Contract 54636: 2010-077-00 EXP WDFW LWD & BLDG REMOVAL IN THE TUCANNON
Project Number:
Title:
Tucannon River Programmatic Habitat Project
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Tucannon 100.00%
Contract Number:
54636
Contract Title:
2010-077-00 EXP WDFW LWD & BLDG REMOVAL IN THE TUCANNON
Contract Continuation:
Previous: Next:
n/a
Contract Status:
Closed
Contract Description:
This contract is being developed to fund two projects on the Washington State Wooten Wildlife Area for restoration of Spring Chinook habitat.  The Tucannon LWD Restoration project is designed to restore physical processes in a 2 mile reach of the Tucannon River.  The LWD (whole conifers with root wad intact) will be placed in the river using helicopter placement techniques.  The project is cost-shared by a $206,000.00 grant through the Snake River Salmon Recovery Funding Board.  The SRFB grant has been used to develop an assessment and design for the project and will be used as match for this BPA contract for the construction of the project.  A final assessment report and project design will be completed by October 2011 and will be added as an attachment  to this contract.

The Quonset Hut Removal and Floodplain Restoration Project is designed to remove a Quonset Storage building and an old bunkhouse from the Tucannon River Floodplain to allow for natural processes to reclaim secondary channels that, up until 3 years ago, were disconnected from the river.  Removal of the buildings and subsequent restoration of native grasses and riparian habitat within the floodplain will make it possible for the river to regain access to over 30 acres of natural floodplain.  Additionally, there is a major spring creek and wetland habitat within the project area that will provide additional rearing habitat opportunities when the river has access to the entire floodplain.  WDFW will provide match by implementing and paying for the habitat restoration.  Habitat restoration will include restoration of over 10 acres of native grassland, reconnection of existing floodplain channels, and restoration of nearly 4 acres of riparian habitat adjacent to an existing mature cottonwood gallery.  The riparian will be irrigated using well water on the property, and the wells will be trusted in a manner that their future use will be strictly for emergency (fire) or if needed for additional habitat restoration efforts. The Tucannon River has been channelized and confined over the past century; this project will open a significant area of spring and wetland habitat to be reclaimed by the river.  The benefits will primarily be restoration of historic spring Chinook spawning and rearing habitat, however large areas of riparian will be restored by the project and it is anticipated that natural riparian restoration will occur as well.
Account Type(s):
Expense
Contract Start Date:
09/15/2011
Contract End Date:
09/30/2012
Current Contract Value:
$492,778
Expenditures:
$492,778

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Assessment and design report A: 175. Assessment, design, and technical review for LWD project 04/30/2012 05/15/2012
All environmental reviews and permits in place prior to construction B: 165. Environmental compliance for LWD & building removal projects 05/15/2012 06/09/2012
200-250 pieces of LWD placed in Tucannon mainstem C: 29. Large woody debris placement 09/30/2012 09/30/2012
Approx. 350 feet of levee breached D: 180. Breach existing cobble levees 08/31/2012 08/31/2012
Design plan for structure removal F: 175. Design plan for structure removal 08/31/2012 08/31/2012
Two buildings removed G: 27. Remove 2 unneeded buildings in floodplain 08/31/2012 08/31/2012
Attach Progress Report in Pisces H: 132. Submit Progress Report for the contract period (9/1/11) to (9/30/12) 09/30/2012 09/30/2012

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 27 Remove Debris
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 2 instances of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 175 Assessment, design, and technical review for LWD project 08/01/2011
B 165 Environmental compliance for LWD & building removal projects 08/01/2011
C 29 Large woody debris placement 05/15/2012
D 180 Breach existing cobble levees 07/29/2013
E 119 Contract management requirements 08/01/2011
F 175 Design plan for structure removal 09/01/2011
G 27 Remove 2 unneeded buildings in floodplain 03/23/2012
H 132 Submit Progress Report for the contract period (9/1/11) to (9/30/12) 08/01/2011
I 185 Periodic Status Reports for BPA 08/01/2011