Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 43095: 2000-001-00 EXP OMAK CREEK ANADROMOUS FISH HABITAT AND PASSAGE
Project Number:
Title:
Omak Creek Anadromous Fish Habitat and Passage
Stage:
Closed
Area:
Province Subbasin %
Columbia Cascade Okanogan 100.00%
Contract Number:
43095
Contract Title:
2000-001-00 EXP OMAK CREEK ANADROMOUS FISH HABITAT AND PASSAGE
Contract Continuation:
Previous: Next:
37147: 2000-001-00 EXP OMAK CRK ANAD FISH HABITAT & PASSAGE
  • 48457: 200000100 EXP OMAK CREEK ANADROMOUS FISH HABITAT AND PASSAGE
Contract Status:
History
Contract Description:
Project title:  Improvement of Anadromous Fish Habitat and Passage in Omak Creek
Project number:  2000-001-00

Technical Contact:  Rhonda Dasher, Anadromous Fisheries Biologist 1
Colville Confederated Tribes, Fish and Wildlife Department
P.O. Box 150, Nespelem, WA 99155
(509) 422-7439
rhonda.dasher@colvilletribes.com

Contracting Contact:  Colette Adolph, Contracting Specialist
Colville Confederated Tribes, Fish and Wildlife Department
P.O. Box 150, Nespelem, WA 99155
(509) 634-2126
Colette.adolph@colvilletribes.com

Project goal:  Improve habitat conditions in Omak Creek to allow for a self-sustaining steelhead population.

Location: Omak Creek watershed, located wholly within the Colville Reservation boundaries.

Background:  This project is directed towards addressing the resource problems identified in the Omak Creek Watershed Plan/Environmental Assessment (NRCS 1995).  The implementation of this project as well as projects funded through a variety of agencies (i.e. Bureau of Indian Affairs – President’s program, Salmon Recovery Funding Board, Pacific Coastal Salmon Recovery Fund, etc.) were based on recommendations from the watershed plan. Projects that are identified in the Omak Creek Watershed Plan/Environmental Assessment have been cost-shared between the Colville Confederated Tribe and the Natural Resource Conservation Service (NRCS). There was a gap in funding available for 2006-07 fiscal year. We are applying for EQUIP money that will be available in 2008-09. Since a federally listed threatened species (summer steelhead) exists within Omak Creek, regulatory approval is required for any and all proposed work that may affect the habitat or the threatened species.

This year, under project 2000-001-00, watershed rehabilitation practices will continue throughout the Omak Creek basin.  The procedure to implement these practices begins by conducting habitat condition inventories within sub-watersheds (i.e. Stapaloop Creek, Camp-seven Creek).  Resource problems are identified during the surveys that may be a result of poor livestock management (loss of riparian vegetation, hoof shear, etc.), damaged or impassable culverts or excessive amounts of sediment delivered from logging roads.  An implementation strategy is developed to address each problem identified during the surveys.  The implementation strategy is developed within a multi-disciplinary team; the Omak Creek Watershed Technical Advisory Group (TAG).  Disciplines represented on this TAG include Range, Fish & Wildlife, Botany, Cultural Resources, and Forestry.  Strategies developed include but are not limited to such techniques as installing instream-structures (i.e. inverted vortex weirs and j-hook veins), planting riparian vegetation, re-contouring vertical cut-banks, installing fences to exclude livestock from sensitive areas, constructing hardened-rock crossings to minimize damage to stream banks from livestock, obliterating road beds near streams to reduce sediment delivered to the stream channel.  Once a “best strategy” is developed for the area, meetings with user groups, primarily ranchers and loggers are conducted to get input and support for the techniques and strategies proposed to be implemented.  Often these meetings provide an opportunity for the user groups to assist in the planning and implementation of restoration practices such as timing of livestock grazing, grazing strategies (rest-rotation, etc.) road obliteration and incorporation of drainage techniques (i.e. waterbars, broad-based dips, out-sloped roads, etc.).

