SOW Report
Contract 49325: 2010-004-00 EXP CREST ESTUARY HABITAT RESTORATION
Project Number:
Title:
CREST Estuary Habitat Restoration
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia River Estuary Columbia Estuary 100.00%
Contract Number:
49325
Contract Title:
2010-004-00 EXP CREST ESTUARY HABITAT RESTORATION
Contract Continuation:
Previous: Next:
n/a
  • 53618: 2010-004-00 EXP CREST ESTUARY HABITAT RESTORATION
Contract Status:
Closed
Contract Description:
CREST proposes to implement two restoration projects in 2010 contract period. The Otter Point Restoration Project Phase I will occur between September 1, 2010 and October 15, 2010. A cross dike will be constructed in Phase I, which allows for appropriate settling before it is subject to tidal forces. Secondarily, the site will be prepared for the dike breach in 2011, and channels will be constructed with LWD placed at key locations. Phase II will reconnect 33.5 acres with full tidal influence. Fort Columbia will be constructed between October 15, 2010 and February 1, 2011. A fish passable culvert will be constructed which will restore passage to a 96 acre wetland and facilitate the restoration of at 8-12 acres of tidal estuarine habitat. A pilot channel will provide immediate access to the wetland for juvenile and adult salmonids.

Within this contract, major work elements are directly related to implementation of Otter Point and Fort Columbia. Additional actions focus on community outreach and project development. Projects in development will be reviewed by the Estuary Partnership' s Science Work Group and additionally be subject to review and assignment of survival benefits by the Expert Regional Technical Group. Monitoring will be conducted by CREST biologists to better quantify use and habitat lift for individual project sites.


Updated 11-24-10 - We are prescheduling $135,000 from FY 11 To FY 10 to complete construction at Ft Columbia site and to complete survey work for future restoration sites.

Updated 04-22-11 - Changes are being made with a contract amendment to reflect that new requirements by ACOE require certification both to breach existing dikes and to build new cross dikes.  This work must be done prior to construction for breaching and new cross dike can occur.  The construction phase will now have to occur in the next contract performance period.
Account Type(s):
Expense
Contract Start Date:
07/01/2010
Contract End Date:
06/30/2011
Current Contract Value:
$771,601
Expenditures:
$771,601

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Draft Environmental Compliance Documentation B: 165. Produce EC for projects 06/30/2011 06/30/2011
Funding Package - Submit draft to COTR C: 119. Manage and Administer Projects 04/01/2011 04/01/2011
Attach Progress Report in Pisces D: 132. Submit Progress Report for the period (July 2010) to (June 2011) 06/15/2011 06/30/2011
Newsletters, Presentations, Educational Materials E: 99. Meetings, Newsletters, and Education 06/30/2011 06/30/2011
1-3 Project Memorandums F: 114. Systematically Identify, Prioritize, and Select Projects 06/30/2011 06/30/2011
Project Design G: 175. Placeholder - Subcontract engineering of specific project design elements 06/30/2011 06/30/2011
Construction Management Complete H: 100. Otter Point - Oversee purchasing, contracting, permit compliance of active projects 06/30/2011 06/30/2011
46 Instream Pieces I: 29. Otter Point - Place LWD to Increase Channel Complexity 06/30/2011 06/30/2011
Reconnect 2 tidal channels J: 30. Otter Point - Excavate Historic Channels 06/30/2011 06/30/2011
Changing to technical review rather than construction K: 180. Otter Point - Construct Cross Dike prior to Site Breach 06/30/2011 06/30/2011
Construction Management Complete L: 100. Fort Columbia - Oversee purchasing, contracting, permit compliance of active projects 06/30/2011 03/28/2011
Install 12' by 12' by 80' Concrete Box Culvert M: 184. Fort Columbia - Installation of Fish Passable Culvert 06/30/2011 03/28/2011
300 Feet Tidal Pilot Channel N: 30. Placeholder: Fort Columbia - Excavate Pilot Channel 02/01/2011 02/07/2011
Field Data Generation O: 157. Pre and Post Project Monitoring & Lab Review 06/30/2011 06/30/2011
Input/Share Data P: 159. Participate in Regional Data Rollup Projects 06/30/2011 06/30/2011
Complete required Army Corps Section 408 submittal package and application. Q: 122. Otter Point - Army Corps Section 408 Review for Construction of cross dike 06/30/2011 06/30/2011

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (Oncorhynchus tshawytscha) - All Populations
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 2 instances of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 184 Install Fish Passage Structure
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 159 Transfer/Consolidate Regionally Standardized Data
Chinook (O. tshawytscha) - Lower Columbia River ESU (Threatened)
  • 1 instance of WE 122 Provide Technical Review and Recommendation
Chum (Oncorhynchus keta) - Columbia River ESU (Threatened)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 2 instances of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 184 Install Fish Passage Structure
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 159 Transfer/Consolidate Regionally Standardized Data
Coho (Oncorhynchus kisutch) - Lower Columbia River ESU (Threatened)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 2 instances of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 184 Install Fish Passage Structure
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 159 Transfer/Consolidate Regionally Standardized Data
Coho (O. kisutch) - Unspecified Population
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 2 instances of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 184 Install Fish Passage Structure
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 159 Transfer/Consolidate Regionally Standardized Data
Cutthroat Trout, Coastal (Oncorhynchus clarkii clarkii) - All Anadromous Populations
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 2 instances of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 184 Install Fish Passage Structure
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 159 Transfer/Consolidate Regionally Standardized Data
Sockeye (Oncorhynchus nerka) - All Populations
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 2 instances of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 184 Install Fish Passage Structure
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 159 Transfer/Consolidate Regionally Standardized Data
Steelhead (Oncorhynchus mykiss) - All Populations
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 2 instances of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 184 Install Fish Passage Structure
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 159 Transfer/Consolidate Regionally Standardized Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 07/01/2010
B 165 Produce EC for projects 07/01/2010
C 119 Manage and Administer Projects 07/01/2010
D 132 Submit Progress Report for the period (July 2010) to (June 2011) 07/01/2010
E 99 Meetings, Newsletters, and Education 07/01/2010
F 114 Systematically Identify, Prioritize, and Select Projects 07/01/2010
G 175 Placeholder - Subcontract engineering of specific project design elements 07/01/2010
H 100 Otter Point - Oversee purchasing, contracting, permit compliance of active projects 07/01/2010
I 29 Otter Point - Place LWD to Increase Channel Complexity 07/22/2010
J 30 Otter Point - Excavate Historic Channels 07/22/2010
K 180 Otter Point - Construct Cross Dike prior to Site Breach 08/01/2010
L 100 Fort Columbia - Oversee purchasing, contracting, permit compliance of active projects 07/01/2010
M 184 Fort Columbia - Installation of Fish Passable Culvert 10/28/2010
N 30 Placeholder: Fort Columbia - Excavate Pilot Channel 10/28/2010
O 157 Pre and Post Project Monitoring & Lab Review 07/01/2010
P 159 Participate in Regional Data Rollup Projects 07/01/2010
Q 122 Otter Point - Army Corps Section 408 Review for Construction of cross dike 07/01/2010