Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 49900: 1998-003-00 EXP WILDLIFE MITIGATION/SPOKANE TRIBE
Project Number:
Title:
Wildlife Mitigation/Operations and Maintenance (O&M) for Spokane Tribe Land Acquisitions
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Intermountain Spokane 100.00%
Contract Number:
49900
Contract Title:
1998-003-00 EXP WILDLIFE MITIGATION/SPOKANE TRIBE
Contract Continuation:
Previous: Next:
44999: 1998-003-00 EXP WILDLIFE MITIGATION - SPOKANE TRIBE
  • 59323: 1998-003-00 EXP SPOKANE WILDLIFE MITIGATION AREAS (OPERATIONS)
Contract Status:
Closed
Contract Description:
Performance Work Statement:

The objective of the project is to conduct the daily operation and maintenance of wildlife lands that have been acquired through the Spokane Tribe Wildlife Mitigation Project (1991-062-00), formerly the Blue Creek Winter Range Project, which has acquired a total of 8403.57 acres, as a result of the FY2007 land acquisitions. These lands are being incorporated into this O&M contract with only minimal activities such as fencing and weed control being conducted prior to the completion of the Site Specific Management Plan that will occur within 18 months of acquisition.  All fencing and weed control efforts will be as identified in this SOW.

The project focus is on maintenance of habitat through removal of domestic livestock and restoration efforts (non-BPA funding) on wildlife lands.  Weed control is a significant part of the project.  Many activities such as road maintenance and agricultural activities are used to reduce and control the spread of noxious weed on mitigation lands.  Past management has focused on mechanical control efforts that had minimal success.  Continued efforts will focus more on chemical control with the use of reduced risk herbicides.  The other major activity is fence construction and removal.  With the property base increasing from 1863 acres in FY03 to 8403 acres in FY07 there are large amounts of boundary fences to be repaired and/or installed.  Also a large amount of land is adjacent to existing WMA's, so many fences need to be removed.

Additionally, native grasses are being seeded.  

Project History:

The O&M project began in 1998 with management activities beginning on the initial 1863 acres of land that was purchased on the Spokane Indian Reservation in 1996 through 1998.  The purpose of the Spokane Tribe Wildlife Mitigation Operation & Maintenance project is for the management of wildlife lands that have been purchased through the Tribes Blue Creek Winter Range project.  

Initial activities began with Habitat Evaluation Procedures (HEP) surveys on those properties.  HSI models used for HEP analysis included White-tailed deer, Mule Deer, Yellow warbler (for Riparian forest), Sharp-tailed grouse, Ruffed grouse, and Western Meadowlark (for Mourning dove) for losses which were associated with the construction and inundation of Grand Coulee Dam.  Results of the HEP analysis were then used to help direct the management activities that take place on the Wildlife properties.  Primary activities that have been conducted include, but are not limited too, fencing (removal, construction, and repair), noxious weed control (mechanical), access road maintenance, and site clean-up.  Past enhancement and habitat improvement activities on these land include native grass establishment, native tree & shrub establishment, tree thinning (forest health), riparian/stream channel restoration, and water development.  Funding of enhancement activities through the O&M project has been limited to only a few small scale projects, while large scale enhancements have been funded by the Spokane Tribe of Indians, USDA Natural Resource Conservation Service, and the Northwest Indian Fisheries Commission.

In 2007, the Blue Creek Winter Range Project acquired an additional 3926 acres which now fall under the O&M project.  These new lands will be incorporated into the O&M project with the Site Specific Management Plans updates.


COST-SHARE ACTIVITIES ON WMA's:

The Spokane Tribe of Indians (STOI) and Natural Resource Conservation Service (NRCS) are working together to conduct habitat enhancement activities on riparian and upland habitat of some Wildlife Mitigation Area's.  Enhancements that occur on BPA acquired projects but are funded by non-BPA dollars will be reported on within the Annual Progress Report.


