Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 49324: 2008-603-00 EXP PAHSIMEROI RIVER HABITAT-CUSTER
Project Number:
Title:
Pahsimeroi River Habitat
BPA PM:
Stage:
Complete
Area:
Province Subbasin %
Mountain Snake Salmon 100.00%
Contract Number:
49324
Contract Title:
2008-603-00 EXP PAHSIMEROI RIVER HABITAT-CUSTER
Contract Continuation:
Previous: Next:
44134: 2008-603-00 EXP PAHSIMEROI RIVER HABITAT-MOA
  • 57289: 2008-603-00 EXP PAHSIMEROI RIVER HABITAT-CUSTER
Contract Status:
Closed
Contract Description:
This project is an expansion of the existing project 2007-268-000 and was identified early in the BPA State of Idaho MOA process as a high priority for inclusion.  Both the IDF&G and the draft NOAAF recovery plans highlight the importance of carrying out habitat actions to assist this key salmon population.

The Pahsimeroi River has a unique population of Snake River Chinook salmon, and in contrast with the Lemhi River and East Fork of the Salmon River watersheds, the salmon population in the Pahsimeroi River is a later migrating summer-run Chinook salmon rather than spring-run. Historically, spawning and rearing habitat was probably supported within the watershed for at least two federally –listed anadromous fish species, spring/summer Chinook salmon, and steelhead. (P. Murphy, 2008)  

The Upper Salmon Watershed Project Technical Team, including IDFG Anadromous Fish Screen Program and Regional Fishery Management has prioritized the lower Pahsimeroi River and its major tributary, Patterson/Big Springs Creek, as SHIPUSS Priority I streams. Those are tributaries and river reaches that have the potential to realize immediate, tangible benefits to fish if recovery efforts are directed toward them. Goals in the lower Pahsimeroi River and Patterson/Big Springs Creek are to enhance migration in both streams by increasing flow regimes and reestablishing habitat connectivity to unused stream reaches. Mechanisms for attaining these goals focus on diversion consolidations and removal/alterations of diversions hindering fish passage. (P. Murphy, 2008)  

At the request of the Idaho Governor’s Office of Species Conservation (OSC) a technical panel with knowledge and expertise of project opportunities within the Pahsimeroi. This team included Paddy Murphy (Fisheries Biologist), Eric Leitzinger, Larry Weeks, Lynn Stratton and Jim Lukins, Idaho Department of Fish and Game, Morgan Case and Helen Herrington, Idaho Department of Water Resources, Mark Olson, Natural Resources Conservation Service, Brian Hamilton, Bureau of Reclamation, Mark Davidson, TNC, Clif Tipton, Bureau of Land Management Fisheries Biologist, Mike Edmondson, OSC and Karma Bragg, Custer Soil and Water Conservation Service. This core team identified the areas of Pahsimeroi with most potential for fisheries enhancement and recovery within the middle Pahsimeroi. Additional support and input is provided by the Custer Soil and Water Conservation District Board of Supervisors. The projects were predominantly in Patterson/Big Springs Creek. Patterson/Big Springs Creek is a very important tributary for spawning and rearing of the unique population of Chinook salmon found in the Pahsimeroi.

Reconnection of Duck Creek, increased flows within Patterson/Big Springs Creek with a focus on the lower five irrigation diversions (PBSC 1-5). This includes flow enhancements on PBSC #1,  #9  and work to close P-13 Diversion. These projects were prioritized as projects that could be implemented within the next eighteen months. Work reflected in this statement of work is for PBSC #1 and PBSC #9 in addition to final work to complete the lower Pahsimeroi Fencing project and willow planting and re-hab on the IDFG property.
Account Type(s):
Expense
Contract Start Date:
10/16/2010
Contract End Date:
04/30/2012
Current Contract Value:
$1,279,682
Expenditures:
$1,279,682

