Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 58734: 201000100 EXP LOWER ENTIAT RM 0.8 - 2.3 RESTORATION
Project Number:
Title:
Upper Columbia Programmatic Habitat
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Cascade Entiat 25.00%
Methow 25.00%
Okanogan 25.00%
Wenatchee 25.00%
Contract Number:
58734
Contract Title:
201000100 EXP LOWER ENTIAT RM 0.8 - 2.3 RESTORATION
Contract Continuation:
Previous: Next:
n/a
  • 64314: 2010-001-00 EXP LOWER ENTIAT RM 0.8 - 2.3 IMPLEMENATION
Contract Status:
Closed
Contract Description:
%  This contract includes a No Cost Time Extension for the continuation of the original scope of work and associated work elements through December 31, 2013. The need for the time extension is to fill a gap between the original contract September end date and an upcoming BPA construction grant contract for the project, beginning in January 2014. Cascadia staff needs to continue working with the landowners, conducting public meetings, developing the design details, and work with permit applications in preparation for project construction in 2014. In addition to submitting the permit applications, there may be information requests by the permitting agencies and other permit management tasks to complete during this time period. Continuing the project through December  will provide continuity during the transition to construction, as well as the opportunity to respond promptly to any partner agency needs related to the project.  

%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%

There are three primary purposes of the subject contract:

One element of this contract is to fund Cascadia Conservation District's participation with the USFWS Design Team (contract #56835) and Chelan County NRD (CR-229364) to design habitat projects in the Lower Entiat Rm 0.8 - 2.3 by providing staff support including but not limited to permit application preparation, landowner coordination, field support preparation of vegetative restoration plans and other services as necessary to complete the design process.  Construction is planned for 2014 under separate contract as one of a suite of projects intended to implement the 2014 Lower Entiat Intensively Monitored Watershed (IMW) program..

The second element is Cascadia Conservation District's participation with the USFWS Design Team (contract #56835) to design habitat projects in the Lower Entiat at the Entiat National Fish Hatchery (ENFH)  Rm 6.7 - 7.0. Cascadia staff will support the design effort through the preparation of permit application packages, field support and other tasks as necessary to complete the design process.  Construction is planned for 2014 under separate contract as one of a suite of projects intended to implement the 2014 Lower Entiat Intensive Monitored Watershed (IMW) program.

The third element of this contract includes funds to be used for Incidental maintenance of the Tyee Ranch Habitat Restoration project, which is being constructed in 2012 under separate contract (#53025).
Account Type(s):
Expense
Contract Start Date:
09/15/2012
Contract End Date:
12/31/2013
Current Contract Value:
$75,281
Expenditures:
$75,281

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Roy Beaty Bonneville Power Administration Yes F&W Approver rebeaty@bpa.gov (503) 230-5213
Joseph Connor Bonneville Power Administration Yes COR jwconnor@bpa.gov (503) 230-3172
Douglas Corkran Bonneville Power Administration Yes Interested Party dfcorkran@bpa.gov (503) 230-7646
Michael Cushman Cascadia Conservation District Yes Contract Manager mikec@cascadiacd.org (509) 436-1601
Peggy Entzel Cascadia Conservation District No Administrative Contact peggye@cascadiacd.org (509) 436-1601
Edward Gresh Bonneville Power Administration Yes Env. Compliance Lead esgresh@bpa.gov (503) 230-5756
Michael Rickel Cascadia Conservation District Yes Supervisor miker@cascadiacd.org (509) 436-1601x103
Jason Sims Cascadia Conservation District No Interested Party jasons@cascadiacd.org (509) 436-1601
Kate Terrell US Fish and Wildlife Service (USFWS) No Interested Party kate_terrell@fws.gov (509) 548-2985
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605
Derek Van Marter Upper Columbia Salmon Recovery Board Yes Interested Party derek.vanmarter@ucsrb.org (509) 670-1462


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Permit Development A: 165. % Initiate EC permitting processess 12/31/2013
Fulfill all administrative tasks with quality products and in a timely manner. B: 119. % Coordination efforts for project design 12/31/2013 12/31/2013
Design and Specifications for 0.8 - 2.3 Restoration Project E: 175. % 0.8 - 2.3 Restoration 12/31/2013
Design and Specifications for ENFH Restoration Project F: 175. % ENFH Phase II 12/31/2013
Maintain Tyee 3A Structures G: 186. % Maintain Tyee 3A Structures 12/31/2013 12/31/2013

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 175 Produce Design
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 % Initiate EC permitting processess 09/15/2012
B 119 % Coordination efforts for project design 09/15/2012
C 185 % Periodic Status Reports for BPA 09/15/2012
D 132 (no report is required per COTR) 09/15/2012
E 175 % 0.8 - 2.3 Restoration 09/15/2012
F 175 % ENFH Phase II 09/15/2012
G 186 % Maintain Tyee 3A Structures 08/20/2012