Project Revenue

This project inherited 5 old farm service contracts on properties acquired with BPA money.  These contract values ranged from $67 to 3463 and total $6475 per year in revenue.   This money is put back into the contract in the form of purchased fence materials, herbicides, seed, and miscellaneous supplies/tools; it is reported on a yearly basis in the annual report.
Account Type(s):
Expense
Contract Start Date:
10/01/2010
Contract End Date:
09/30/2012
Current Contract Value:
$790,290
Expenditures:
$790,290

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Candace Bennett Spokane Tribe No Interested Party candaceb@spokanetribe.com (509) 626-4430
Katie Eaton Spokane Tribe Yes Interested Party katiee@spokanetribe.com (509) 626-4404
Jeanne Flett Spokane Tribe No Administrative Contact jeannef@spokanetribe.com (509) 458-6560
Katey Grange Bonneville Power Administration Yes Env. Compliance Lead kcgrange@bpa.gov (503) 230-4047
B.J. Kieffer Spokane Tribe No Supervisor bjk@spokanetribe.com (509) 626-4427
Andre L'Heureux Bonneville Power Administration Yes COR allheureux@bpa.gov (503) 230-4482
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Jenna Peterson Bonneville Power Administration No Interested Party jepeterson@bpa.gov (503) 230-3018
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605
Douglas Wood Spokane Tribe Yes Contract Manager dougw@spokanetribe.com (509) 626-4429


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
FY13-14 SOW package signed by 8/31/12, accrual estimate, accurate invoices, general management. A: 119. FY2011-2012 Budget and Project Management 09/30/2012 09/30/2012
Environmental Compliance & Consultation Review B: 165. NEPA information to BPA for Project Activities 01/31/2012 01/31/2012
Plant 10.0 Acres of Forage/Cover Crops. C: 47. Cottonwood WMA Forage Seeding 09/14/2012 09/06/2012
Seed 20 acres with Forage/Cover Crops. D: 47. Fox Creek WMA Forage Seeding 09/14/2012 06/28/2012
Seed 162 acres with Forage/Cover Crops. E: 47. McCoy Lake Watershed WMA Forage/Weed Control Seeding 09/14/2012 09/14/2012
Seed 20 acres with Forage/Cover Crops. F: 47. Peaks/Wellpinit Mt. WMA Forage Seeding 09/13/2012 09/11/2012
Seed 10 acres with Forage/Cover Crops. G: 47. Tshimikan WMA Forage Seeding 09/17/2012 09/11/2012
Seed 60 acres of native grass. H: 47. McCoy Lake Watershed WMA Native Grass Seeding 12/16/2011 11/10/2011
Invasive/Noxious Weed Control on 500 acres. I: 53. Blue Creek WMA Invasive/Noxious Weed Control 09/30/2012 09/30/2012
Invasive/Noxious Weed Control on 200 acres. J: 53. Cottonwood WMA Invasive/Noxious Weed Control 09/28/2012 09/28/2012
Invasive/Noxious Weed Control on 600 acres. K: 53. Fox Creek WMA Invasive/Noxious Weed Control 09/30/2012 09/30/2012
Invasive/Noxious Weed Control on 1,200 acres. L: 53. McCoy Lake Watershed WMA Invasive/Noxious Weed Control 09/30/2012 09/30/2012
Invasive/Noxious Weed Control on 400 acres. M: 53. Peaks/Wellpinit Mt. WMA Invasive/Noxious Weed Control 09/30/2012 09/30/2012
Invasive/Noxious Weed Control on 100 acres. N: 53. Tshimikan Creek WMA Invasive/Noxious Weed Control 09/30/2012 05/31/2012
Conduct Conifer Thinning on 40 acres. O: 53. WMA Conifer Removal 09/30/2012 09/30/2012
Burn 250 acres to Maintain Wildlife Habitat. P: 53. McCoy Lake Watershed WMA Prescribed Burning 09/30/2012 04/23/2012
8.0 Miles of New Fence. Q: 40. Fox Creek WMA Boundary Fence Installation 09/13/2012 08/31/2012
5.0 Miles of Old Fence Removal R: 27. Wildlife Mitigation Area Fence Removal 09/14/2012 09/14/2012
75.0 Miles of Fence Line Maintained S: 186. WMA Boundary Fence Maintenance 09/30/2012 09/30/2012
Operate and Maintain Irrigation Pivot T: 186. McCoy Lake Watershed WMA Irrigation Operations 09/30/2012 09/30/2012
Place Gravel to Improve Access Road Maintenance. U: 38. WMA Access Road Maintenance 08/31/2012
Maintain 24.0 miles of Access Roads V: 38. Blue Creek WMA Access Roads 09/30/2012 08/28/2012
Maintain 13.0 miles of Access Roads W: 38. Cottonwood WMA Access Roads 09/30/2012 08/28/2012
Maintain 13.0 miles of Access Roads X: 38. Fox Creek WMA Access Roads 09/30/2012 08/28/2012
Maintain 70.0 miles of Access Roads Y: 38. McCoy Lake Watershed WMA Access Roads 09/30/2012 08/28/2012
Maintain 28.0 miles of Access Roads Z: 38. Peaks/Wellpinit Mt. WMA Access Roads 09/30/2012 08/28/2012
Maintain 2.0 miles of Access Roads AA: 38. Tshimikan Creek WMA Access Roads 09/30/2012 08/28/2012
Decommission 1.0 Mile of Road. AB: 33. Fox Creek WMA Road Decommission 09/17/2012 09/27/2012
Decommission 1.0 Mile of Road. AC: 33. McCoy Lake Watershed WMA Road Decommission 09/17/2012 09/27/2012
Attach Annual Report in Pisces AE: 132. Submit Annual Report - FY 11 - Date Range is 10/1/10 to 9/30/11 07/02/2012

