Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 41827: 199000501 EXP UMATILLA RIVER STEELHEAD RADIO TRACKING-NMFS
Project Number:
Title:
Umatilla Basin Natural Production Monitoring and Evaluation (M&E)
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Umatilla 100.00%
Contract Number:
41827
Contract Title:
199000501 EXP UMATILLA RIVER STEELHEAD RADIO TRACKING-NMFS
Contract Continuation:
Previous: Next:
n/a
  • 46273 REL 2: 199000501 EXP UMATILLA RIVER STEELHEAD RADIO TRACKING-NMFS
Contract Status:
Closed
Contract Description:
This contract is specifically designed for National Oceanic and Atmospheric Adminstration (NOAA) personnel in the National Marine Fisheries Service (NMFS) to work collaboratively with the CTUIR fisheries monitoring and evaluation staff in the design, implementation, data collation, and reporting of radio tagged steelhead in the Umatilla River.  This project's field work will be minimal but will include some tagging at Three Mile Dam and site visits to each diversion to ensure a good understanding of the research design, methods and particulars so that NMFS can assist CTUIR in collating and summarizing telemetry data.

Upstream migration and passage of summer steelhead in the Umatilla River past potential passage impediments created by irrigation diversions is a critical uncertainty in the basin that affects how managers operate and monitor passage facilities and fish passage flows in the Umatilla River. There are also considerable uncertainties regarding the spawning location of hatchery origin spawners in the headwaters and mainstem reaches of the river basin.  Radio telemetry methods will be used to evaluate both passage and spawner distribution of hatchery and wild origin endemic summer steelhead returning to the Umatilla River.  Steelhead will be captured and tagged at Three Mile Falls dam and released back into the river.  Mobile tracking and fixed site receivers at each diversion dam and major tributary will be used to document passage timing, delays, and impediments.  Tagged steelhead that pass the dams will me radio tracked to their spawning location which will be recorded with GPS equipment and mapped in a GIS layer.
Account Type(s):
Expense
Contract Start Date:
04/01/2009
Contract End Date:
03/31/2010
Current Contract Value:
$20,000
Expenditures:
$20,000

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Obtain Valid ESA Permits and Submit Annual Permit Reports B: 165. Submit Annual ESA Permit Reports and Permit Applications (CTUIR) 01/29/2010 01/29/2010
Funding Package - Submit draft to COTR C: 119. Project Management for Data Collation of CTUIR Telemetry Study 01/04/2010 01/20/2010
Assist CTUIR with steelhead and salmon passage and spawning distribution evaluations D: 157. Assist CTUIR with Adult Salmon and Steelhead Passage Evaluations 03/31/2010 03/31/2010
Receive, maintain, organize and collate CTUIR's radio tag data E: 160. Manage CTUIR's Radio Telemetry Data 03/31/2010 03/31/2010
Attach Progress Report in Pisces F: 132. Annual Progress Report (March 2009 to Feb 2010) 02/08/2010

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (Oncorhynchus tshawytscha) - All Populations
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 02/09/2007
B 165 Submit Annual ESA Permit Reports and Permit Applications (CTUIR) 02/09/2007
C 119 Project Management for Data Collation of CTUIR Telemetry Study 02/09/2007
D 157 Assist CTUIR with Adult Salmon and Steelhead Passage Evaluations 03/13/2009
E 160 Manage CTUIR's Radio Telemetry Data 02/09/2007
F 132 Annual Progress Report (March 2009 to Feb 2010) 02/09/2007