Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 57335: 1996-035-01 EXP YAKAMA RESERVATION WATERSHED PROJECT
Project Number:
Title:
Yakama Reservation Watershed Project
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Yakima 100.00%
Contract Number:
57335
Contract Title:
1996-035-01 EXP YAKAMA RESERVATION WATERSHED PROJECT
Contract Continuation:
Previous: Next:
52386: 1996-035-01 EXP YAKAMA RESERVATION WATERSHED PROJECT
  • 56662 REL 15: 1996-035-01 EXP YAKIMA RESERVATION WATERSHED PROJECT (YRWP)
Contract Status:
Closed
Contract Description:
The YRWP works to restore natural function to the Satus, Toppenish and Ahtanum Watersheds. Our restoration and monitoring efforts take a comprehensive approach to the restoration of habitat for fisheries resources including steelhead and bull trout.
Account Type(s):
Expense
Contract Start Date:
03/01/2012
Contract End Date:
02/28/2013
Current Contract Value:
$1,123,004
Expenditures:
$1,123,004

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Shannon Adams Yakama Confederated Tribes Yes Contract Manager adas@yakamafish-nsn.gov (509) 945-0754
Debbie Azure Yakama Confederated Tribes Yes Administrative Contact azud@yakamafish-nsn.gov (509) 865-5121x6334
Kelly Clayton Yakama Confederated Tribes Yes Technical Contact clak@yakamafish-nsn.gov (509) 945-7195
Ryan DeKnikker Yakama Confederated Tribes Yes Technical Contact dekr@yakamafish-nsn.gov (509) 945-5389
Loverne George Yakama Confederated Tribes Yes Administrative Contact geol@yakamafish-nsn.gov (509) 865-5121x6364
Edward Gresh Bonneville Power Administration Yes Env. Compliance Lead esgresh@bpa.gov (503) 230-5756
Tana Hoptowit Yakama Confederated Tribes Yes Interested Party hopt@yakamafish-nsn.gov (509) 865-5121x6318
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Khanida Mote Bonneville Power Administration Yes Contracting Officer kpmote@bpa.gov (503) 230-4599
Michelle O'Malley Bonneville Power Administration Yes COR mmomalley@bpa.gov (503) 230-5138
Steve Parker Yakama Confederated Tribes No Supervisor pars@yakamafish-nsn.gov (509) 865-6262x6342
Tim Resseguie Yakama Confederated Tribes Yes Technical Contact rest@yakamafish-nsn.gov (509) 945-7409
Brandon Rogers Yakama Confederated Tribes Yes Interested Party rogb@yakamafish-nsn.gov (509) 949-4109
Paul Ward Yakama Confederated Tribes No Supervisor warp@yakamafish-nsn.gov (509) 949-4129


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
FY13 SOW and LIB submitted B: 119. Manage Restoration Projects 02/28/2013 01/30/2013
List of Selected Projects (and contingency projects) to be implemented in 2013 C: 114. Select habitat improvement actions and identify possible projects for 2013 09/30/2012 09/30/2012
Project databases that are maintained and up to date. D: 160. Update Project Database 02/28/2013 02/28/2013
Disseminated data E: 161. Create informal summary reports and maps 12/31/2012 12/31/2012
5 outreach sessions completed F: 99. Conduct field and classroom education at local schools 11/30/2012 12/31/2012
Technical review and input provided to various policy and planning efforts G: 122. Input to various Tribal planning and policy efforts 02/28/2013 02/28/2013
Completed environmental documentation H: 165. Environmental Compliance 11/08/2012 11/07/2012
Completed 2011 Annual Report submitted to BPA I: 132. Produce Project Annual Report for FY 11 (3/1/2011 - 2/28/2012) 02/01/2013 02/28/2013
2 rotary screw traps deployed and recovered J: 70. Deploy and Recover 5ft Rotary Screw Traps 10/31/2012 10/31/2012
Outmigration estimate and other data from screw traps K: 157. Operate rotary screw traps 02/28/2013 02/28/2013
Complete three pass surveys in Satus and Ahtanum Creeks L: 157. Conduct spawner surveys 06/15/2012 05/31/2012
15 miles of completed snorkel surveys M: 157. Conduct snorkel surveys 10/31/2012 09/30/2012
Complete 1500 meters of surveys N: 157. Conduct habitat surveys 10/31/2012 09/30/2012
Water temperature record O: 157. Collect water temperature data 01/31/2013 12/31/2012
Weekly manual discharge measurements P: 157. Collect discharge measurements 02/28/2013 02/28/2013
Electrofishing surveys Q: 157. Conduct electrofishing surveys 10/31/2012 09/30/2012
Monitor water level in monitoring wells R: 157. Collect data from monitoring wells 02/28/2013 02/28/2013
Wapato Irrigation Project diversions managed for minimum instream flow. S: 186. Manage Operation of Upper and Lower WIP canals on Ahtanum Creek 02/28/2013 02/28/2013
water diversion managed at Olney lateral to provide minimum streamflow T: 186. Assist with operation of Olney Lateral 02/28/2013 02/28/2013
Functioning fences, wells, stock tanks, and habitat improvements U: 186. Maintain livestock wells/stock tanks/livestock fences/improved springs 02/28/2013 02/28/2013
Install Barb Wire Fence W: 40. Install Barb Wire Fence on Camas Patch Meadow 07/01/2012 06/30/2012
Install Buck & Pole Fence X: 40. Install Buck & Pole Fence at Camas Patch Meadow 09/30/2012 09/30/2012
Remove Diversion Y: 84. Durham Dam Removal Construction 09/30/2012 08/30/2012
Install Fish Screen Z: 69. CCR27642 CHANGES - SF Simcoe Creek Feeder Ditch Fish Screen 12/31/2012 10/08/2012
Remove Culvert AA: 85. CCR27642 CHANGES - NF Simcoe Creek Culvert Removal 09/30/2012 07/09/2012
Produce/Design engineering plans AD: 175. CCR27642 CHANGES - Simcoe Creek Bank Stabilization Project 02/28/2013 02/28/2013
outmigration estimates and timing information AE: 162. Analyze smolt outmigration data 02/28/2013 02/28/2013
index of spawner abundance and spawning distribution AF: 162. Analyze spawner survey data 02/28/2013 02/28/2013
Water temperature record and descriptive statistics AG: 162. Analyze water temperature data 02/28/2013 02/28/2013
Habitat metrics and indicators AH: 162. Analyze habitat survey data 02/28/2013 02/28/2013
Spatial Fish Density AI: 162. Analyze snorkel survey data 12/01/2012 12/01/2012
Camas Patch Meadow Assessment AJ: 174. CCR27642 NEW - Camas Patch Meadow Assessment 02/28/2013 02/28/2013
technical review recommendations provided AK: 122. CCR27642 NEW - Project engineering support 02/28/2013 02/28/2013

