Contract 40778: 2008-307-00 EXP DESCHUTES R. SOCKEYE DEVELOPMENT
Project Number:
Title:
Deschutes River Sockeye Development
BPA PM:
Stage:
Complete
Area:
Province Subbasin %
Columbia Plateau Deschutes 100.00%
Contract Number:
40778
Contract Title:
2008-307-00 EXP DESCHUTES R. SOCKEYE DEVELOPMENT
Contract Continuation:
Previous: Next:
n/a
  • 52139: 2008-307-00 EXP DESCHUTES RIVER SOCKEYE DEVELOPMENT
Contract Status:
Closed
Contract Description:
To implement the development and re-establishment of sockeye in the Deschutes Basin.  The project would develop natural and harvest mortality factors, providing information to the Columbia genetic library for Oncorhyncus nerka.  

Oregon historically had two sockeye runs; the Wallowa Lake and the Deschutes/Suttle Lake Run.  The Deschutes population became extirpated in the 1960’s with the finished construction of the Roundbutte Dam.  This project in coordination with the Portland General Electric and Confederated Tribes of Warm Springs Reservation of Oregon Pelton–Roundbutte FERC license begins the redevelopment of the Deschutes sockeye population.  To re-establish a sockeye run in the Deschutes Basin critical population information is necessary.  This project in partnership with Oregon Department of Fish and Wildlife, and Portland General Electric will develop a cost effective and reliable method of sampling reservoir age class population data for predicting the age 1+ population available for outmigration and source for kokanee harvest.  Genetic information for the sockeye library will be collected and tracked through the Columbia Basin.  The study will also link the use of Suttle Lake production with Lake Billy Chinook and assess if separation is applicable.  Spawning escapement estimates will also be refined.  As a result of the information collected the basin managers can make informed decisions on managing and balancing the re-establishment of sockeye in the Deschutes Basin with a harvestable kokanee population in Lake Billy Chinook.
Account Type(s):
Expense
Contract Start Date:
12/15/2008
Contract End Date:
02/28/2011
Current Contract Value:
$243,190
Expenditures:
$243,190

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Assist With Hydro Acoustic Transects At Lake Billy Chinook A: 157. Assist With Hyrdoacoustic Sampling At Lake Billy Chinook 12/14/2009 11/19/2009
Analyze & Interpret Hydro Acoustic Data B: 162. Analyze & Interpret Hydro Acoustic Data 02/28/2010 10/31/2010
Final Report Complete C: 141. Prepare Report From Hydro Acoustic Data 02/28/2010 12/13/2010
Assess Outmigrant Production For Suttle Lake D: 70. Assess Outmigrant Production For Suttle Lake 06/30/2009 06/23/2009
Monitor & Evaluate Screw Trap/Collect Genetic Samples At Suttle Lake & Lake Creek E: 157. Monitor & Evaluate Screw Trap At Suttle Lake 06/30/2009 06/12/2009
PIT Tag O. nerka Juveniles From Suttle Lake F: 158. PIT Tag O. nerka Juveniles From Suttle Lake 05/31/2009 06/12/2009
Analyze Screw Trap Data & Genetic Samples G: 162. Analyze Screw Trap Data From Suttle Lake 12/14/2009 12/14/2009
Assist With Floy Tagging O. nerka At Lake Billy Chinook H: 158. Assist With Mark/Tag O. nerka At Lake Billy Chinook 09/15/2009 09/03/2009
Collect Genetic Samples At Lake Billy Chinook I: 157. Collect Genetic Samples Of O. nerka At Lake Billy Chinook 10/02/2009 09/03/2009
Assist With Spawning Escapement J: 157. Assist With Spawning Escapement Estimate Refinement 10/31/2009 10/31/2009
Analyze Genetic Samples K: 162. Analyse Genetics Of O. nerka At Lake Billy Chinook 02/28/2011
Cancelled L: 162. Develop Life History Model
Coordinate Sockeye Reintroduction Plan M: 191. Coordinate On Sockeye Reintroduction Plan 02/28/2010 02/28/2010
Sockeye Reintroduction Plan Complete N: 174. Develop Sockeye Reintroduction Plan 02/28/2011
Funding Package - Submit Package To COTR Q: 119. Manage Project 02/28/2010 02/28/2010
Conduct Hydro Acoustic Surveys At Lake Billy Chinook R: 157. Conduct Hyrdoacoustic Sampling At Lake Billy Chinook 12/31/2010
Analyze & Interpret Hydro Acoustic Data S: 162. Analyze & Interpret Hydro Acoustic Data 02/15/2011
Final Report Complete T: 141. Prepare Report From Hydro Acoustic Data 02/28/2011
Assess Outmigrant Production Of O. nerka From Suttle Lake U: 70. Assess Outmigrant Production For Suttle Lake 02/28/2011 02/21/2011
Monitor & Evaluate Smolt Trap/Collect Genetic Samples Below Suttle Lake Outlet In Lake Creek V: 157. Monitor & Evaluate Smolt Trap At Suttle Lake 06/30/2010 06/30/2010
PIT Tag O. nerka Juveniles From Suttle Lake W: 158. PIT Tag O. nerka Juveniles From Suttle Lake 06/30/2010
Analyze Smolt Trap Data & Genetic Samples X: 162. Analyze Smolt Trap Data From Suttle Lake 01/15/2011 02/28/2011
Assist With Floy Tagging O. nerka At Lake Billy Chinook Y: 158. Assist With Mark/Tag O. nerka At Lake Billy Chinook 09/15/2010 08/26/2010
Collect O. nerka Genetic Samples At Lake Billy Chinook Z: 157. Collect Genetic Samples Of O. nerka At Lake Billy Chinook 09/15/2010 08/26/2010
Analyze O. nerka Genetic Samples AA: 162. Analyze Genetics Of O. nerka At Lake Billy Chinook 02/28/2011
Coordinate Sockeye Reintroduction Plan AB: 191. Coordinate On Sockeye Reintroduction Plan 02/28/2011 02/28/2011
Funding Package - Submit Package To COTR AD: 119. Manage Project 11/30/2010 12/20/2010
Sockeye Reintroduction Plan Complete AE: 174. Complete the Sockeye Reintroduction Plan 02/28/2011

