Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 56662 REL 176: 1997-051-00 EXP YAKIMA BASIN SIDE CHANNELS
Project Number:
Title:
Yakima Basin Habitat
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Yakima 100.00%
Contract Number:
56662 REL 176
Contract Title:
1997-051-00 EXP YAKIMA BASIN SIDE CHANNELS
Contract Continuation:
Previous: Next:
56662 REL 151: 1997-051-00 EXP YAKIMA BASIN SIDE CHANNELS
Contract Status:
Closed
Contract Description:
The project serves as the overarching habitat stewardship program for YKFP in the Yakima Subbasin, for off-reservation activities. Examples of work that is performed under this project includes all aspects of stream restoration including revegetation, weed control, fencing, removal of fish passage barriers, installation of NOAA-compliant fish screens, placement of woody material in streams at strategic locations, levee removal and road relocation. Other activities include collaboration with other resource management entities, review and input on restoration plans and programs, review and comment on land use plans and development projects. The project has a strong history of collaboration with many entities. Over 50 miles of habitat has been reopened to anadromous fish through this program, dozens of screens have been installed and over 80 restoration and protection projects have been implemented.
Account Type(s):
Expense
Contract Start Date:
03/01/2019
Contract End Date:
03/31/2020
Current Contract Value:
$1,472,786
Expenditures:
$1,472,786

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Shirley Alvarado Yakama Confederated Tribes Yes Administrative Contact shirley_alvarado@yakama.com (509) 865-5121x6304
Wilbur Barrick Yakama Confederated Tribes No Technical Contact barw@yakamafish-nsn.gov (509) 929-2641
Ashton Bunce Yakama Confederated Tribes No Technical Contact buna@yakamafish-nsn.gov (509) 945-2478
Kelly Clayton Yakama Confederated Tribes Yes Contract Manager clak@yakamafish-nsn.gov (509) 945-7195
William Cochenour Bonneville Power Administration Yes Contracting Officer wmcochenour@bpa.gov (360) 619-6463
Ryan DeKnikker Yakama Confederated Tribes No Technical Contact dekr@yakamafish-nsn.gov (509) 945-5389
Desmond Gelman Bonneville Power Administration No CO Assistant dxgelman@bpa.gov (503) 230-4960
Ilene Goudy Yakama Confederated Tribes No Technical Contact goui@yakamafish-nsn.gov (509) 388-3217
Douglas Knapp Bonneville Power Administration Yes Technical Contact ddknapp@bpa.gov (503) 230-3285
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
John Marvin Yakama Confederated Tribes No Technical Contact marj@yakamafish-nsn.gov (509) 966-7406
Claire McClory Bonneville Power Administration Yes Env. Compliance Lead cdmcclory@bpa.gov (503) 230-5922
Scott Nicolai Yakama Confederated Tribes Yes Supervisor nics@yakamafish-nsn.gov
Michelle O'Malley Bonneville Power Administration Yes COR mmomalley@bpa.gov (503) 230-5138
Mel Sampson Yakama Confederated Tribes Yes Supervisor mel@yakama.com (509) 865-5121x6303
Adrienne Wilson Yakama Confederated Tribes Yes Administrative Contact Adrienne_Wilson@Yakama.com (509) 865-5121x6306


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
2019 Annual Report (3/1/19-2/28/20) B: 132. YKFP Habitat Project 2019 Annual Report (3/1/19-02/28/20) 02/28/2020 02/28/2020
Effective implementation management and timely contract administration C: 119. Manage and Administer Projects 02/28/2020 02/28/2020
Participate in ESA/NEPA Compliance for Yakima Basin habitat management activities D: 165. Environmental Compliance 02/28/2020 02/28/2020
