Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 45839: 200205000 EXP ACCD COUSE-TENMILE HABITAT RESTORATION
Project Number:
Title:
Riparian Buffers on Couse and Tenmile Creeks in Asotin County
Stage:
Closed
Area:
Province Subbasin %
Blue Mountain Asotin 100.00%
Contract Number:
45839
Contract Title:
200205000 EXP ACCD COUSE-TENMILE HABITAT RESTORATION
Contract Continuation:
Previous: Next:
40711: 200205000 EXP ACCD COUSE-TENMILE HABITAT RESTORATION
  • 51043: 200205000 EXP ACCD COUSE-TENMILE HABITAT RESTORATION
Contract Status:
History
Contract Description:
Tenmile Creek is a 42 square mile tributary to the Snake River between Asotin Creek and Grande Ronde, and is almost exclusively held under private ownership.  Wild steelhead and rainbow/redband trout spawning and rearing was documented by WDFW in 2000 and 2002.  36 redds in 15.9 miles in 2000 and 29 redds in 7 miles were also documented in 2001 with an additional 23 resident rainbow/redband trout redds.

Couse Creek is a 24 square mile tributary to the Snake River between Tenmile Creek and the Grande Ronde.  It is also almost exclusively held under private ownership with wild steelhead and rainbow/redband trout spawning and rearing documented by WDFW.

The ACCD, in cooperation with co-managers and local landowners, has identified priority restoration projects and the need to continue to assess salmonid use of streams outside of Asotin Creek.  The CREP Program, independent of BPA, has been successful in working with landowners to protect riparian areas and implement upland BMPs to reduce erosion.  This initiative has gained momentum and is needed to continue to implement the Asotin Subbasin Plan, which has identified priority areas and actions for ESA listed streams within Asotin County.  Couse and Tenmile are protection areas as identified by the Asotin Subbasin Plan.

The objectives within the overall SOW are to continue to identify priority areas and actions for ESA listed streams and fish species within Asotin County and to provide habitat restoration and to further establish, protect and improve overall water quality, riparian areas, and stream habitat.  Additional objectives are to continue to reduce soil erosion and instream sedimentation by stabilizing soils and streambanks with agricultural BMP's and livestock management and exclusion from adjacent streambanks and beds.

Current Work Elements (WE's), such as tree plantings, fencing, no-till direct seeding, and upland erosion and sedimentation control, meet these objectives by utilizing tree plantings and no-till direct seed to further reduce upland erosion and soil loss, sediment loading, and to increase riparian buffer establishment.  Riparian buffers also serve to reduce instream temperatures, provide direct soil stabilization and provide needed stream shading and habitat for fish redds and fry in the stream.  Fencing keeps livestock out of the streams, further protecting the streambanks, reducing in-stream sedimentation and reducing fecal coliform levels.  Sediment basins serve to collect runoff and soil loss before leaving the site and before entering stream systems.  Basins hold the water and soil on-site, allowing the water to percolate back into the soil and overall water table where it is needed.

The ACCD board set a maximum hourly amount a landowner could charge for their time at $20 (less than what a contractor would charge but still showing their time has a value).  This is the same rate that the USDA Farm Service Agency in Asotin County has set for landowner labor.  Other agencies that we work with accept this rate.  Since the district sets hold downs or caps for every practice we provide cost-share for, it ensures the landowners and contractors aren't able to overcharge and abuse the cost-share program.  The cost to BPA is based on documented expenses not to exceed the rates set by the board, so even if a landowner spent an inordinate amount of time on a project they only get reimbursed to the maximum cost-share rates.  At the same time, their expense can come in under the rate which means less cost to BPA.  All projects have to be inspected and approved prior to the landowner receiving cost-share reimbursement for the project, so if it doesn't meet the required spec then we wont pay for it until it is fixed to meet our standards.
Account Type(s):
Expense
Contract Start Date:
01/01/2010
Contract End Date:
12/31/2010
Current Contract Value:
$254,726
Expenditures:
$254,726

