Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 55129: 2002-060-00 EXP NEZ PERCE HARVEST MONITORING
Project Number:
Title:
Nez Perce Harvest Monitoring on Snake and Clearwater Rivers
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Clearwater 50.00%
Upper Snake Snake Upper 50.00%
Contract Number:
55129
Contract Title:
2002-060-00 EXP NEZ PERCE HARVEST MONITORING
Contract Continuation:
Previous: Next:
50363: 2002-060-00 EXP NEZ PERCE HARVEST MONITORING
  • 60006: 2002-060-00 EXP NEZ PERCE HARVEST MONITORING
Contract Status:
Closed
Contract Description:
This project describes the Nez Perce Tribe's efforts to monitor currently ongoing NPT fisheries.  Sampling strategies are designed to provide greater data precision in treaty catch reports and exploitation rates during select Nez Perce fishery seasons.  Harvest management is intertwined with all Columbia Basin artificial production programs and affects the status of naturally produced stocks as well.  The Nez Perce Tribe has monitored its fisheries primarily by funding sources outside the Northwest Power Planning Council (NPPC) process.  However, the subbasin planning process has documented the need to incorporate this very important aspect of fisheries management within the existing Fish and Wildlife Program.  

The current SOW has three major areas of activity.  Biological Assessments and Tribal Management Plans will be prepared to assure both incidental and direct take of ESA listed species does not jeopardize their existence.  The bulk of the work of the SOW in involved in actual on the ground harvest monitoring in Snake, Salmon and Clearwater rivers and their tributaries and in the Zone 6 fishery (Bonneville Dam to McNary Dam, including some Below Bonneville fishing).  In addition, there will be work to design and verify the monitoring techniques and disseminate the monitoring data to cooperating agencies on a regular basis.
Account Type(s):
Expense
Contract Start Date:
12/01/2011
Contract End Date:
11/30/2012
Current Contract Value:
$323,799
Expenditures:
$323,799

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Katey Grange Bonneville Power Administration Yes Env. Compliance Lead kcgrange@bpa.gov (503) 230-4047
Arleen Henry Nez Perce Tribe Yes Administrative Contact arleenh@nezperce.org (208) 621-3833
David Johnson Nez Perce Tribe No Supervisor davej@nezperce.org (208) 621-3736
Paul Krueger Bonneville Power Administration Yes F&W Approver pqkrueger@bpa.gov (503) 230-5723
Jonathan McCloud Bonneville Power Administration Yes COR jmmccloud@bpa.gov (503) 230-3110
Joseph Oatman Nez Perce Tribe Yes Contract Manager joeo@nezperce.org (208) 843-7320x3730
Dave Statler Nez Perce Tribe Yes Technical Contact daves@nezperce.org (208) 621-3575
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605
Lisa Wright Bonneville Power Administration No Interested Party lswright@bpa.gov (503) 230-4047


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Environmental Compliance Documentation A: 165. Produce Environmental Compliance Documentation 01/10/2012 01/10/2012
BA's for tribal harvest and TMT's for selected subbasins B: 174. Prepare Biological Assessment and Tribal Management Plans 11/30/2012 11/30/2012
Develop Harvest Monitoring Methodology C: 156. Develop harvest monitoring methodology 11/30/2012
Implement Harvest Monitoring Methodology and Disseminate Data D: 157. Implement harvest monitoring methodology and disseminate harvest monitoring results (Creel Survey) 11/30/2012
Implement In-season Survey Harvest Monitoring Methodology and Disseminate Results E: 157. Implement Harvest Monitoring Methodology and Disseminate Harvest Monitoring results (In-season Int.) 11/30/2012 11/30/2012
Implement Harvest Monitoring Methodology and Disseminate Harvest Monitoring Results. F: 157. Implement Harvest Monitoring Methodology and Disseminate Harvest Monitoring Results (Post-season) 11/30/2012
Implement Harvest Monitoring Methodology and Disseminate Harvest Monitoring Results. G: 157. Implement Harvest Monitoring methodology and Disseminate Harvest Monitoring Results (Gill net Int.) 11/30/2012
Attach Combined 2007/2008/2009 Progress Report in Pisces H: 132. Joint Annual Progress Report for 2007, 2008 and 2009 (Dec 2007 to Nov 2009) 04/13/2012 04/13/2012
Attach FY10 Progress Report in Pisces I: 132. Submit Progress Report for the period Dec 2009 to Nov 2010 (FY10) 11/30/2012
Attach FY11 Progress Report in Pisces J: 132. Submit Progress Report for the period Dec 2010 to Nov 2011 (FY11) 11/30/2012
Project Management, Planning and Budgetary Processes K: 119. Project Management & Planning plus Budgetary Processes 11/01/2012 11/21/2012

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Fall ESU (Threatened)
  • 1 instance of WE 174 Produce Plan
  • 4 instances of WE 157 Collect/Generate/Validate Field and Lab Data
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 174 Produce Plan
  • 4 instances of WE 157 Collect/Generate/Validate Field and Lab Data
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 174 Produce Plan
  • 4 instances of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Produce Environmental Compliance Documentation 12/01/2011
B 174 Prepare Biological Assessment and Tribal Management Plans 12/01/2011
C 156 Develop harvest monitoring methodology 12/01/2011
D 157 Implement harvest monitoring methodology and disseminate harvest monitoring results (Creel Survey) 12/01/2011
E 157 Implement Harvest Monitoring Methodology and Disseminate Harvest Monitoring results (In-season Int.) 12/01/2011
F 157 Implement Harvest Monitoring Methodology and Disseminate Harvest Monitoring Results (Post-season) 12/01/2011
G 157 Implement Harvest Monitoring methodology and Disseminate Harvest Monitoring Results (Gill net Int.) 12/01/2011
H 132 Joint Annual Progress Report for 2007, 2008 and 2009 (Dec 2007 to Nov 2009) 12/01/2011
I 132 Submit Progress Report for the period Dec 2009 to Nov 2010 (FY10) 12/01/2011
J 132 Submit Progress Report for the period Dec 2010 to Nov 2011 (FY11) 12/01/2011
K 119 Project Management & Planning plus Budgetary Processes 12/01/2011
L 185 Periodic Status Reports for BPA 12/01/2011