP/CREP Agreement Signed With Private Landowner M: 92. Sign CCRP/CREP Agreements with Landowners, NRCS, SWCD & FSA 03/31/2010 03/31/2010
Sign CCRP/CREP Agreement Signed With Private Landowner N: 92. Sign CCRP/CREP Agreements with Landowners, NRCS, SWCD & FSA 03/31/2010
Sign CCRP/CREP Agreement Signed With Private Landowner O: 92. Sign CCRP/CREP Agreements with Landowners, NRCS, SWCD & FSA 03/31/2010
Sign CCRP/CREP Agreement Signed With Private Landowner P: 92. Sign CCRP/CREP Agreements with Landowners, NRCS, SWCD & FSA 03/31/2010
Sign CCRP/CREP Agreement Signed With Private Landowner Q: 92. Sign CCRP/CREP Agreements with Landowners, NRCS, SWCD & FSA 03/31/2010
Sign CCRP/CREP Agreement Signed With Private Landowner R: 92. Sign CCRP/CREP Agreements with Landowners, NRCS, SWCD & FSA 03/31/2010
Sign CCRP/CREP Agreement Signed With Private Landowner S: 92. Sign CCRP/CREP Agreements with Landowners, NRCS, SWCD & FSA 03/31/2010
Annual Report Uploaded In Pisces AA: 132. Prepare Annual Report For 4/1/07 - 3/31/08 05/31/2008 05/31/2008
Annual Report Uploaded In Pisces AB: 132. Prepare Annual Report For 4/1/08 - 3/31/09 07/29/2009 07/29/2009
Manage & Administer Project AC: 119. Manage & Administer Project 03/31/2010 03/31/2010

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 21 instances of WE 92 Lease Land
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 1 instance of WE 174 Produce Plan

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 99 Outreach & Education to the Private Landowners 02/09/2007
B 165 Prepare & Submit NRCS Environmental Checklist 02/09/2007
C 174 Produce Conservation Plan for Landowners 02/09/2007
D 122 Provide Technical Review on Implementation of Conservation Plans 02/09/2007
E 92 Sign CCRP/CREP Agreements with Landowners, NRCS, SWCD & FSA 02/15/2008
F 92 Sign CCRP/CREP Agreements with Landowners, NRCS, SWCD & FSA 02/15/2008
G 92 Sign CCRP/CREP Agreements with Landowners, NRCS, SWCD & FSA 02/15/2008
H 92 Sign CCRP/CREP Agreements with Landowners, NRCS, SWCD & FSA 02/15/2008
I 92 Sign CCRP/CREP Agreements with Landowners, NRCS, SWCD & FSA 02/15/2008
J 92 Sign CCRP/CREP Agreements with Landowners, NRCS, SWCD & FSA 02/15/2008
K 92 Sign CCRP/CREP Agreements with Landowners, NRCS, SWCD & FSA 02/15/2008
L 92 Sign CCRP/CREP Agreements with Landowners, NRCS, SWCD & FSA 02/15/2008
M 92 Sign CCRP/CREP Agreements with Landowners, NRCS, SWCD & FSA 02/15/2008
N 92 Sign CCRP/CREP Agreements with Landowners, NRCS, SWCD & FSA 02/15/2008
O 92 Sign CCRP/CREP Agreements with Landowners, NRCS, SWCD & FSA 02/15/2008
P 92 Sign CCRP/CREP Agreements with Landowners, NRCS, SWCD & FSA 02/15/2008
Q 92 Sign CCRP/CREP Agreements with Landowners, NRCS, SWCD & FSA 02/15/2008
R 92 Sign CCRP/CREP Agreements with Landowners, NRCS, SWCD & FSA 02/15/2008
S 92 Sign CCRP/CREP Agreements with Landowners, NRCS, SWCD & FSA 02/15/2008
T 92 Sign CCRP/CREP Agreements with Landowners, NRCS, SWCD & FSA (Placeholder) 02/15/2008
U 92 Sign CCRP/CREP Agreements with Landowners, NRCS, SWCD & FSA (Placeholder) 02/15/2008
V 92 Sign CCRP/CREP Agreements with Landowners, NRCS, SWCD & FSA (Placeholder) 02/15/2008
W 92 Sign CCRP/CREP Agreements with Landowners, NRCS, SWCD & FSA (Placeholder) 02/15/2008
X 92 Sign CCRP/CREP Agreements with Landowners, NRCS, SWCD & FSA (Placeholder) 02/15/2008
Y 92 Sign CCRP/CREP Agreements with Landowners, NRCS, SWCD & FSA (Placeholder) 02/15/2008
Z 185 Periodic Status Reports for BPA 02/09/2007
AA 132 Prepare Annual Report For 4/1/07 - 3/31/08 02/09/2007
AB 132 Prepare Annual Report For 4/1/08 - 3/31/09 02/09/2007
AC 119 Manage & Administer Project 02/09/2007