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Kokanee (Oncorhynchus nerka)
  • 2 instances of WE 174 Produce Plan
  • 2 instances of WE 70 Install Fish Monitoring Equipment
  • 7 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 4 instances of WE 158 Mark/Tag Animals
  • 7 instances of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 157 Assist With Hyrdoacoustic Sampling At Lake Billy Chinook 01/23/2009
B 162 Analyze & Interpret Hydro Acoustic Data 02/09/2007
C 141 Prepare Report From Hydro Acoustic Data 02/09/2007
D 70 Assess Outmigrant Production For Suttle Lake 02/09/2007
E 157 Monitor & Evaluate Screw Trap At Suttle Lake 02/09/2007
F 158 PIT Tag O. nerka Juveniles From Suttle Lake 02/09/2007
G 162 Analyze Screw Trap Data From Suttle Lake 02/09/2007
H 158 Assist With Mark/Tag O. nerka At Lake Billy Chinook 08/06/2009
I 157 Collect Genetic Samples Of O. nerka At Lake Billy Chinook 01/27/2009
J 157 Assist With Spawning Escapement Estimate Refinement 02/09/2007
K 162 Analyse Genetics Of O. nerka At Lake Billy Chinook 02/09/2007
L 162 Develop Life History Model 02/09/2007
M 191 Coordinate On Sockeye Reintroduction Plan 02/09/2007
N 174 Develop Sockeye Reintroduction Plan 02/09/2007
O 185 Periodic Status Reports for BPA 02/09/2007
P 132 No Annual Progess Report Due 02/09/2007
Q 119 Manage Project 02/09/2007
R 157 Conduct Hyrdoacoustic Sampling At Lake Billy Chinook 03/05/2010
S 162 Analyze & Interpret Hydro Acoustic Data 12/15/2008
T 141 Prepare Report From Hydro Acoustic Data 12/15/2008
U 70 Assess Outmigrant Production For Suttle Lake 12/15/2008
V 157 Monitor & Evaluate Smolt Trap At Suttle Lake 12/15/2008
W 158 PIT Tag O. nerka Juveniles From Suttle Lake 12/15/2008
X 162 Analyze Smolt Trap Data From Suttle Lake 12/15/2008
Y 158 Assist With Mark/Tag O. nerka At Lake Billy Chinook 03/05/2010
Z 157 Collect Genetic Samples Of O. nerka At Lake Billy Chinook 12/15/2008
AA 162 Analyze Genetics Of O. nerka At Lake Billy Chinook 12/15/2008
AB 191 Coordinate On Sockeye Reintroduction Plan 12/15/2008
AC 132 Submit Progress Report For The Period December 2008 to February 2010 12/15/2008
AD 119 Manage Project 12/15/2008
AE 174 Complete the Sockeye Reintroduction Plan 12/15/2008