| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Fulfill all administrative tasks with quality products and in a timely manner. | A: 119. Submittal of September Accrual estimates and monthly invoices. | 06/30/2014 | 06/30/2014 | |
| Procure Fiberglass Tanks and Incubators | B: 171. Procurement | 02/28/2013 | 03/29/2013 | |
| Complete Pre-Construction Demolition and Material Removal Work | C: 171. Demolition | 10/09/2012 | 09/20/2012 | |
| Complete Hatchery Area Site Work | D: 171. Hatchery Site Work and Utilities | 11/01/2013 | 09/05/2013 | |
| Complete Headbox Construction | E: 171. Headbox and Degassing | 08/15/2013 | 08/15/2013 | |
| Complete Water Supply Delivery System | F: 171. Water Supply and Yard Piping | 06/15/2013 | 08/26/2013 | |
| Complete construction of hatchery building | G: 171. Hatchery Building | 10/30/2013 | 12/13/2013 | |
| Complete construction of roads and parking areas for Springfield Hatchery | H: 171. Roads and Access | 10/30/2013 | 08/29/2013 | |
| Convert existing residence to bunkhouse | I: 171. Remodel Residence 1 | 01/30/2014 | 01/16/2014 | |
| Complete Outdoor Raceways 1-24 | J: 171. Raceways | 10/30/2013 | 12/05/2013 | |
| Obtain all necessary state and local construction and disposal permits | K: 165. Secure state and local permits | 07/31/2012 | 06/30/2012 | |
| Complete Hatchery Housing and Site Construction | L: 171. Construct three residences | 10/01/2013 | 09/05/2013 | |
| Complete Shop Building | M: 171. Construct Shop/Storage Building | 10/27/2013 | 12/05/2013 | |
| Complete construction of dual cell effluent/settling basin | N: 171. Effluent / Settling Basin | 10/30/2013 | 11/07/2013 | |
| Mobilize/Demobilize to and from site. Ascertain needed bonds and insurance | O: 171. Mobilization/Demobilization | 12/31/2013 | 11/15/2013 | |
| Attach Progress Report in Pisces | Q: 132. Submit Completion Report for the period (May 2012) to (Dec 2013) | 06/30/2014 | ||
| Provide owner designated oversight of construction activities | R: 171. Construction Oversight | 12/31/2013 | 12/31/2013 | |
| Application of General Conditions | S: 171. General Conditions | 06/30/2014 | 06/27/2014 | |
| Prepare Springfield Hatchery Operation and Maintenance Manual | T: 175. Draft O and M Manual | 04/30/2014 | 06/20/2014 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Sockeye (O. nerka) - Snake River ESU (Endangered) |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 119 | Submittal of September Accrual estimates and monthly invoices. | 06/01/2012 | ||||||
| B | 171 | Procurement | 06/13/2012 | ||||||
| C | 171 | Demolition | 06/13/2012 | ||||||
| D | 171 | Hatchery Site Work and Utilities | 06/13/2012 | ||||||
| E | 171 | Headbox and Degassing | 06/13/2012 | ||||||
| F | 171 | Water Supply and Yard Piping | 06/13/2012 | ||||||
| G | 171 | Hatchery Building | 06/13/2012 | ||||||
| H | 171 | Roads and Access | 06/13/2012 | ||||||
| I | 171 | Remodel Residence 1 | 06/13/2012 | ||||||
| J | 171 | Raceways | 06/13/2012 | ||||||
| K | 165 | Secure state and local permits | 06/01/2012 | ||||||
| L | 171 | Construct three residences | 06/13/2012 | ||||||
| M | 171 | Construct Shop/Storage Building | 06/13/2012 | ||||||
| N | 171 | Effluent / Settling Basin | 06/13/2012 | ||||||
| O | 171 | Mobilization/Demobilization | 06/13/2012 | ||||||
| P | 185 | Periodic Status Reports for BPA | 06/01/2012 | ||||||
| Q | 132 | Submit Completion Report for the period (May 2012) to (Dec 2013) | 06/01/2012 | ||||||
| R | 171 | Construction Oversight | 06/13/2012 | ||||||
| S | 171 | General Conditions | 06/13/2012 | ||||||
| T | 175 | Draft O and M Manual | 05/10/2012 |