Technical review E: 122. YKFP Habitat, Water and Passage Technical Review Activities 02/28/2020 02/28/2020
Pre-Acquisition Activities F: 172. Conduct Pre-Acquisition Activities 02/28/2020 02/28/2020
Manage Habitat Parcels G: 186. Manage Habitat Parcels 02/28/2020 02/28/2020
Remove undesirable vegetation at the ECP property H: 198. ECP weed control 02/28/2020 09/30/2019
Remove undesirable vegetation at the Henne property I: 198. Henne weed control 02/28/2020 02/28/2020
Establish native vegetation at the Fortune habitat parcel J: 198. Fortune Vegetation Management 02/28/2020 02/28/2020
Establish native vegetation at the Harris habitat parcel K: 198. Harris Vegetation Management 02/28/2020 02/28/2020
Establish native vegatation L: 198. Ahtanum Village Vegetation Management 02/28/2020
Install fence M: 40. Ahtanum Village fence installation 02/28/2020 08/31/2019
Remove invasive crack willow N: 199. Pott Road invasive crack willow removal 02/28/2020
Place large wood in Jungle Creek O: 29. TCF Phase III: Jungle Creek Wood Replenishment 02/28/2020
Place large wood in Indian Creek P: 29. TCF Phase III: Indian Creek Wood Replenishment 02/28/2020
Place large woody material on Carlson Creek Q: 29. TCF Phase III: Carlson Creek Wood Replenishment 02/28/2020 10/31/2019
Place large wood in Little Rattlesnake Creek R: 29. Phase II Little Rattlesnake Creek Wood Replenishment 08/30/2019
Install large wood in North Fork Manastash Creek S: 29. Phase II NF Manastash Creek Wood Replenishment 02/28/2020 08/31/2019
Construct instream and floodplain wood structures T: 29. Phase II SF Cowiche Creek Wood Replenishment 02/28/2020
Place large wood in Swauk Creek U: 29. Phase III Lower Swauk Creek Wood Replenishment 02/28/2020 08/31/2019
Place large wood in Cedar Creek Meadow V: 29. Cedar Meadow/Taneum Creek Wood Replenishment 02/28/2020
Correct barrier to provide fish passage at Taneum 1.8 X: 184. Taneum Creek RM 1.8 (Ragland) Fish Passage 02/28/2020
Placed large wood in NF Teanaway Y: 29. NF Teanaway River Floodplain Restoration 02/28/2020 09/30/2019
Produce edge habitat design Z: 175. Tieton River Habitat Enhancement 02/28/2020
Install locally gathered large woody material for rearing habitat enhancement AA: 29. Phase III Yakima River Edge Habitat Enhancement 02/28/2020
Place Large Wood Instream AB: 29. Phase III Taneum Creek Wood Replenishment 02/28/2020 02/28/2020
Complete cultural resources surveys AC: 175. Lower Longmire Levee Removal (cultural resources only) 02/28/2020
Complete cultural resources surveys AE: 175. Nile Creek Wood Replenishment (cultural resources only) 02/28/2020
Produce permit-level designs AF: 175. Ahtanum Creek Floodplain Restoration (cultural resources only) 02/28/2020
Complete cultural resources surveys AH: 175. Heart K property/Taneum Creek Floodplain Restoration (cultural resources only) 02/28/2020
Complete cultural resources surveys AI: 175. Section 2 Meadow/Tanuem Creek Restoration (cultural resources only) 02/28/2020
Complete cultural resources surveys AJ: 175. Section 34/Taneum Creek Floodplain Restoration (cultural resources only) 02/28/2020
Complete cultural resources surveys AK: 175. Icewater/Taneum Creek Wood Replenishment (cultural resources only) 02/28/2020
Complete cultural resources surveys AL: 175. Middle Fork Ahtanum Creek Wood Replenishment (cultural resources only) 02/28/2020
Complete cultural resources surveys AM: 175. SF Tanuem Creek Wood Replenishment (cultural resources only) 02/28/2020
Add wood to Heart K property AN: 29. CCR-42480 Heart K/Taneum Creek Floodplain Restoration 02/29/2020
Complete cultural resources surveys AO: 175. CCR-42480 SF Manastash Creek Wood Replenishment (cultural resources only) 02/29/2020

