Contract 39168: 2008-603-00 PAHSIMEROI RIVER HABITAT
Project Number:
Title:
Pahsimeroi River Habitat
BPA PM:
Stage:
Complete
Area:
Province Subbasin %
Mountain Snake Salmon 100.00%
Contract Number:
39168
Contract Title:
2008-603-00 PAHSIMEROI RIVER HABITAT
Contract Continuation:
Previous: Next:
n/a
  • 44134: 2008-603-00 EXP PAHSIMEROI RIVER HABITAT-MOA
Contract Status:
Closed
Contract Description:
This project is an expansion of the existing project 2007-268-000 and was identified early in the BPA State of Idaho MOA process as a high priority for inclusion.  Both the IDF&G and the draft NOAAF recovery plans highlight the importance of carrying out habitat actions to assist this key salmon population.

The Pahsimeroi River has a unique population of Snake River Chinook salmon, and in contrast with the Lemhi River and East Fork of the Salmon River watersheds, the salmon population in the Pahsimeroi River is a later migrating summer-run Chinook salmon rather than spring-run. Historically, spawning and rearing habitat was probably supported within the watershed for at least two federally –listed anadromous fish species, spring/summer Chinook salmon, and steelhead. (P. Murphy, 2008)  

The Upper Salmon Watershed Project Technical Team, including IDFG Anadromous Fish Screen Program and Regional Fishery Management has prioritized the lower Pahsimeroi River and its major tributary, Patterson/Big Springs Creek, as SHIPUSS Priority I streams. Those are tributaries and river reaches that have the potential to realize immediate, tangible benefits to fish if recovery efforts are directed toward them. Goals in the lower Pahsimeroi River and Patterson/Big Springs Creek are to enhance migration in both streams by increasing flow regimes and reestablishing habitat connectivity to unused stream reaches. Mechanisms for attaining these goals focus on diversion consolidations and removal/alterations of diversions hindering fish passage. (P. Murphy, 2008)  

At the request of the Idaho Governor’s Office of Species Conservation (OSC) a technical panel with knowledge and expertise of project opportunities within the Pahsimeroi. This team included the Vince Kozakiewicz, NOAA Fisheries, Paddy Murphy (Fisheries Biologist), Eric Leitzinger, Larry Weeks, Lynn Stratton and Jim Lukins, Idaho Department of Fish and Game, Morgan Case and Helen Herrington, Idaho Department of Water Resources, Mark Olson, Natural Resources Conservation Service, Brian Hamilton, Bureau of Reclamation, Jude Trapani, Bureau of Land Management Fisheries Biologist, Jeff Allen, OSC and Karma Bragg, Custer Soil and Water Conservation Service. This core team identified the areas of Pahsimeroi with most potential for fisheries enhancement and recovery within the middle Pahsimeroi. The projects were predominantly in Patterson/Big Springs Creek. Patterson/Big Springs Creek is a very important tributary for spawning and rearing of the unique population of Chinook salmon found in the Pahsimeroi.

Reconnection of Duck Creek, increased flows within Patterson/Big Springs Creek with a focus on the lower five irrigation diversions (PBSC 1-5). This includes a closure of PBSC #2 including any necessary screening to accommodate this closure,  flow enhancements on PBSC #1 & #3 and a Siphon on Mayrick Creek. These projects were prioritized as projects that could be implemented within the next eighteen months. Work reflected in this statement of work is for PBSC #3 and to prepare environmental compliance documents for the reconnect of Duck Creek and removal of the P-9 Structure on the Pahsimeroi.
Account Type(s):
Expense
Contract Start Date:
09/01/2008
Contract End Date:
08/31/2009
Current Contract Value:
$210,748
Expenditures:
$210,748

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Patterson Big Springs Creek #3 Flow Enhancements A: 119. Manage and administer projects within this contract 08/31/2009 08/31/2009
Produce environmental compliance documentation B: 165. Provide BPA with all necessary permits and documents 07/15/2009 09/30/2008
Produce Design and/or Specifications C: 175. Produce Design and/or Specifications 08/31/2009 08/31/2009
Irrigation Equipment and partial installation of equipment D: 150. Purchase sprinkler equipment for PBSC #3 Project 07/31/2009 05/22/2009
Attach Progress Report in Pisces F: 132. Submit Progress Report for the period Sept 08 thru Aug 09 08/31/2009 08/26/2009
Reconnect Duck Creek to it's Historic Channel G: 30. Reconnect Duck Creek to it's historic channel 08/31/2009
Remove P-9 Structure from Pahsimeroi H: 84. Remove P-9 Structure from Pahsimeroi 08/15/2009

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 84 Remove/Install Diversion
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 150 Install Sprinkler
Sockeye (O. nerka) - Snake River ESU (Endangered)
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 84 Remove/Install Diversion
  • 1 instance of WE 150 Install Sprinkler
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Manage and administer projects within this contract 02/09/2007
B 165 Provide BPA with all necessary permits and documents 02/09/2007
C 175 Produce Design and/or Specifications 02/09/2007
D 150 Purchase sprinkler equipment for PBSC #3 Project 08/15/2008
E 185 Periodic Status Reports for BPA 02/09/2007
F 132 Submit Progress Report for the period Sept 08 thru Aug 09 02/09/2007
G 30 Reconnect Duck Creek to it's historic channel 08/04/2009
H 84 Remove P-9 Structure from Pahsimeroi 08/04/2009