| Province | Subbasin | % |
|---|---|---|
| Mountain Snake | Clearwater | 100.00% |
* Expenditures data includes accruals and are based on data through 30-Nov-2025.
| Full Name | Organization | Write Permission | Contact Role | Work Phone | |
|---|---|---|---|---|---|
| Brenda Aguirre | Bonneville Power Administration | Yes | Env. Compliance Lead | baguirre@bpa.gov | (503) 230-5928 |
| Jan Brady | Bonneville Power Administration | Yes | COR | jebrady@bpa.gov | (503) 230-4514 |
| Andrew Dux | Idaho Department of Fish and Game (IDFG) | Yes | Supervisor | andy.dux@idfg.idaho.gov | (208) 769-1414 |
| Paul Krueger | Bonneville Power Administration | Yes | F&W Approver | pqkrueger@bpa.gov | (503) 230-5723 |
| Susan Smith | Idaho Department of Fish and Game (IDFG) | No | Administrative Contact | susan.smith@idfg.idaho.gov | (208) 287-2803 |
| Kristi Van Leuven | Bonneville Power Administration | Yes | Contracting Officer | kjvleuven@bpa.gov | (503) 230-3605 |
| David Venditti | Idaho Department of Fish and Game (IDFG) | Yes | Interested Party | david.venditti@idfg.idaho.gov | (208) 465-8404x231 |
| Sean Wilson | Idaho Department of Fish and Game (IDFG) | Yes | Contract Manager | sean.wilson@idfg.idaho.gov | (208) 770-3761 |
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| BPA Environmental Compliance | A: 165. BPA Environmental Compliance | 03/11/2011 | 03/11/2011 | |
| Collection of reservoir limnology data | B: 157. Collect reservoir limnology data | 11/18/2011 | 11/09/2011 | |
| Analyze and interpret limnological data | C: 162. Analyze and interpret limnological data | 02/28/2012 | 02/28/2012 | |
| Conduct hydroacoustic survey | D: 157. Conduct hydroacoustic survey | 07/31/2011 | 07/29/2011 | |
| Conduct mid-water trawl surveys | E: 157. Conduct mid-water trawl surveys | 10/31/2011 | 10/26/2011 | |
| Survey kokanee spawners | F: 157. Survey kokanee spawners | 09/30/2011 | 09/23/2011 | |
| Analyze and interpret kokanee population data | G: 162. Analyze and interpret kokanee population data | 02/28/2012 | 02/28/2012 | |
| Present project results and findings | H: 161. Present project results and findings | 02/28/2012 | 10/28/2011 | |
| Manage project data | I: 160. Manage project data | 02/28/2012 | 02/28/2012 | |
| FY 11 SOW package and accrual estimate | J: 119. Manage and Administer Projects | 02/28/2012 | 01/06/2012 | |
| Final FY 10 annual report attached to this contract | K: 132. Produce Annual Report for the period 3/1/10 - 2/28/11 | 01/31/2012 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Kokanee (Oncorhynchus nerka) |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 165 | BPA Environmental Compliance | 03/01/2011 | ||||||
| B | 157 | Collect reservoir limnology data | 03/01/2011 | ||||||
| C | 162 | Analyze and interpret limnological data | 03/01/2011 | ||||||
| D | 157 | Conduct hydroacoustic survey | 03/01/2011 | ||||||
| E | 157 | Conduct mid-water trawl surveys | 03/01/2011 | ||||||
| F | 157 | Survey kokanee spawners | 03/01/2011 | ||||||
| G | 162 | Analyze and interpret kokanee population data | 03/01/2011 | ||||||
| H | 161 | Present project results and findings | 03/01/2011 | ||||||
| I | 160 | Manage project data | 03/01/2011 | ||||||
| J | 119 | Manage and Administer Projects | 03/01/2011 | ||||||
| K | 132 | Produce Annual Report for the period 3/1/10 - 2/28/11 | 03/01/2011 | ||||||
| L | 185 | Periodic Status Reports for BPA | 03/01/2011 |