Contract 42316: 2008-469-00 EXP YKFP - NELSON SPRINGS
Project Number:
Title:
Nelson Springs Design and Construction-Yakima/Klickitat Fisheries Project (YKFP)
Stage:
Closed
Area:
Province Subbasin %
Columbia Plateau Yakima 100.00%
Contract Number:
42316
Contract Title:
2008-469-00 EXP YKFP - NELSON SPRINGS
Contract Continuation:
Previous: Next:
n/a
Contract Status:
History
Contract Description:
This proposal is to support the design and construction of replacement YKFP M&E facilities at Nelson Springs, WA
Construction Management requires awarding sub contracts for the construction and installation of M&E Office Complex Facility at Nelson Springs.  
This will be a modular M & E Office Complex, including a parking lot.  
YN will coordinate and seek bids for a well, sewer system, electrical requirements, site preparation, bullpen fencing, IT infrastructure, facility demolition, and storage.

BPA has requested that we integrage the Leadership in Energy and Environmental Design (LEED) Green Building Rating System standards into the construction of the Nelson Springs Complex.  YN and BPA will coordinate on exactly what conservation measures are reasonable and prudent for this building site.  The LEED rating system encourages and accelerates global adoption of sustainable green building and development practices through the creation and implementation of universally understood  and accepted tools and performance criteria.  LEED is a third-party certification program and the nationally accepted benchmark for the design, construction and operation of high performance green buildings. LEED gives building owners and operators the tools they need to have an immediate and measurable impact on their buildings’ performance. LEED promotes a whole-building approach to sustainability by recognizing performance in five key areas of human and environmental health: sustainable site development, water savings, energy efficiency, materials selection and indoor environmental quality.
Account Type(s):
Expense
Contract Start Date:
03/01/2009
Contract End Date:
09/30/2012
Current Contract Value:
$922,531
Expenditures:
$922,531

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Shirley Alvarado Yakama Confederated Tribes Yes Interested Party shirley_alvarado@yakama.com (509) 865-5121x6304
Israel Duran Bonneville Power Administration Yes Env. Compliance Lead induran@bpa.gov (503) 230-3967
Dave Fast Yakama Confederated Tribes No Contract Manager fast@yakama.com (509) 966-5291
Andre L'Heureux Bonneville Power Administration Yes COR allheureux@bpa.gov (503) 230-4482
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
John Marvin Yakama Confederated Tribes Yes Technical Contact marj@yakamafish-nsn.gov (509) 966-7406
Michael Mayer Bonneville Power Administration No Interested Party msmayer@bpa.gov (503) 230-7692
Khanida Mote Bonneville Power Administration Yes Contracting Officer kpmote@bpa.gov (503) 230-4599
Mel Sampson Yakama Confederated Tribes Yes Supervisor mel@yakama.com (509) 865-5121x6303
Adrienne Wilson Yakama Confederated Tribes Yes Administrative Contact Adrienne_Wilson@Yakama.com (509) 865-5121x6306


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Obtain acceptable Environmental Compliance Document B: 165. M & E Complex NEPA Compliance 06/30/2011 10/31/2010
Develop Design Plans for Replacement M & E Modular Office Building C: 175. Plan & Design Nelson Springs M & E Modular Replacement Facility 10/15/2010 05/31/2010
Coordination and Oversight D: 119. Overall oversight of all work elements 09/30/2012 09/30/2012
Monitoring & Evaluation Complex E: 100. M & E Complex-Utilities & Operational Support Requirements 12/31/2011 12/31/2011
Nelson Springs M&E Office Complex F: 171. M&E Complex - Implement Construction Activities 09/30/2012 09/30/2012
Remove UST J: 98. Remove UST at Nelson Springs Construction Site 08/26/2011 09/30/2011

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 1 instance of WE 98 Other
  • 1 instance of WE 175 Produce Design
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 1 instance of WE 171 Build, Modify, and/or Refurbish Artificial Production Facility
Chinook (O. tshawytscha) - Upper Columbia River Summer/Fall ESU
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 171 Build, Modify, and/or Refurbish Artificial Production Facility
  • 1 instance of WE 100 Construction Management
Coho (Oncorhynchus kisutch) - Lower Columbia River ESU (Threatened)
  • 1 instance of WE 171 Build, Modify, and/or Refurbish Artificial Production Facility
Coho (O. kisutch) - Unspecified Population
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 100 Construction Management
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 02/09/2007
B 165 M & E Complex NEPA Compliance 02/09/2007
C 175 Plan & Design Nelson Springs M & E Modular Replacement Facility 02/09/2007
D 119 Overall oversight of all work elements 02/09/2007
E 100 M & E Complex-Utilities & Operational Support Requirements 02/09/2007
F 171 M&E Complex - Implement Construction Activities 10/31/2010
G 132 No Annual Report is Required 02/09/2007
H 40 N/A - WE is canceled
I 92 N/A - WE is canceled
J 98 Remove UST at Nelson Springs Construction Site 08/05/2011