Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 45346: 198805315 CAP HOOD RIVER MASTER PLAN STEP III FINAL DESIGN/BUILD
Project Number:
Title:
Hood River Artificial Production-Parkdale
Stage:
Complete
Area:
Province Subbasin %
Columbia Gorge Hood 100.00%
Contract Number:
45346
Contract Title:
198805315 CAP HOOD RIVER MASTER PLAN STEP III FINAL DESIGN/BUILD
Contract Continuation:
Previous: Next:
n/a
Contract Status:
Closed
Contract Description:
This statement of work details activities necessary to complete HRPP interim facility improvements as described in the Revised Hood River Master Plan.

Funds awarded to the CTWSRO will be used to complete construction of a fish ladder, adult trap and acclimation facility on the West Fork Hood River at Moving Falls, maintenance of the Moving Falls grade control structures and
a seasonal fish trapping facility in the East Fork Hood River at Dee Mill.

Tasks to be completed in this contract period include:

1. Complete final design for a fish ladder and adult fish trap around the Moving Falls grade control structures.
2 Construct Moving Falls fish ladder and trapping facility.
3. Construct East Fork Fish trapping facility.
4. Construct Moving Falls acclimation facility.
5. Repair stream grade control structures at Moving Falls.
6 Secure necessary permits for construction of all Moving Falls facilities.
7. Provide project management and construction inspection.
Account Type(s):
Capital
Contract Start Date:
12/15/2009
Contract End Date:
12/31/2014
Current Contract Value:
$3,792,877
Expenditures:
$3,792,877

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
All required environmental and land use permits secured. A: 165. Produce environmental compliance documentation and land use permits 09/30/2011 09/30/2011
Construction Management B: 100. West Fork acclimation facility construction administration 09/30/2013 09/30/2013
Moving Falls fish ladder and adult fish trapping facility completed. C: 70. Install an adult fish trapping facility in the West Fork Hood River at Moving Falls. 06/28/2013 06/28/2013
Dee Mill adult fish trapping facility completed. D: 70. Install an adult fish trapping faclity in the East Fork Hood River at Dee Mill. 04/01/2011 03/01/2011
Moving Falls Acclimation Facility Construction Complete E: 171. Construct Moving Falls acclimation facility. 08/29/2014 08/29/2014
Moving Falls grade control structures maintained. F: 184. Maintain Moving Falls grade control structures. 10/14/2011 10/17/2011
Project management and coordination G: 100. Project management and coordination 02/28/2011 02/28/2011
Funding Package - Submit draft to COTR H: 119. Routine contract administration 10/01/2013 09/30/2013
Access agreement secured. I: 172. Secure land use agreement with East Fork trap site landowner. 10/11/2010 07/23/2010
Attach Progress Report in Pisces K: 132. Submit Progress Report for the period January 2010 through Dec. 2013. 12/31/2014
Moving Falls acclimation facility access road and Dee Mill trap site improved. L: 38. Improve access road to Moving Falls acclimation site and Dee Mill Trap Site 10/29/2010 10/29/2010
Final design complete design for HRPP West Fork Hood River facilities. M: 175. Complete final design of new HRPP adult trapping and acclimation facilities. 06/30/2010 06/30/2010
Moving Falls lease agreement secured. N: 92. Complete lease agreement with West Fork landowner. 08/30/2010 08/16/2010
Moving Falls fish ladder / trapping facility final engineering designs complete. O: 175. Produce final engineering designs for Moving Falls fish ladder and adult trapping facility. 04/29/2011 04/29/2011
Moving Falls Acclimation Facility completed. P: 171. Complete construction of Moving Falls Acclimation Facility 11/28/2014 11/28/2014
Moving Falls fish ladder construction complete. Q: 184. Complete construction of Moving Falls fish ladder. 10/31/2014
Moving Falls fish trapping facility completed. R: 70. Complete constructon of Moving Falls fish trapping facility. 10/31/2014

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Lower Columbia River ESU (Threatened)
  • 1 instance of WE 38 Improve Road for Instream Habitat Benefits
  • 2 instances of WE 184 Install Fish Passage Structure
  • 1 instance of WE 92 Lease Land
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 2 instances of WE 175 Produce Design
  • 3 instances of WE 70 Install Fish Monitoring Equipment
  • 2 instances of WE 171 Build, Modify, and/or Refurbish Artificial Production Facility
  • 2 instances of WE 100 Construction Management
Steelhead (O. mykiss) - Lower Columbia River DPS (Threatened)
  • 1 instance of WE 38 Improve Road for Instream Habitat Benefits
  • 2 instances of WE 184 Install Fish Passage Structure
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 2 instances of WE 175 Produce Design
  • 3 instances of WE 70 Install Fish Monitoring Equipment
  • 1 instance of WE 171 Build, Modify, and/or Refurbish Artificial Production Facility
  • 2 instances of WE 100 Construction Management

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Produce environmental compliance documentation and land use permits 11/16/2009
B 100 West Fork acclimation facility construction administration 11/16/2009
C 70 Install an adult fish trapping facility in the West Fork Hood River at Moving Falls. 05/20/2011
D 70 Install an adult fish trapping faclity in the East Fork Hood River at Dee Mill. 01/01/2011
E 171 Construct Moving Falls acclimation facility. 07/26/2010
F 184 Maintain Moving Falls grade control structures. 05/20/2011
G 100 Project management and coordination 11/16/2009
H 119 Routine contract administration 11/16/2009
I 172 Secure land use agreement with East Fork trap site landowner. 11/16/2009
J 185 Periodic Status Reports for BPA 11/16/2009
K 132 Submit Progress Report for the period January 2010 through Dec. 2013. 11/16/2009
L 38 Improve access road to Moving Falls acclimation site and Dee Mill Trap Site 03/09/2010
M 175 Complete final design of new HRPP adult trapping and acclimation facilities. 12/15/2009
N 92 Complete lease agreement with West Fork landowner. 12/15/2009
O 175 Produce final engineering designs for Moving Falls fish ladder and adult trapping facility. 12/15/2009
P 171 Complete construction of Moving Falls Acclimation Facility 01/01/2014
Q 184 Complete construction of Moving Falls fish ladder. 01/02/2014
R 70 Complete constructon of Moving Falls fish trapping facility. 01/01/2014