SOW Report
Contract 61797: 1998-019-00 EXP WIND RIVER WATERSHED USFS
Project Number:
Title:
Wind River Watershed
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Gorge Wind 100.00%
Contract Number:
61797
Contract Title:
1998-019-00 EXP WIND RIVER WATERSHED USFS
Contract Continuation:
Previous: Next:
57337: 1998-019-00 EXP WIND RIVER WATERSHED USFS
  • 65582: 1998-019-00 EXP WIND RIVER WATERSHED USFS
Contract Status:
Closed
Contract Description:
The Wind River Watershed project is a collaborative effort to restore wild steelhead in the Wind River.  The four agencies forming the nucleus of this partnership include the US Forest Service (FS), Washington Department of Fish and Wildlife (WDFW), U.S. Geological Survey Columbia River Research Lab (CRRL), and Underwood Conservation District (UCD).  This partnership was established in the early 1990's and with support from BPA, has continued to conduct important habitat, research, monitoring and coordination activities across the subbasin.  The project works at multiple levels to identify and characterize key limiting habitat factors in the Wind River, to restore degraded habitats and watershed processes, to measure, track and document fish populations, life histories, and interactions, and to share information across agency and non-agency boundaries.

This contract funds continued habitat restoration within the Wind River watershed.  In FY13, a portion of the USFS budget ($30,000) has been moved to UCD to help cover work on the Little Wind River Restoration project.  The USFS contract for FY2013 includes continued operation of the Wind River Gage to support all of the habitat and monitoring efforts underway across the watershed.  The contract will also help fund the following work items:  1) work to enhance access to a side channel in the Hemlock Reach of Lower Trout Creek;  2) preparation of a subcontract that will result in removal of a culvert and installation of a bridge at Layout Creek on Forest Road 4300;  3) monitoring of channel conditions at the Martha Creek Dam removal project site; and  4) assessment of instream wood placement opportunities in Trout Creek upstream of the Hemlock site..
Account Type(s):
Expense
Contract Start Date:
06/01/2013
Contract End Date:
05/31/2014
Current Contract Value:
$45,766
Expenditures:
$45,766

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Erin Black US Forest Service (USFS) No Supervisor ekblack@fs.fed.us (509) 395-3411
Bengt Coffin (USFS) US Forest Service (USFS) Yes Contract Manager bcoffin@fs.fed.us (509) 395-3425
Edward Gresh Bonneville Power Administration Yes Env. Compliance Lead esgresh@bpa.gov (503) 230-5756
Mary Haight Bonneville Power Administration Yes COR mthaight@bpa.gov (503) 230-3112
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Khanida Mote Bonneville Power Administration Yes Contracting Officer kpmote@bpa.gov (503) 230-4599
Gloria Perez US Forest Service (USFS) No Administrative Contact gperez@fs.fed.us (360) 891-5168


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Fulfill all administrative tasks with quality products and in a timely manner. B: 119. Manage Wind River Project 05/30/2014 05/30/2014
Complete Environmental Compliance C: 165. Complete All Contract EC 11/30/2013 11/30/2013
Attach Progress Report in Pisces D: 132. Submit Progress Report for the period (Dec 2010) to (Dec 2011) 05/31/2014
Attach Progress Report in Pisces E: 132. Submit Progress Report for the period (Jan 2012) to (Dec 2013) 05/31/2014
Share project information F: 191. Share project activity and progress with partner agencies 05/31/2014 05/31/2014
Data collection G: 157. Operate and maintain Wind River Gage 05/31/2014 05/31/2014
Provide data regionally H: 159. Develop plan to provide data regionally 05/31/2014 05/31/2014
Monitoring report I: 157. Monitor for fish passage at Martha Creek Dam removal site 05/31/2014 05/31/2014
Instream project design criteria J: 29. Complete pre-NEPA field reviews for habitat improvement work in Lower Trout Creek 02/28/2014 03/31/2014
Contract for culvert removal and bridge installation K: 184. Complete contract prep and receive final permits for bridge installation 04/30/2014 04/30/2014
Enhanced side channel L: 30. Enhance use of side channel at Hemlock reach of Trout Creek 09/30/2013 09/30/2013

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Lower Columbia River DPS (Threatened)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 184 Install Fish Passage Structure
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 159 Transfer/Consolidate Regionally Standardized Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 06/01/2013
B 119 Manage Wind River Project 06/01/2013
C 165 Complete All Contract EC 06/01/2013
D 132 Submit Progress Report for the period (Dec 2010) to (Dec 2011) 06/01/2013
E 132 Submit Progress Report for the period (Jan 2012) to (Dec 2013) 06/01/2013
F 191 Share project activity and progress with partner agencies 06/01/2013
G 157 Operate and maintain Wind River Gage 06/01/2013
H 159 Develop plan to provide data regionally 06/01/2013
I 157 Monitor for fish passage at Martha Creek Dam removal site 06/01/2013
J 29 Complete pre-NEPA field reviews for habitat improvement work in Lower Trout Creek 06/01/2013
K 184 Complete contract prep and receive final permits for bridge installation 06/01/2013
L 30 Enhance use of side channel at Hemlock reach of Trout Creek 05/08/2013