Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 40847: 1985-038-00 EXP COLVILLE HATCHERY O&M / M&E
Project Number:
Title:
Colville Hatchery Operation and Maintenance (O&M)
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Intermountain Sanpoil 100.00%
Contract Number:
40847
Contract Title:
1985-038-00 EXP COLVILLE HATCHERY O&M / M&E
Contract Continuation:
Previous: Next:
35782: 1985-038-00 EXP. COLVILLE HATCHERY O&M /M&E
  • 45253: 1985-038-00 EXP COLVILLE HATCHERY O&M / M&E
Contract Status:
Closed
Contract Description:
Federal hydropower projects, as well as private power utility systems, have had a devastating impact upon anadromous fish resources that once flourished in the Columbia River and it's tributaries.  Several area have been blocked to anadromous fish by dams, destroying the primary food resource (salmon) for many native people; forcing them to rely heavily upon resident fish to replace these lost resources.  The Colville Tribal Fish Hatchery is an artificial production program that addresses the loss of anadromous fish resources in the Upper Columbia Sub-Region within the "blocked area" created by the construction of Chief Joseph and Grand Coulee Dams.  This project enhances resident fisheries located in the Intermountain and Columbia Cascade Provinces, specifically within the Colville Reservation portion of the Upper Columbia, San Poil and Okanogan Sub-Basins.  The project particularly mitigates for anadromous fish losses through protection/augmentation of resident fish ;populations to enhance fishery potential (i.e., in-place, out-of-kind mitigation).  The Colville Tribal Hatchery (CTH) is located on the northern bank of the Columbia River just down stream of the town of Bridgeport, Washington on land owned by the Colville Tribes.  The minimum production quota for this facility is 22,679 kg (50,000 lbs.) of trout annually.

All fish produced are released into reservation waters, including boundary waters, in an effort to provide a successful subsistence/recreational fishery for Colville Tribal members and provide for a successful non-member sport fishery.

The goal of the project as stated in the 2008 Statement of Work (SOW) was to provide artificial production of fish that will help support and enhance tribal subsistence fisheries and non-tribal recreational sport fisheries within the Colville Reservation, including it's boundary waters.  The majority of the hatchery production provide "carry-over" fisheries rather than "put-and-take" fisheries.

In addition to the work elements, there are six primary goals for 2009:

1.  Complete the shift from coastal rainbow trout production to all redband rainbow trout production.

2.  Continue to improve biosecurity at the hatchery.  Hatchery biosecurity risks were assessed in 2006.  Based on this assessment physical and procedural changes were made in 2007.  The biosecurity assessment will continue and additional changes will be made in 2009.

3.  Improve tagging and marking program.   A number of changes have been made to this program in 2008.  Additional changes will be made in 2009.

4.  Reestablish M&E studies on critical lakes.

5.  Continue monitoring of stocked fish.  In 2007 a program was begun where each group of stocked fish was monitored at the specific stocking locations and up and downstream locations.  This was very successful and will be expanded in FY' 09.

6.  Study the effects of wildfire on Kartar and Coyote Creeks.
Account Type(s):
Expense
Contract Start Date:
12/01/2008
Contract End Date:
11/30/2009
Current Contract Value:
$830,356
Expenditures:
$830,356

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
NEPA review and clearance A: 165. Obtain NEPA review and clearance 11/30/2009 11/30/2009
Purchase net pen fish for planting in reservation lakes. B: 187. Purchase net pen fish 06/15/2009 06/15/2009
Maintenance of Hatchery Facility C: 61. Hatchery Maintenance 11/30/2009 11/30/2009
Maintain on-station Redband Rainbow Broodstock D: 176. Maintain on-station Redband Rainbow Broodstock and produce fish for reservation waters. 11/30/2009 11/30/2009
Produce Eastern Brook Trout for Reservation Waters E: 176. Produce Eastern Brook Trout for Reservation Waters. 11/30/2009 11/30/2009
Produce Lahontan Cutthroat F: 176. Produce Lahontan Cutthroat 11/30/2009 11/30/2009
Local and regional information exchange G: 99. Local and regional information exchange 11/30/2009 11/30/2009
Stream Surveys H: 157. Stream Surveys 11/30/2009 11/30/2009
Biological and Environmental Survey of Reservation Lakes I: 157. Lake Surveys 11/30/2009 11/30/2009
Creel Reservation Stocked Waters J: 157. Roving and voluntary creel of all reservation stocked waters. 11/30/2009 11/30/2009
Differentially mark all hatchery production K: 158. Differentially mark all hatchery production. 11/30/2009 11/30/2009
Project Administration L: 119. Project Administration 11/30/2009 11/30/2009
Progress Report Attached in Pisces M: 132. Submit Progress Report for the period (12/01/07) to (11/30/08) 05/01/2009 05/01/2009

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Cutthroat Trout, Lahontan (O. c. henshawi) (Threatened)
  • 1 instance of WE 176 Produce Hatchery Fish
Trout, Brook (Salvelinus fontinalis)
  • 1 instance of WE 176 Produce Hatchery Fish
Trout, Rainbow (Oncorhynchus mykiss)
  • 1 instance of WE 187 Put and Take Fisheries
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Trout, Interior Redband (O. mykiss gairdnerii)
  • 1 instance of WE 176 Produce Hatchery Fish
  • 1 instance of WE 61 Maintain Artificial Production Facility/Infrastructure
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 158 Mark/Tag Animals

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Obtain NEPA review and clearance 02/09/2007
B 187 Purchase net pen fish 09/15/2009
C 61 Hatchery Maintenance 09/15/2009
D 176 Maintain on-station Redband Rainbow Broodstock and produce fish for reservation waters. 09/15/2009
E 176 Produce Eastern Brook Trout for Reservation Waters. 09/15/2009
F 176 Produce Lahontan Cutthroat 09/15/2009
G 99 Local and regional information exchange 02/09/2007
H 157 Stream Surveys 09/15/2009
I 157 Lake Surveys 09/15/2009
J 157 Roving and voluntary creel of all reservation stocked waters. 09/15/2009
K 158 Differentially mark all hatchery production. 09/15/2009
L 119 Project Administration 02/09/2007
M 132 Submit Progress Report for the period (12/01/07) to (11/30/08) 02/09/2007
N 185 Periodic Status Reports for BPA 02/09/2007