| Province | Subbasin | % |
|---|---|---|
| Basinwide | - | 100.00% |
| Previous: | Next: |
|---|---|
| n/a |
|
* Expenditures data includes accruals and are based on data through 30-Nov-2025.
| Full Name | Organization | Write Permission | Contact Role | Work Phone | |
|---|---|---|---|---|---|
| Matt Berger | Colville Confederated Tribes | Yes | Technical Contact | matt.berger@colvilletribes.com | (509) 634-2142 |
| Chase Davis | Upper Columbia United Tribes (UCUT) | Yes | Contract Manager | chase@ucut-nsn.org | (509) 209-2414 |
| Ray Entz | Kalispel Tribe | Yes | Supervisor | rentz@knrd.org | (509) 445-1147 |
| Paul Krueger | Bonneville Power Administration | Yes | F&W Approver | pqkrueger@bpa.gov | (503) 230-5723 |
| Jenifer Mccune | Bonneville Power Administration | Yes | Contracting Officer | jamccune@bpa.gov | (503) 230-7429 |
| Lori Rothrock | Upper Columbia United Tribes (UCUT) | Yes | Technical Contact | lori@ucut-nsn.org | (509) 838-1057 |
| Virgil Watts III | Bonneville Power Administration | Yes | COR | vlwatts@bpa.gov | (503) 230-4625 |
| Nancy Weintraub | Bonneville Power Administration | Yes | Env. Compliance Lead | nhweintraub@bpa.gov | (503) 230-5373 |
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Produce documentation to satisfy EC needs | A: 165. Produce documentation to satisfy EC needs | 03/31/2009 | 03/31/2009 | |
| Manage Project and EWU subcontract for PhD and field Technician oversight | B: 119. Manage project and subcontract | 03/31/2009 | 03/31/2009 | |
| Input data into and maintain a central UCUT database | C: 160. Input data and maintain database | 01/01/2009 | 01/01/2009 | |
| Summarize data for web based dissemination | D: 161. Summarize data for web based dissemination | 03/31/2009 | 03/31/2009 | |
| Complete M&E plan for permanent sample site selection and site revisitation intervals | E: 156. Complete M&E plan for future permanent sample site selection and site interval revisitation | 03/31/2009 | 03/31/2009 | |
| Funding Package - Submit draft to COTR | F: 119. FY 2009 Funding package submission to BPA COTR | 02/02/2009 | 02/09/2009 | |
| Attach Progress Report in Pisces | G: 132. Submit Progress Report for the period (June 2008) to (March 2009) | 03/30/2009 | 03/30/2009 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Wildlife |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 165 | Produce documentation to satisfy EC needs | 02/09/2007 | ||||||
| B | 119 | Manage project and subcontract | 02/09/2007 | ||||||
| C | 160 | Input data and maintain database | 02/09/2007 | ||||||
| D | 161 | Summarize data for web based dissemination | 02/09/2007 | ||||||
| E | 156 | Complete M&E plan for future permanent sample site selection and site interval revisitation | 02/09/2007 | ||||||
| F | 119 | FY 2009 Funding package submission to BPA COTR | 02/09/2007 | ||||||
| G | 132 | Submit Progress Report for the period (June 2008) to (March 2009) | 02/09/2007 | ||||||
| H | 185 | Periodic Status Reports for BPA | 02/09/2007 |