Initially, rehabilitation efforts originating from the Omak Creek Watershed Plan have focused on providing access for anadromous fish and reducing water temperatures, particularly in the lower reaches of Omak Creek.  With those factors addressed, the emphasis for restoration activities have been directed towards reducing fine sediment delivered to surface waters.  During this BPA contract year, tasks are directed towards minimizing both acute and chronic sediment inputs to Omak Creek and connected tributaries. While developing strategies for 2008, the TAG group considered ISRP comments made during project review for 2007-09. The strategy for 2008-09 involves concentrated projects in areas identified as chronically disturbed. These areas are considered a substantial risk for contributing high sediment loads to the watershed.

Some of the work described in this SOW was described in the narrative rather than the work elements in the proposal to NPCC.  They are also all described as action items in the Okanogan Watershed Limited Factors Analysis and the Okanogan Subbasin Management Plan, and called out in the proposal for addressing (section C of the Narrative).  BPA review by COTR and manager has agreed these actions fit into the intent and purpose of the original proposal.

Efforts will include but not be limited to: installation of exclusionary fencing to protect established riparian areas from degradation by livestock, re-routing of roads away from creeks, removing under sized culverts and grading bank, abandoning segments of road next to creeks, recontouring road and adding waterbars and cross-drains when needed. Seeding/mulching areas of disturbed ground, and planting native riparian vegetation along the stream banks of Omak Creek on the newly acquired property commonly referred to as the Moomaw property .  
Results from monitoring and evaluation will direct future efforts towards the most effective rehabilitation techniques in Omak Creek.  It is expected that the results from this project as well as others (i.e. The Presidents Grant, Pacific Coastal Salmon Recovery Fund, Salmon Recovery Fund, etc.) will result in a self-sustaining population of summer steelhead.  This stock may be utilized to develop a more adapted steelhead stock for the Okanogan River Basin, as described in the BPA 2007-09 proposal #200721200. Current strategies for Omak Creek have been revised due to reduced funding by BPA for 2007-09. Instead of focusing on replacing large culverts that are at risk of failure we have shifted focus to smaller scale projects. We are combining efforts and funds of Range, Forestry, Fish & Wildlife, and NRCS to reduce sediment load in Omak Creek and improve habitat.

Members of the TAG group are working collectively to acquire additional grant money in order to expand existing efforts in the Omak Creek Drainage. As new funds become available, money will be combined with BPA funds and projects will be expanded to include replacement of large culverts, updated watershed assessments, and land acquisition to protect springs and seeps that provide coldwater refugia to fish in Omak Creek.
Account Type(s):
Expense
Contract Start Date:
02/01/2009
Contract End Date:
03/31/2010
Current Contract Value:
$503,964
Expenditures:
$503,964

