| 35896: 2000-035-00 EXP USFS NEWSOME CREEK WATERSHED RESTORATION |
* Expenditures data includes accruals and are based on data through 31-Oct-2025.
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Environmental compliance documentation submitted to BPA | A: 165. Provide Environmental Compliance Documentation to BPA | 05/31/2009 | 05/31/2009 | |
| Road decommissioning complete | B: 33. Newsome Phase III Road Decommissioning | 11/30/2009 | 11/13/2009 | |
| Road Improvements Complete | C: 38. Newsome Phase III Road Improvement | 11/30/2009 | 11/13/2009 | |
| FY 2010 SOW package and FY 09 accrual estimate | D: 119. Management, Coordination and Communication | 09/18/2009 | 11/13/2009 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Chinook (O. tshawytscha) - Snake River Spring/Summer (not listed) |
|
| Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
| Trout, Bull (S. confluentus) (Threatened) |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 165 | Provide Environmental Compliance Documentation to BPA | 02/09/2007 | ||||||
| B | 33 | Newsome Phase III Road Decommissioning | 02/15/2007 | ||||||
| C | 38 | Newsome Phase III Road Improvement | 02/15/2007 | ||||||
| D | 119 | Management, Coordination and Communication | 02/09/2007 | ||||||
| E | 132 | Progress (Annual) Report Not Required | 02/09/2007 | ||||||
| F | 185 | Periodic Status Reports for BPA | 02/09/2007 |