| Province | Subbasin | % |
|---|---|---|
| Columbia Gorge | Wind | 100.00% |
* Expenditures data includes accruals and are based on data through 30-Nov-2025.
| Full Name | Organization | Write Permission | Contact Role | Work Phone | |
|---|---|---|---|---|---|
| Edward Gresh | Bonneville Power Administration | Yes | Env. Compliance Lead | esgresh@bpa.gov | (503) 230-5756 |
| Ann Gross | Underwood Conservation District (UCD) | Yes | Administrative Contact | ann@ucdwa.org | (509) 493-1936 |
| Mary Haight | Bonneville Power Administration | Yes | COR | mthaight@bpa.gov | (503) 230-3112 |
| Carly Lemon | Underwood Conservation District (UCD) | No | Technical Contact | carly@ucdwa.org | (509) 493-1936 |
| Peter Lofy | Bonneville Power Administration | Yes | F&W Approver | ptlofy@bpa.gov | (503) 230-4193 |
| Khanida Mote | Bonneville Power Administration | Yes | Contracting Officer | kpmote@bpa.gov | (503) 230-4599 |
| Dan Richardson | Underwood Conservation District (UCD) | Yes | Contract Manager | dan@ucdwa.org | (509) 493-1936 |
| Tova Tillinghast | Underwood Conservation District (UCD) | Yes | Supervisor | tova@ucdwa.org | (509) 493-1936 |
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Funding Package - Submit Final to COTR | A: 119. Manage and Administer Projects | 02/28/2014 | 05/08/2014 | |
| Share project information | B: 191. Share Project Progress and Activities with Project Partners | 06/30/2014 | 06/30/2014 | |
| Final report uploaded to the BPA website | D: 132. Submit Annual Report for the period of July 2011 to Dec 2012 | 02/28/2014 | 04/14/2014 | |
| Attach Progress Report in Pisces | E: 132. Submit Progress Report for the period Jan 2013 to Dec 2013 | 03/15/2014 | 03/14/2014 | |
| Environmental Compliance Support | F: 165. Produce Environmental Compliance Documentation | 06/30/2014 | 06/30/2014 | |
| Up-to-date Watershed Enhancement Project List | G: 114. Identify and Develop Future Projects | 06/30/2014 | 06/30/2014 | |
| Temperature Data Stored in Water Quality Database | H: 157. Stream Temperature Monitoring | 06/30/2014 | ||
| Implement Little Wind River Construction Plans According to Project Drawings & Specifications | I: 29. Increase Habitat Complexity Construction Activities - Little Wind River | 11/01/2013 | 11/01/2013 | |
| Construction Management Complete | J: 100. Engineer Oversight - Little Wind River | 12/31/2013 | 11/01/2013 | |
| Plant Native Vegetation - Little Wind River | K: 47. Plant Native Vegetation - Little Wind River | 12/31/2013 | 11/01/2013 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Steelhead (O. mykiss) - Lower Columbia River DPS (Threatened) |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 119 | Manage and Administer Projects | 07/01/2013 | ||||||
| B | 191 | Share Project Progress and Activities with Project Partners | 07/01/2013 | ||||||
| C | 185 | Periodic Status Reports for BPA | 07/01/2013 | ||||||
| D | 132 | Submit Annual Report for the period of July 2011 to Dec 2012 | 07/01/2013 | ||||||
| E | 132 | Submit Progress Report for the period Jan 2013 to Dec 2013 | 07/01/2013 | ||||||
| F | 165 | Produce Environmental Compliance Documentation | 07/01/2013 | ||||||
| G | 114 | Identify and Develop Future Projects | 07/01/2013 | ||||||
| H | 157 | Stream Temperature Monitoring | 07/01/2013 | ||||||
| I | 29 | Increase Habitat Complexity Construction Activities - Little Wind River | 07/01/2013 | ||||||
| J | 100 | Engineer Oversight - Little Wind River | 07/01/2013 | ||||||
| K | 47 | Plant Native Vegetation - Little Wind River | 07/01/2013 |