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Obtain or complete Environmental consultation documents and provide to BPA A: 165. Produce EC documents on identified projects 08/01/2011 07/08/2011
Produce Design and/or Specifications B: 175. Produce Design and/or Specifications 08/31/2011 08/19/2011
Install Sprinklers to provide water savings in Patterson/Big Sprigs Creek from POD to Pahsimeroi C: 150. Install irrigation system to provide water conservation on PBSC 1 04/27/2012 04/16/2012
Install irrigation system to allow for the closure of the PBSC #9 Ditch and Diversion D: 150. Install Sprinkler to allow closure of the PBSC #9 Ditch and Diversion 04/27/2012 04/16/2012
Installation of 9800 feet of fence to be completed on the Lower Pahsimeroi E: 40. Install fence on lower Pahsimeroi 09/15/2011 06/30/2011
Maintain and/or re-plant vegetation on IDFG easement property F: 22. Maintain and Continue plantings on IDFG Easement Property 08/31/2011 08/30/2011
Installation of projects yet to be identified and approved. G: 119. Manage and administer projects within this contract 04/30/2012 04/30/2012
Attach Progress Report in Pisces H: 132. Submit Progress Report for the period Oct 10 thru Sept 11 04/13/2012
Remove culverts/passage barriers on Patterson/Big Springs Creek at Hooper Lane i J: 184. Remove culverts/passage barriers on Patterson/Big Springs Creek on Hooper Lane 09/30/2011 09/16/2011
Remove culverts/passage barriers on Patterson/Big Springs Creek Connector Channel at Hooper Lane K: 184. Remove culverts/passage barriers on Patterson/Big Springs Creek Connector Channel on Hooper Lane 09/30/2011 09/16/2011
Remove culverts/passage barriers on Patterson Little Spring Creek at Hooper Lane L: 184. Remove culverts/passage barriers on Patterson Little Spring Creek on Hooper Lane 09/30/2011 09/16/2011
Remove culverts/passage barriers on Pahsimeroi at Hooper Lane M: 184. Remove culverts/passage barriers on Pahsimeroi on Hooper Lane 09/30/2011 09/16/2011
Remove two culverts and replace with bottomless arch bridges. N: 85. Remove two culverts on Muddy Springs and replace with bottomless culverts 09/30/2011 09/02/2011
One day workshop provided by CH2M Hill in cooperation with OSC and USBoR facilitated by IDFG O: 99. Coordinate with Agencies and Contractors to complete a training for In-Stream Work Windows 05/06/2011 04/19/2011

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 22 Maintain Vegetation
  • 1 instance of WE 40 Install Fence
  • 1 instance of WE 85 Remove/Breach Fish Passage Barrier
  • 4 instances of WE 184 Install Fish Passage Structure
  • 1 instance of WE 175 Produce Design
  • 2 instances of WE 150 Install Sprinkler
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 22 Maintain Vegetation
  • 1 instance of WE 40 Install Fence
  • 1 instance of WE 85 Remove/Breach Fish Passage Barrier
  • 4 instances of WE 184 Install Fish Passage Structure
  • 1 instance of WE 175 Produce Design
  • 2 instances of WE 150 Install Sprinkler

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Produce EC documents on identified projects 10/01/2010
B 175 Produce Design and/or Specifications 10/01/2010
C 150 Install irrigation system to provide water conservation on PBSC 1 07/17/2011
D 150 Install Sprinkler to allow closure of the PBSC #9 Ditch and Diversion 07/17/2011
E 40 Install fence on lower Pahsimeroi 10/01/2010
F 22 Maintain and Continue plantings on IDFG Easement Property 10/01/2010
G 119 Manage and administer projects within this contract 10/01/2010
H 132 Submit Progress Report for the period Oct 10 thru Sept 11 10/01/2010
I 185 Periodic Status Reports for BPA 10/01/2010
J 184 Remove culverts/passage barriers on Patterson/Big Springs Creek on Hooper Lane 07/11/2011
K 184 Remove culverts/passage barriers on Patterson/Big Springs Creek Connector Channel on Hooper Lane 07/11/2011
L 184 Remove culverts/passage barriers on Patterson Little Spring Creek on Hooper Lane 07/11/2011
M 184 Remove culverts/passage barriers on Pahsimeroi on Hooper Lane 07/11/2011
N 85 Remove two culverts on Muddy Springs and replace with bottomless culverts 10/16/2010
O 99 Coordinate with Agencies and Contractors to complete a training for In-Stream Work Windows 10/16/2010