| Province | Subbasin | % |
|---|---|---|
| Columbia Cascade | Columbia Upper Middle | 100.00% |
| Previous: | Next: |
|---|---|
| n/a |
|
* Expenditures data includes accruals and are based on data through 30-Nov-2025.
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Produce environmental clearances for the project. | A: 165. Obtain environmental clearances for project | 04/15/2009 | 04/15/2009 | |
| Rear Captive Brood | B: 63. Rear Captive Brood | 03/14/2010 | 03/31/2010 | |
| Collect Field Data | C: 157. Collect Field Data | 03/14/2010 | 03/31/2010 | |
| Feasibility of White Sturgeon Culture for use in Restoration/ Mitigation to Mid-Columbia River | D: 176. White Sturgeon Restoration/ Mitigation to Mid-Columbia River | 03/14/2010 | 03/31/2010 | |
| Funding Package - Submit draft to COTR | E: 119. Manage and Administer project | 12/15/2009 | 12/15/2009 | |
| Workshop Participation | H: 189. Workshop Participation | 12/31/2009 | 12/02/2009 | |
| Draft Strategic Plan Review & Comment | I: 174. Draft Strategic Plan Review & Comment | 11/30/2009 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Sturgeon, White (A. transmontanus) - Lower Columbia River |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 165 | Obtain environmental clearances for project | 02/09/2007 | ||||||
| B | 63 | Rear Captive Brood | 04/17/2009 | ||||||
| C | 157 | Collect Field Data | 02/09/2007 | ||||||
| D | 176 | White Sturgeon Restoration/ Mitigation to Mid-Columbia River | 04/17/2009 | ||||||
| E | 119 | Manage and Administer project | 02/09/2007 | ||||||
| F | 185 | Periodic Status Reports for BPA | 02/09/2007 | ||||||
| G | 132 | Begin Preparing Progress Report for the period Jan 2009 to Dec 2009 | 02/09/2007 | ||||||
| H | 189 | Workshop Participation | 02/09/2007 | ||||||
| I | 174 | Draft Strategic Plan Review & Comment | 02/09/2007 |