Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 55349: 2010-001-00 EXP ENVIRONMENTAL COMPLIANCE M2 PRE-IMPLEMENTATION
Project Number:
Title:
Upper Columbia Programmatic Habitat
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Cascade Entiat 25.00%
Methow 25.00%
Okanogan 25.00%
Wenatchee 25.00%
Contract Number:
55349
Contract Title:
2010-001-00 EXP ENVIRONMENTAL COMPLIANCE M2 PRE-IMPLEMENTATION
Contract Continuation:
Previous: Next:
n/a
Contract Status:
Closed
Contract Description:
Methow Salmon Recovery Foundation (MSRF) and its partners, including Bureau of Reclamation (Reclamation), Yakama Nation (YN), WA Department of Fish and Wildlife (WDFW), and Trout Unlimited (TU), plan to implement multiple salmon habitat enhancement projects in the Middle Methow (M2) reach of the Methow River between 2012 and 2014. The EC M2 Pre-implementation project will conduct environmental compliance activities in advance of the contract for the M2 Habitat Project through the UCSRB targeted solicitation process in order to facilitate project construction in 2012.

Environmental compliance for this project includes both Section 106 cultural consultation and federal Section 7 ESA consultation (USFWS and NOAA).  MSRF  has secured funding through Reclamation to complete the SEPA and JARPA permitting processes.  Cultural and ESA consultation are not included in MSRF’s budget with Reclamation and cannot be delayed until funding would be available through the BPA targeted solicitation process. Time constraints are further exacerbated by the weather in the Methow, which requires that field work for S. 106 generally be completed prior to the end of November.  If the November window is missed, the field work could not be completed until snow melt, which could be as late as May, and would eliminate the opportunity to modify project designs to accommodate cultural concerns. To meet the planned start time of July1st, 2012 for instream construction on the first two scheduled M2 project areas (Whitefish Island and WDFW Floodplain),  the BA needs to be submitted to USFWS no later than the end of January to receive a BiOp by June. As a BA is time consuming to prepare, it is necessary to start it well in advance of the January submission deadline.

The goal of this M2 pre-implementation contract would be to complete BPA’s EC requirements ahead of the UCSRB targeted solicitation in order to ensure completion of these requirements within their respective timelines to allow construction to proceed in the summer 2012 work window.
Account Type(s):
Expense
Contract Start Date:
12/01/2011
Contract End Date:
11/30/2012
Current Contract Value:
$29,800
Expenditures:
$29,800

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Complete BPA EC permitting process A: 165. Obtain required permits and documentation for the M2 Habitat Project 11/30/2012 11/30/2012
Manage and Administer Project B: 119. Manage BPA Contracting Requirements 11/30/2012 11/30/2012
Attach Progress Report in Pisces D: 132. Project Completion Report 11/30/2012

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Obtain required permits and documentation for the M2 Habitat Project 01/15/2012
B 119 Manage BPA Contracting Requirements 01/15/2012
C 185 Periodic Status Reports for BPA 01/15/2012
D 132 Project Completion Report 01/15/2012