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (Oncorhynchus tshawytscha) - All Populations
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 4 instances of WE 198 Maintain Vegetation
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 6 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 40 Install Fence
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 3 instances of WE 175 Produce Design
Coho (O. kisutch) - Unspecified Population
  • 5 instances of WE 198 Maintain Vegetation
  • 1 instance of WE 199 Remove Vegetation
  • 9 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 40 Install Fence
  • 3 instances of WE 175 Produce Design
Steelhead (Oncorhynchus mykiss) - All Populations
  • 1 instance of WE 175 Produce Design
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 5 instances of WE 198 Maintain Vegetation
  • 1 instance of WE 199 Remove Vegetation
  • 12 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 40 Install Fence
  • 1 instance of WE 184 Install Fish Passage Structure
  • 13 instances of WE 175 Produce Design
Trout, Bull (S. confluentus) (Threatened)
  • 6 instances of WE 175 Produce Design
Trout, Rainbow (Oncorhynchus mykiss)
  • 2 instances of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 03/01/2019
B 132 YKFP Habitat Project 2019 Annual Report (3/1/19-02/28/20) 03/01/2019
C 119 Manage and Administer Projects 03/01/2019
D 165 Environmental Compliance 03/01/2019
E 122 YKFP Habitat, Water and Passage Technical Review Activities 03/01/2019
F 172 Conduct Pre-Acquisition Activities 03/01/2019
G 186 Manage Habitat Parcels 08/12/2019
H 198 ECP weed control 08/12/2019
I 198 Henne weed control 08/12/2019
J 198 Fortune Vegetation Management 08/12/2019
K 198 Harris Vegetation Management 08/12/2019
L 198 Ahtanum Village Vegetation Management
M 40 Ahtanum Village fence installation 11/25/2019
N 199 Pott Road invasive crack willow removal 08/12/2019
O 29 TCF Phase III: Jungle Creek Wood Replenishment
P 29 TCF Phase III: Indian Creek Wood Replenishment
Q 29 TCF Phase III: Carlson Creek Wood Replenishment 11/25/2019
R 29 Phase II Little Rattlesnake Creek Wood Replenishment
S 29 Phase II NF Manastash Creek Wood Replenishment 08/12/2019
T 29 Phase II SF Cowiche Creek Wood Replenishment
U 29 Phase III Lower Swauk Creek Wood Replenishment 08/12/2019
V 29 Cedar Meadow/Taneum Creek Wood Replenishment
W 175 Taneum Creek Floodplain Restoration
X 184 Taneum Creek RM 1.8 (Ragland) Fish Passage
Y 29 NF Teanaway River Floodplain Restoration 08/12/2019
Z 175 Tieton River Habitat Enhancement
AA 29 Phase III Yakima River Edge Habitat Enhancement
AB 29 Phase III Taneum Creek Wood Replenishment 08/12/2019
AC 175 Lower Longmire Levee Removal (cultural resources only)
AD 175 NF Ahtanum Creek Wood Replenishment (cultural resources only)
AE 175 Nile Creek Wood Replenishment (cultural resources only)
AF 175 Ahtanum Creek Floodplain Restoration (cultural resources only)
AG 175 Lower Canyon Habitat Enhancement Project (cultural resources only)
AH 175 Heart K property/Taneum Creek Floodplain Restoration (cultural resources only)
AI 175 Section 2 Meadow/Tanuem Creek Restoration (cultural resources only)
AJ 175 Section 34/Taneum Creek Floodplain Restoration (cultural resources only)
AK 175 Icewater/Taneum Creek Wood Replenishment (cultural resources only)
AL 175 Middle Fork Ahtanum Creek Wood Replenishment (cultural resources only)
AM 175 SF Tanuem Creek Wood Replenishment (cultural resources only)
AN 29 CCR-42480 Heart K/Taneum Creek Floodplain Restoration
AO 175 CCR-42480 SF Manastash Creek Wood Replenishment (cultural resources only)