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Colette Adolph Colville Confederated Tribes Yes Administrative Contact colette.adolph@colvilletribes.com (509) 422-5652
Eleanor Bosman-Clark Colville Confederated Tribes No eleanor.bosman-clark@colvilletribes.com (509) 422-7418
Rhonda Dasher Colville Confederated Tribes Yes Contract Manager rhonda.dasher@colvilletribes.com (509) 422-7439
Chris Fisher Colville Confederated Tribes No Supervisor chris.fisher@colvilletribes.com (509) 422-7427
Billy Gunn Colville Confederated Tribes Yes Administrative Contact billy.gunn@colvilletribes.com (509) 422-7740
Keith Kistler Colville Confederated Tribes No Technical Contact keith.kistler@colvilletribes.com (509) 422-7429
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Terri Mail Colville Confederated Tribes No Administrative Contact terri.mail@colvilletribes.com (509) 634-2124
Cindy McCartney Colville Confederated Tribes No Administrative Contact cindy.mccartney@colvilletribes.com (509) 634-2112
Jennifer McKim Colville Confederated Tribes No Interested Party jennifer.mckim@colvilletribes.com (509) 422-7418
Michelle O'Malley Bonneville Power Administration No Interested Party mmomalley@bpa.gov (503) 230-5138
Jenna Peterson Bonneville Power Administration Yes Env. Compliance Lead jepeterson@bpa.gov (503) 230-3018
David Roberts Bonneville Power Administration Yes COR daroberts@bpa.gov (503) 230-4511
Norma Sanchez Colville Confederated Tribes No Administrative Contact norma.sanchez@colvilletribes.com (509) 634-2109
Tom Sargent Colville Confederated Tribes No Interested Party tom.sargent@colvilletribes.com (509) 634-2853
Kimberly Upham Bonneville Power Administration Yes Interested Party kaupham@bpa.gov (503) 230-3196
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Written strategy to address identified problems (in annual report) B: 114. Identify areas of poor land management practices and develop implementation strategy 12/28/2009 12/28/2009
Documentation and assistance to support BPA's Environmental Compliance Group C: 165. Ensure all work identified in this SOW complies with environmental regulations 11/28/2009 11/28/2009
Project management activities D: 119. Project Management and Administration 03/31/2010 03/31/2010
Field testing the fish module for the OBMEP database E: 160. Link PTAGIS database to OBMEP database and field test 01/29/2010 01/29/2010
Undersized culvert replaced with appropriately sized culvert F: 184. Replace culvert in Upper Omak Creek (UO 11) 09/30/2009
Undersized culvert replaced with appropriately sized culvert G: 184. Replace undersized culvert in Upper Omak Creek (UO 12) 09/30/2009
Undersized culvert replaced with appropriately sized culvet H: 184. Replace undersized culvert in Upper Omak Creek (UO 13) 09/30/2009
Undersized culvert replaced with appropriately sized culvert I: 184. Replace undersized culvert in Upper Omak Creek (UO 5) 09/30/2009
replace culvert in upper Omak Creek watershed J: 184. Replace undersized culvert in Upper Omak Creek (UO 7) 09/30/2009
Remove culvert in Upper Omak Creek K: 184. Replace undersized culvert in Upper Omak Creek (UO 9) 09/30/2009
Inspect & repair livestock exclusion fence along various tributaries to Omak Creek L: 186. Maintain existing exclusion fence along various tributaries to Omak Creek 09/30/2009 09/30/2009
Replace two culverts, construct driving dips M: 184. Replace two culverts construct road dips in Clark Creek Drainage (C-1, C-2) 10/15/2009 11/13/2009
750' of road abandoned in the Clark Creek drainage N: 33. Abandon 750' of road in the Clark Creek Drainage (C-3) 09/30/2009 11/13/2009
Three undersized culverts replaced with appropriately sized culverts and driving dips installed O: 184. Replace three culverts, install driving dips-Camp 7 Creek (CS-1, CS-2, CS-3) 09/30/2009
Driving dips installed on approaches to culvert in the Rattlesnake drainage. P: 38. Drain dips to culvert crossing Rattlesnake Drainage 09/30/2009
Gravel approaches to culvert replacement in Dutch Anderson Drainage Q: 38. Gravel approaches to culvert replacement Dutch Anderson 09/30/2009 09/30/2009
Replace culvert in Dutch Anderson Drainage R: 184. Replace culvert Dutch Anderson Drainage 09/30/2009
Replace undersized culvert in the Dutch Anderson Drainage S: 184. Replace culvert#2 Dutch Anderson Drainage 09/30/2009
Replace undersized culvert in the Dutch Anderson Drainage T: 184. Replace culvert #3 in the Dutch Anderson Drainage 09/30/2009
Inspect & maintain culverts to avoid washout U: 186. Monitor culverts during high flow periods, remove accumulated debris 06/10/2009 06/10/2009
Replace undersized culvert with bridge span V: 184. Replace Marchand Culvert with Bridge 09/30/2009 09/30/2009
Replace undersized culvert with bridge span W: 184. Replace Sam culvert with Bridge 09/30/2009 09/30/2009
Install video weir above Mission Falls X: 70. Install video weir above Mission Falls 07/08/2009 07/08/2009
Install PIT tag detector above Mission Falls and upgrade reader at mouth of Omak Creek. Y: 70. Upgrade existing PIT tag equipment 07/16/2009 07/16/2009
Remove boulders from pool, rearrange boulders and add woody debris Z: 29. Remove boulders from pool and add woody debris 09/30/2009 09/25/2009
Plant native riparian vegetation along impacted areas of Omak Creek (Moomaw property) AA: 47. Plant native riparian vegetation along impacted areas 10/30/2009 10/30/2009
Maintain riparian plants that were planted along impacted sections of Omak Creek AB: 22. Water, weed and fertilize riparian plants 09/24/2009 09/24/2009
Riparian protection Fencing AC: 40. Install Riparian fencing along Omak Creek 08/28/2009 08/28/2009
Management plan for acquired property AD: 174. Produce management plan for 1 newly-acquired properties 11/16/2009 03/31/2010
Pre-acquisition activities for land purchases AE: 172. Land acquisition activities 01/29/2010
Progress Report for the period February 1, 2008 to January 31, 2009 AF: 132. Produce annual report for Feb 2009 - Jan 2010 12/16/2009
develop existing community wells to minimize withdrawals from Omak Creek AG: 34. Assess and develop alternative community wells on Omak Creek 11/30/2009
Develop community wells to minimize withdrawals from Omak Creek AH: 82. Develop community wells in priority areas to decrease withdrawals from Omak Creek 03/31/2010
Development and distribution of education materials regarding conservation, habitat, water resources AI: 99. Develop and distribute critical information regarding resources in Omak Creek Watershed 03/31/2010 12/31/2009
Attach Progress Report in Pisces AJ: 132. Submit Progress Report for the period (2/1/08 to 1/31/09) 07/17/2009 07/17/2009

