Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 37639: 2007-535-00 EXP TEST FLOW VELOCITY ENHANCEMENT SYSTEM (FVES)
Project Number:
Title:
Physical and Biological Testing of a Flow Velocity Enhancement System (FVES)
Stage:
Closed
Area:
Province Subbasin %
Columbia River Estuary Cowlitz 100.00%
Contract Number:
37639
Contract Title:
2007-535-00 EXP TEST FLOW VELOCITY ENHANCEMENT SYSTEM (FVES)
Contract Continuation:
Previous: Next:
n/a
Contract Status:
History
Contract Description:
This contract funds a new, innovative BPA project. Background engineering, equipment operation, and small-scale tests have already occurred under private funding, which lead to this full-scale field test at an example site on the Cowlitz River with a fish enumeration system. This contract will result in documentation of the capability of a Flow Velocity Enhancement System to direct fish to specific locations through the use of mechanically-induced flow and turbulence in reservoir environments.
Account Type(s):
Expense
Contract Start Date:
05/01/2008
Contract End Date:
03/10/2010
Current Contract Value:
$318,310
Expenditures:
$318,310

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Brenda Aguirre Bonneville Power Administration No Env. Compliance Lead baguirre@bpa.gov (503) 230-5928
Gordon Burns Natural Solutions No Supervisor (406) 458-6363
Deborah Carlson Bonneville Power Administration No Interested Party dcarlson@bpa.gov (509) 372-5751
Brenda Heister Bonneville Power Administration Yes Contracting Officer bsheister@bpa.gov (503) 230-3531
Jamae Hilliard Bonneville Power Administration Yes F&W Approver jlhilliard@bpa.gov (360) 418-8658
Jean Johnson Natural Solutions Yes Contract Manager smolts@msn.com (406) 458-6363
Brian Marotz Montana Fish, Wildlife and Parks (MFWP) No Technical Contact bmarotz@mt.gov (406) 751-4546
John Piccininni Bonneville Power Administration Yes COR jppiccininni@bpa.gov (503) 230-7641


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Project management and administration A: 119. Mobilization and routine administration 10/31/2009 03/10/2010
Environmental Compliance B: 165. Secure Environmental Compliance documentation 06/02/2008 06/02/2008
Site selected and site conditions mapped.. C: 157. Site mapping and micro site selection 06/16/2008 06/29/2008
Installation of trap lead and net D: 70. Installation of trap net and lead 06/21/2008 08/31/2008
Computational Fluid Dynamics Modeling E: 157. Computational Fluid Dynamics Modeling 06/01/2009 03/10/2010
FVES and work barge in place and functioning; service barge fully functional as well. F: 70. Install Flow Velocity Enhancement System 07/31/2008 08/21/2008
FVES sized for test site conditions G: 70. Final site sizing of FVES 07/31/2008 07/31/2008
From study and evaluation, determine whether an FVES can successfully guide migrating smolt H: 157. Determine if FVES can guide migrating smolt 12/31/2008 12/31/2008
Collection results and recommendations for fish guidance and logical next steps I: 162. Statistical Analysis, Evaluation, Reports 06/01/2009 03/10/2010
Attach Progress Report in Pisces J: 132. Submit Progress Report for the period (MMM YYYY) to (MMM YYYY) 09/01/2009 03/10/2009
Statistical analysis, journal article K: 183. Document the flow field and efficiency of fish guidance in First Test 04/01/2009 03/10/2010
Environmental Compliance M: 165. Secure Environmental Compliance documentation for Second Test 05/15/2009 05/15/2009
Installation of trap lead and net N: 70. Installation of trap net and lead for Second Test 07/15/2009 07/15/2009
FVES and work barge in place and functioning; service barge fully functional as well. O: 70. Install Flow Velocity Enhancement System for Second Test 07/07/2009 07/15/2009
Collection results and recommendations for fish guidance and logical next steps P: 162. Statistical Analysis, Evaluation, Reports for Second Test 11/16/2009 03/10/2010
Project management and administration Q: 119. Mobilization and routine contract administration for Second Test 03/10/2010 03/10/2010
Attach Progress Report in Pisces R: 132. Submit Progress Report for the period (May 2008) to (Jan 2010) 02/01/2010 03/10/2010

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Lower Columbia River ESU (Threatened)
  • 1 instance of WE 183 Produce Journal Article
  • 5 instances of WE 70 Install Fish Monitoring Equipment
  • 3 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 2 instances of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Mobilization and routine administration 02/09/2007
B 165 Secure Environmental Compliance documentation 02/09/2007
C 157 Site mapping and micro site selection 02/09/2007
D 70 Installation of trap net and lead 02/09/2007
E 157 Computational Fluid Dynamics Modeling 02/09/2007
F 70 Install Flow Velocity Enhancement System 03/27/2008
G 70 Final site sizing of FVES 02/09/2007
H 157 Determine if FVES can guide migrating smolt 02/09/2007
I 162 Statistical Analysis, Evaluation, Reports 02/09/2007
J 132 Submit Progress Report for the period (MMM YYYY) to (MMM YYYY) 02/09/2007
K 183 Document the flow field and efficiency of fish guidance in First Test 02/09/2007
L 185 Periodic Status Reports for BPA 02/09/2007
M 165 Secure Environmental Compliance documentation for Second Test 02/09/2007
N 70 Installation of trap net and lead for Second Test 03/27/2008
O 70 Install Flow Velocity Enhancement System for Second Test 03/27/2008
P 162 Statistical Analysis, Evaluation, Reports for Second Test 02/09/2007
Q 119 Mobilization and routine contract administration for Second Test 02/09/2007
R 132 Submit Progress Report for the period (May 2008) to (Jan 2010) 02/09/2007