| Funding Package - Submit draft to COTR |
A: 119. Manage Restoration Projects |
|
10/31/2013 |
10/31/2013 |
| Assist BPA to produce Environmental Compliance Documentation |
B: 165. Produce EC Documentation |
|
05/31/2014 |
05/27/2014 |
| Design reports, outreach materials, and final construction documents |
E: 175. Chewuch River Mile 11.75-13 Design 2011-74 |
|
06/28/2013 |
06/28/2013 |
| Restored Floodplain and Increased Channel Complexity |
F: 30. Twisp Ponds Habitat Restoration Construction 2010-54 |
|
05/01/2013 |
05/01/2013 |
| Regraded in-flow ditch servicing floodplain rearing habitat ponds |
G: 186. Twisp River Ponds Inflow Ditch Regrade 2009-04 |
|
11/01/2012 |
09/27/2012 |
| Construct 4 miles of cattle exclusion fence |
H: 40. Twisp River Fence Project 1 0f 4 2011-75 |
|
11/16/2012 |
09/13/2012 |
| Construct 0.75 miles of cattle exclusion fence |
I: 40. Twisp River Fence Project 2 of 4 2011-75 |
|
11/16/2012 |
09/13/2012 |
| Construct 0.75 miles of cattle exclusion fence |
J: 40. Twisp River Fence Project 3 of 4 2011-75 |
|
11/16/2012 |
09/13/2012 |
| Construct 1.2 miles of cattle exclusion fence |
K: 40. Twisp River Fence Project 4 of 4 2011-75 |
|
11/16/2012 |
09/13/2012 |
| Constructed Log Jam and Large Wood Placement in Side Channel |
L: 29. M2 LRT Eagle Rocks ELJ Construction 2011-80 |
|
07/12/2013 |
07/12/2013 |
| Constructed Log Jam and Large Wood Placement along Riprap |
M: 29. M2 LRT Two Channels ELJ Construction 2011-86 |
|
05/31/2014 |
|
| Constructed Log Jam and Large Wood Placement along Riprap |
N: 29. M2 LRT Sugar Dike ELJ Construction 2011-87 |
|
09/15/2013 |
09/13/2013 |
| Large Wood Habitat along Riprap |
O: 29. M2 LRT Site D ELJ Construction 2011-88 |
|
09/15/2013 |
09/15/2013 |
| Removal of a fish passage barrier |
Q: 85. Tillicum Cr. Culvert Replacement Project #1 2011-82 |
|
05/31/2014 |
10/27/2013 |
| Removal of a fish passage barrier |
R: 85. Tillicum Cr. Culvert Replacement Project #2 2012-86 |
|
05/31/2014 |
05/27/2014 |
| One completed assessment document as per the Work Element Description |
S: 174. Entiat Upper Stillwaters Reach Assessment - 2012-92 |
|
10/01/2013 |
06/28/2013 |
| Final Design documents for Peshastin RM 0.8 project |
T: 175. Peshastin RM 0.8 Design 2011-69 |
|
07/01/2012 |
07/01/2012 |
| Constructed Peshastin RM 0.8 project |
U: 30. Peshastin RM 0.8 Construction 2011-69 |
|
11/30/2012 |
08/30/2012 |
| Restored riparian habitat. |
V: 47. Peshastin RM 1.2L Riparian Restoration 2011-79 |
|
05/16/2014 |
09/30/2013 |
| Peshastin Fishway repaired to operating standards |
W: 186. Peshastin Fishway Repairs 2012-93 |
|
11/16/2012 |
09/21/2012 |
| Permit-ready and construction designs for several projects in the Upper White Pine (Nason Creek) |
X: 175. UWP Nason Creek Design 2011-70 |
|
05/31/2014 |
05/27/2014 |
| Design reports, outreach materials, and final construction documents |
Z: 175. NEW CCR28679 Natapoc Design 2010-53 |
|
05/31/2014 |
05/27/2014 |
| Produce Big Valley South Fish Enhancement Project Conceptual Designs |
AB: 175. NEW CCR28679 Big Valley South Fish Enhancement Project 2012-101 |
|
04/18/2014 |
05/01/2014 |
| Design reports/models, outreach materials and various plan percentage based plan sets |
AD: 175. NEW CCR28679 Road's End Design 2012-103 |
|
05/31/2014 |
|