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Wildlife
  • 1 instance of WE 27 Remove Debris
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 33 Decommission Road/Relocate Road
  • 7 instances of WE 38 Improve Road for Instream Habitat Benefits
  • 1 instance of WE 40 Install Fence
  • 6 instances of WE 47 Plant Vegetation
  • 8 instances of WE 53 Remove Vegetation

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 FY2011-2012 Budget and Project Management 10/01/2011
B 165 NEPA information to BPA for Project Activities 10/01/2011
C 47 Cottonwood WMA Forage Seeding 10/01/2011
D 47 Fox Creek WMA Forage Seeding 10/01/2011
E 47 McCoy Lake Watershed WMA Forage/Weed Control Seeding 10/01/2011
F 47 Peaks/Wellpinit Mt. WMA Forage Seeding 10/01/2011
G 47 Tshimikan WMA Forage Seeding 10/01/2011
H 47 McCoy Lake Watershed WMA Native Grass Seeding 10/01/2011
I 53 Blue Creek WMA Invasive/Noxious Weed Control 10/01/2011
J 53 Cottonwood WMA Invasive/Noxious Weed Control 10/01/2011
K 53 Fox Creek WMA Invasive/Noxious Weed Control 10/01/2011
L 53 McCoy Lake Watershed WMA Invasive/Noxious Weed Control 10/01/2011
M 53 Peaks/Wellpinit Mt. WMA Invasive/Noxious Weed Control 10/01/2011
N 53 Tshimikan Creek WMA Invasive/Noxious Weed Control 10/01/2011
O 53 WMA Conifer Removal 10/01/2011
P 53 McCoy Lake Watershed WMA Prescribed Burning 07/07/2011
Q 40 Fox Creek WMA Boundary Fence Installation 10/01/2011
R 27 Wildlife Mitigation Area Fence Removal 10/01/2011
S 186 WMA Boundary Fence Maintenance 10/01/2011
T 186 McCoy Lake Watershed WMA Irrigation Operations 10/01/2011
U 38 WMA Access Road Maintenance 10/01/2010
V 38 Blue Creek WMA Access Roads 10/01/2011
W 38 Cottonwood WMA Access Roads 10/01/2011
X 38 Fox Creek WMA Access Roads 10/01/2011
Y 38 McCoy Lake Watershed WMA Access Roads 10/01/2011
Z 38 Peaks/Wellpinit Mt. WMA Access Roads 10/01/2011
AA 38 Tshimikan Creek WMA Access Roads 10/01/2011
AB 33 Fox Creek WMA Road Decommission 10/01/2011
AC 33 McCoy Lake Watershed WMA Road Decommission 10/01/2011
AD 185 Periodic Status Reports for BPA 10/01/2011
AE 132 Submit Annual Report - FY 11 - Date Range is 10/1/10 to 9/30/11 10/01/2011
AF 132 Submit Annual Report - FY 12 - Date Range is 10/1/11 to 9/30/12 10/01/2010