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 1 instance of WE 34 Develop Alternative Water Source
  • 1 instance of WE 82 Install Well
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 1 instance of WE 22 Maintain Vegetation
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 33 Decommission Road/Relocate Road
  • 1 instance of WE 34 Develop Alternative Water Source
  • 2 instances of WE 38 Improve Road for Instream Habitat Benefits
  • 1 instance of WE 40 Install Fence
  • 1 instance of WE 47 Plant Vegetation
  • 13 instances of WE 184 Install Fish Passage Structure
  • 1 instance of WE 174 Produce Plan
  • 2 instances of WE 70 Install Fish Monitoring Equipment
  • 1 instance of WE 82 Install Well

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 02/09/2007
B 114 Identify areas of poor land management practices and develop implementation strategy 02/09/2007
C 165 Ensure all work identified in this SOW complies with environmental regulations 02/09/2007
D 119 Project Management and Administration 02/09/2007
E 160 Link PTAGIS database to OBMEP database and field test 02/09/2007
F 184 Replace culvert in Upper Omak Creek (UO 11)
G 184 Replace undersized culvert in Upper Omak Creek (UO 12)
H 184 Replace undersized culvert in Upper Omak Creek (UO 13) 02/18/2010
I 184 Replace undersized culvert in Upper Omak Creek (UO 5)
J 184 Replace undersized culvert in Upper Omak Creek (UO 7)
K 184 Replace undersized culvert in Upper Omak Creek (UO 9)
L 186 Maintain existing exclusion fence along various tributaries to Omak Creek 02/09/2007
M 184 Replace two culverts construct road dips in Clark Creek Drainage (C-1, C-2) 07/30/2009
N 33 Abandon 750' of road in the Clark Creek Drainage (C-3)
O 184 Replace three culverts, install driving dips-Camp 7 Creek (CS-1, CS-2, CS-3)
P 38 Drain dips to culvert crossing Rattlesnake Drainage
Q 38 Gravel approaches to culvert replacement Dutch Anderson
R 184 Replace culvert Dutch Anderson Drainage
S 184 Replace culvert#2 Dutch Anderson Drainage
T 184 Replace culvert #3 in the Dutch Anderson Drainage
U 186 Monitor culverts during high flow periods, remove accumulated debris 02/09/2007
V 184 Replace Marchand Culvert with Bridge 03/12/2010
W 184 Replace Sam culvert with Bridge 03/12/2010
X 70 Install video weir above Mission Falls 08/25/2009
Y 70 Upgrade existing PIT tag equipment 02/09/2007
Z 29 Remove boulders from pool and add woody debris
AA 47 Plant native riparian vegetation along impacted areas 11/02/2009
AB 22 Water, weed and fertilize riparian plants 02/09/2007
AC 40 Install Riparian fencing along Omak Creek 11/02/2009
AD 174 Produce management plan for 1 newly-acquired properties 02/09/2007
AE 172 Land acquisition activities 02/09/2007
AF 132 Produce annual report for Feb 2009 - Jan 2010 02/09/2007
AG 34 Assess and develop alternative community wells on Omak Creek 02/09/2007
AH 82 Develop community wells in priority areas to decrease withdrawals from Omak Creek 02/09/2007
AI 99 Develop and distribute critical information regarding resources in Omak Creek Watershed 02/09/2007
AJ 132 Submit Progress Report for the period (2/1/08 to 1/31/09) 02/09/2007