Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 44446: 2008-906-00 EXP CRYSTAL SPRINGS PLANNING AND O&M
Project Number:
Title:
Crystal Springs Planning and Operations/Maintenance
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Upper Snake Snake Upper 100.00%
Contract Number:
44446
Contract Title:
2008-906-00 EXP CRYSTAL SPRINGS PLANNING AND O&M
Contract Continuation:
Previous: Next:
n/a
  • 50777: 2008-906-00 EXP CRYSTAL SPRINGS PLANNING AND O&M
Contract Status:
Closed
Contract Description:
FY 10 funding is proposed to be used for completing Step 1 of the Council's 3-Step process, complete a hatchery genetics management plan, produce environmental compliance documentation and perform routine administration of the contract.
Account Type(s):
Expense
Contract Start Date:
10/01/2009
Contract End Date:
12/31/2010
Current Contract Value:
$131,298
Expenditures:
$131,298

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Chad Colter Shoshone-Bannock Tribes Yes Supervisor ccolter@sbtribes.com (208) 239-4553
Joe Deherrera Bonneville Power Administration Yes COR jldeherrera@bpa.gov (503) 230-3442
Israel Duran Bonneville Power Administration No Env. Compliance Lead induran@bpa.gov (503) 230-3967
Paul Krueger Bonneville Power Administration Yes F&W Approver pqkrueger@bpa.gov (503) 230-5723
Hunter Osborne Shoshone-Bannock Tribes Yes Technical Contact hosborne@sbtribes.com (208) 239-4564
Daniel Stone Shoshone-Bannock Tribes Yes Contract Manager dstone@sbtribes.com (208) 239-4555
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605
Shannell Ward Shoshone-Bannock Tribes Yes Administrative Contact shannell.ward@sbtribes.com (208) 478-3821
Nancy Weintraub Bonneville Power Administration Yes Interested Party nhweintraub@bpa.gov (503) 230-5373


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Complete Step 1 B: 168. Complete Step 1 12/31/2010
Final Hatchery Genetics Management Plan C: 174. Produce Hatchery Genetics Management Plan 12/31/2010
Collect baseline data for hatchery and satellite facility site. D: 157. Collect baseline environmental data for hatchery construction/design 12/31/2010
Funding Package - Submit draft to COTR E: 119. Routine contract administration 10/29/2010 11/09/2010
Environmental Compliance Documents F: 165. Submit required Environmental Compliance documents 10/31/2010 10/31/2010

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 168 Council 3-step Process: Step 1
Cutthroat Trout, Yellowstone (O. c. bouvieri)
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 168 Council 3-step Process: Step 1

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 02/09/2007
B 168 Complete Step 1 02/09/2007
C 174 Produce Hatchery Genetics Management Plan 02/09/2007
D 157 Collect baseline environmental data for hatchery construction/design 10/08/2009
E 119 Routine contract administration 02/09/2007
F 165 Submit required Environmental Compliance documents 02/09/2007
G 132 This WE and report are unnecessary for this contract (per the COTR) 02/09/2007