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Lower Columbia River DPS (Threatened)
  • 1 instance of WE 162 Analyze/Interpret Data
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 4 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 40 Install Fence
  • 1 instance of WE 55 Erosion and Sedimentation Control
  • 1 instance of WE 69 Install Fish Screen
  • 1 instance of WE 84 Remove/Install Diversion
  • 2 instances of WE 85 Remove/Breach Fish Passage Barrier
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 70 Install Fish Monitoring Equipment
  • 8 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 161 Disseminate Raw/Summary Data and Results
  • 4 instances of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 03/01/2012
B 119 Manage Restoration Projects 03/01/2012
C 114 Select habitat improvement actions and identify possible projects for 2013 03/01/2012
D 160 Update Project Database 03/01/2012
E 161 Create informal summary reports and maps 03/01/2012
F 99 Conduct field and classroom education at local schools 03/01/2012
G 122 Input to various Tribal planning and policy efforts 03/01/2012
H 165 Environmental Compliance 03/01/2012
I 132 Produce Project Annual Report for FY 11 (3/1/2011 - 2/28/2012) 03/01/2012
J 70 Deploy and Recover 5ft Rotary Screw Traps 03/01/2012
K 157 Operate rotary screw traps 03/01/2012
L 157 Conduct spawner surveys 03/01/2012
M 157 Conduct snorkel surveys 03/01/2012
N 157 Conduct habitat surveys 03/01/2012
O 157 Collect water temperature data 03/01/2012
P 157 Collect discharge measurements 03/01/2012
Q 157 Conduct electrofishing surveys 03/01/2012
R 157 Collect data from monitoring wells 03/01/2012
S 186 Manage Operation of Upper and Lower WIP canals on Ahtanum Creek 03/01/2012
T 186 Assist with operation of Olney Lateral 03/01/2012
U 186 Maintain livestock wells/stock tanks/livestock fences/improved springs 03/01/2012
V 55 CCR27642 CHANGE - Camas Patch Meadow Grade Control
W 40 Install Barb Wire Fence on Camas Patch Meadow 03/01/2012
X 40 Install Buck & Pole Fence at Camas Patch Meadow 03/01/2012
Y 84 Durham Dam Removal Construction 03/01/2012
Z 69 CCR27642 CHANGES - SF Simcoe Creek Feeder Ditch Fish Screen 07/23/2012
AA 85 CCR27642 CHANGES - NF Simcoe Creek Culvert Removal 08/07/2012
AB 85 CCR27642 CHANGE - NF Topp Creek Culvert Removal
AC 186 CCR27642 CHANGE - Ahtanum Creek Bank Stabilization Project 2012
AD 175 CCR27642 CHANGES - Simcoe Creek Bank Stabilization Project 03/01/2012
AE 162 Analyze smolt outmigration data 03/01/2012
AF 162 Analyze spawner survey data 03/01/2012
AG 162 Analyze water temperature data 03/01/2012
AH 162 Analyze habitat survey data 03/01/2012
AI 162 Analyze snorkel survey data 03/01/2012
AJ 174 CCR27642 NEW - Camas Patch Meadow Assessment 03/01/2012
AK 122 CCR27642 NEW - Project engineering support 03/01/2012