SOW Report
Contract 40057: 2007-251-00 EXP UPA MVID EAST PHASE 1
Project Number:
Title:
Methow Valley Irrigation District (MVID) East Irrigation Diversion
BPA PM:
Stage:
Closed
Area:
Province Subbasin %
Columbia Cascade Methow 100.00%
Contract Number:
40057
Contract Title:
2007-251-00 EXP UPA MVID EAST PHASE 1
Contract Continuation:
Previous: Next:
n/a
  • 44205: 2007-251-00 EXP UPA MVID PHASE 1 YEAR 2
Contract Status:
History
Contract Description:
The Methow Valley Irrigation District (MVID) East diversion is located on the Methow River at river mile (RM) 44.8. The present diversion dam has been identified as a partial passage barrier to listed salmonids and bull trout in the Methow Basin. Irrigation canal operations require annual excavation and placement of material within the active river channel to maintain adequate diversion volume to meet irrigation needs. This annual activity adversely affects fish usage within the immediate area of disturbance.

IMPROVEMENTS TO BE COMPLETED 2008 - 2009 UNDER THIS CONTRACT:

1.  Remove 2/3 of the width of the remaining existing wood crib diversion dam
2.  Complete excavation of the intake canal
3.  Renew elevation of existing wing dam with materials excavated from intake canal
4.  Revegetate wing dam structure
5.  Install debris exclusion boom
6.  Access road improvements as required

Objectives:

1. Immediate fish passage improvement
2. Reduce width of main river channel (improve width/depth ratio)
3. Increase reliability of adequate flows required for fish passage
4. Reduce annual disturbance to river from irrigation structure maintenance
5. Increase riparian vegetation cover
6. Reduce loss of woody debris by excluding it from intake canal (boom will direct lwd into the main river channel, where it will remain)

BACKGROUND INFORMATION

Completion of the barrier removal project will require work elements over a 3-year period, through multiple funding sources.

Improvements completed in 2007 under separate funding included:

1. Removal of the top 2 feet of the wood and rock crib dam structure
2. Placement of a temporary weir at the wasteway outlet
3. Preliminary excavation within the intake diversion canal

Improvements necessary to complete the barrier removal project, and planned for 2009 under rescheduled BPA funding, include:

1. Replace headgates (2)
2. Replace existing temporary wasteway
3. Extend and fortify wing wall
4. Complete revegetation
5. Improve security fencing

Preliminary engineering for these components is complete. Final engineering to be completed based on survey findings post construction and value engineering product completed in 2008 .
Account Type(s):
Expense
Contract Start Date:
09/19/2008
Contract End Date:
06/30/2009
Current Contract Value:
$20,000
Expenditures:
$20,000

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Brenda Aguirre Bonneville Power Administration No Env. Compliance Lead baguirre@bpa.gov (503) 230-5928
Cecilia Brown Bonneville Power Administration Yes COR ckbrown@bpa.gov (503) 230-3462
Chris Eliassen Methow Salmon Recovery Foundation Yes Administrative Contact chrise@methowsalmon.org (509) 996-2787
Lisa Gang Bonneville Power Administration Yes Contracting Officer lrgang@bpa.gov (503) 230-3893
Jessica Goldberg Methow Salmon Recovery Foundation Yes Technical Contact jessica@methowsalmon.org (360) 624-3592
Chris Johnson Methow Salmon Recovery Foundation Yes Supervisor chrisj@methowsalmon.org (509) 996-2787
Greg Knott Methow Salmon Recovery Foundation Yes Contract Manager vh_llc@methownet.com (509) 997-0640
Paul Krueger Bonneville Power Administration Yes F&W Approver pqkrueger@bpa.gov (503) 230-5723


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Project management, financial and program administration A: 119. Project management, coordination, provide BPA programmatic information 04/30/2009 04/30/2009
NEPA documentation, HIP compliance, USFWS consultation B: 165. Produce Environmental Permit and Compliance Documents 09/30/2008 09/30/2008
Completed bid package. C: 84. Remove existing diversion structure 06/30/2009
Attach Progress Report in Pisces D: 132. Submit Progress Report for period 09/19/2008 - 03/31/2009 06/30/2009

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 1 instance of WE 84 Remove/Install Diversion
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 1 instance of WE 84 Remove/Install Diversion
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 84 Remove/Install Diversion

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Project management, coordination, provide BPA programmatic information 02/09/2007
B 165 Produce Environmental Permit and Compliance Documents 02/09/2007
C 84 Remove existing diversion structure 10/17/2008
D 132 Submit Progress Report for period 09/19/2008 - 03/31/2009 02/09/2007
E 185 Periodic Status Reports for BPA 02/09/2007