| 56662 REL 221: 2008-455-00 EXP STURGEON MANAGEMENT |
|
* Expenditures data includes accruals and are based on data through 30-Nov-2025.
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Environmental clearances for the project | B: 165. Obtain environmental clearances for project | 03/31/2022 | 12/31/2021 | |
| Effective implementation management and timely contract administration | C: 119. Manage and Administer project | 08/31/2022 | ||
| Completed 2020-21 Annual Report | D: 132. Prepare and submit Progress Report for September 2020 through August 2021 | 01/31/2022 | ||
| Completed Annual Report | E: 132. Submit Progress Report for the period (Sept 2019) to (August 2020) | 10/30/2021 | ||
| Staff training summary | F: 99. Hatchery Training and Development | 03/31/2022 | 03/31/2022 |
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 185 | Periodic Status Reports for BPA | |||||||
| B | 165 | Obtain environmental clearances for project | |||||||
| C | 119 | Manage and Administer project | |||||||
| D | 132 | Prepare and submit Progress Report for September 2020 through August 2021 | |||||||
| E | 132 | Submit Progress Report for the period (Sept 2019) to (August 2020) | |||||||
| F | 99 | Hatchery Training and Development |