* Expenditures data includes accruals and are based on data through 30-Apr-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Keith Ausman Asotin County Conservation District No Supervisor (509) 758-8012
Dawn Boorse Bonneville Power Administration Yes Env. Compliance Lead drboorse@bpa.gov (503) 230-5678
Sandy Cunningham Asotin County Conservation District Yes Contract Manager sandyaccd@cableone.net (509) 758-8012
Andre L'Heureux Bonneville Power Administration Yes COR allheureux@bpa.gov (503) 230-4482
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Megan Stewart Asotin County Conservation District Yes Administrative Contact megan@asotincd.org (509) 552-8100
Kimberly Upham Bonneville Power Administration No kaupham@bpa.gov (503) 230-3196
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Landowner coordination for Habitat Enhancement Projects A: 114. Direct planning & implementation of habitat enhancement projects 12/31/2010 12/31/2010
Project operating smoothly B: 119. Project administration 12/31/2010 12/31/2010
All environmental clearances & permits obtained before work begins C: 165. Obtain environmental compliance for upland and riparian projects 12/31/2010 12/31/2010
Final 2008-2009 Annual Report provided to COTR for posting E: 132. Annual Report for calendar years 2008-2009 08/31/2010 09/30/2010
Data and photos collection complete F: 157. Data and Photos for Reporting 12/31/2010 12/31/2010
Approximately 6000 stems planted G: 47. Plant trees and shrubs 12/31/2010 12/31/2010
Approximately 6000 stems maintained H: 22. Water trees and shrubs 09/30/2010 09/30/2010
Approximately 2 miles fencing installed I: 40. Install fencing-spring/summer 07/31/2010 07/31/2010
Approximately 1 mile fencing installed J: 40. Install fencing-fall 12/31/2010 12/31/2010
Approximately 1,750 acres enrolled in residue management program K: 48. Provide cost-share for residue management 11/30/2010 11/30/2010
Approximately 400 acres converted to grassland L: 47. Practice upland farmland conversion 11/30/2010 11/30/2010
Approximately 10 upland practices installed M: 55. Upland erosion control measures and sedimentation control 12/31/2010 12/31/2010
Approximately 3 water developments installed in spring N: 34. Install Off-site Water Facilities-spring 07/31/2010 07/31/2010
Approximately 3 water developments installed in summer O: 34. Install Off-site Water Facilities-summer 11/15/2010 11/15/2010
Approximately 2 water developments installed P: 34. Install Off-site Water Facilities-fall 12/31/2010 12/31/2010
2 Water Developments rescheduled from 2009 - #2008-37 & #2009-37 Q: 34. Install Off-site Water Facilities - #2008-49 & #2009-37 12/31/2010 12/31/2010

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 22 Maintain Vegetation
  • 4 instances of WE 34 Develop Alternative Water Source
  • 2 instances of WE 40 Install Fence
  • 2 instances of WE 47 Plant Vegetation
  • 1 instance of WE 48 Practice No-till and Conservation Tillage Systems
  • 1 instance of WE 55 Erosion and Sedimentation Control
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 114 Direct planning & implementation of habitat enhancement projects 02/09/2007
B 119 Project administration 02/09/2007
C 165 Obtain environmental compliance for upland and riparian projects 02/09/2007
D 185 Periodic Status Reports for BPA 02/09/2007
E 132 Annual Report for calendar years 2008-2009 02/09/2007
F 157 Data and Photos for Reporting 02/09/2007
G 47 Plant trees and shrubs 12/10/2010
H 22 Water trees and shrubs 01/01/2010
I 40 Install fencing-spring/summer 12/10/2010
J 40 Install fencing-fall 12/14/2010
K 48 Provide cost-share for residue management 12/10/2010
L 47 Practice upland farmland conversion 12/10/2010
M 55 Upland erosion control measures and sedimentation control 12/10/2010
N 34 Install Off-site Water Facilities-spring 12/17/2010
O 34 Install Off-site Water Facilities-summer 12/10/2010
P 34 Install Off-site Water Facilities-fall 12/14/2010
Q 34 Install Off-site Water Facilities - #2008-49 & #2009-37 12/10/2010