| Province | Subbasin | % |
|---|---|---|
| Mountain Snake | Clearwater | 100.00% |
* Expenditures data includes accruals and are based on data through 30-Nov-2025.
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Funding Package - Submit draft to COTR | A: 119. Project management and administration | 11/15/2011 | 11/15/2011 | |
| Environmental Compliance and Consultation Review | B: 165. Environmental Compliance and Consultation Review | 07/29/2011 | 07/29/2011 | |
| Two new habitat restoration site identified | C: 114. Identify and prioritize future projects | 12/30/2011 | 10/28/2011 | |
| Public Outreach and Education | D: 99. Public Outreach and Education | 12/30/2011 | 12/30/2011 | |
| Restoring channel to natural conditions | E: 30. Pine Creek Channel Restoration | 12/30/2011 | 12/30/2011 | |
| Increase Instream Habitat Complexity | F: 29. Pine Creek Channel Restoration | 12/30/2011 | 11/15/2011 | |
| Completed Bid Package & Contractor Hired | G: 188. Pine Creek Channel Restoration and Bridge | 12/30/2011 | 07/29/2011 | |
| Pine Creek Bridge Barrier Removed | H: 85. Pine Creek Bridge on Cedar Ridge Road | 12/30/2011 | 12/16/2011 | |
| Pine Creek re-planted | I: 47. Pine Creek Revegetation | 12/30/2011 | 10/30/2011 | |
| Shea Meadow Restoration Plan | J: 174. Shea Meadows Restoration Plan | 12/30/2011 | ||
| Temperature loggers in the Potlatch River and select tributaries | K: 157. Temperature loggers | 08/31/2011 | 11/15/2011 | |
| Annual Completion Report | L: 132. Annual report for Contract 43702 | 11/19/2010 | 11/19/2010 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 119 | Project management and administration | 07/01/2010 | ||||||
| B | 165 | Environmental Compliance and Consultation Review | 07/01/2010 | ||||||
| C | 114 | Identify and prioritize future projects | 07/01/2010 | ||||||
| D | 99 | Public Outreach and Education | 07/01/2010 | ||||||
| E | 30 | Pine Creek Channel Restoration | |||||||
| F | 29 | Pine Creek Channel Restoration | |||||||
| G | 188 | Pine Creek Channel Restoration and Bridge | |||||||
| H | 85 | Pine Creek Bridge on Cedar Ridge Road | |||||||
| I | 47 | Pine Creek Revegetation | |||||||
| J | 174 | Shea Meadows Restoration Plan | 07/01/2010 | ||||||
| K | 157 | Temperature loggers | 07/01/2010 | ||||||
| L | 132 | Annual report for Contract 43702 | 07/01/2010 | ||||||
| M | 185 | Periodic Status Reports for BPA | 07/01/2010 | ||||||
| N | 132 | Progress report | 09/01/2010 |