Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 38390: 1994-015-00 EXP IDAHO FISH SCREENING IMPROVEMENTS-IDFG
Project Number:
Title:
Idaho Fish Screening Improvement
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Salmon 100.00%
Contract Number:
38390
Contract Title:
1994-015-00 EXP IDAHO FISH SCREENING IMPROVEMENTS-IDFG
Contract Continuation:
Previous: Next:
35392: 1994-015-00 EXP IDAHO FISH SCREENING IMPROVEMENT
  • 43275: 1994-015-00 EXP IDAHO FISH SCREENING IMPROVEMENTS-FTE
Contract Status:
History
Contract Description:
The purpose of this project is to fund two fishery biologist positions (personnel only), one in the Salmon Region, and one in the Clearwater Region in order to accelerate the pace of implementation and completion of high priority, on-the-ground fish habitat improvement projects that will be funded from a variety of sources.  These sources may include (but are not limited to) Bonneville Power, Pacific Coast Salmon Recovery Fund, Farm Bill, Snake River Basin Adjudication, Fisheries Restoration and Irrigation Mitigation Act, National Fish Passage Program, Western Native Trout Initiative, NOAA, Landowner Incentive Program, Habitat Improvement Program, etc.  The primary responsibilities will be to identify potential fish habitat improvement projects, prepare proposals for funding, review and prioritize projects and proposals, coordinate activities with other public and private entities, and implement fish habitat improvement projects.
Account Type(s):
Expense
Contract Start Date:
07/01/2008
Contract End Date:
06/30/2009
Current Contract Value:
$92,773
Expenditures:
$92,773

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Funding Package - Submit draft to COTR A: 119. Routine admin of contract 04/17/2009 04/17/2009
Preliminary plans, projects, proposals for the Clearwater basin B: 114. Develop preliminary plans, projects and proposals - Clearwater Region 05/31/2009 05/31/2009
Preliminary plans, projects, proposals for the Upper Salmon basin C: 114. Develop preliminary plans, projects and proposals - Salmon Region 05/31/2009 05/31/2009
Communicate/coordinate in Upper Salmon Subbasin D: 99. Communicate and coordinate with participants in habitat projects - Salmon Region 05/31/2009 05/31/2009
Communicate/coordinate in Clearwater subbasin E: 99. Communicate and coordinate with participants in habitat projects - Clearwater Region 05/31/2009 05/31/2009
Attach Progress Report in Pisces G: 132. Submit Progress Report for the period July 1, 2008 thru June 30, 2009 05/15/2009 05/15/2009

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Routine admin of contract 02/09/2007
B 114 Develop preliminary plans, projects and proposals - Clearwater Region 02/09/2007
C 114 Develop preliminary plans, projects and proposals - Salmon Region 02/09/2007
D 99 Communicate and coordinate with participants in habitat projects - Salmon Region 02/09/2007
E 99 Communicate and coordinate with participants in habitat projects - Clearwater Region 02/09/2007
F 185 Periodic Status Reports for BPA 02/09/2007
G 132 Submit Progress Report for the period July 1, 2008 thru June 30, 2009 02/09/2007