Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 62642: 2010-077-00 EXP TUCANNON (AREA 3) BUILD - ADD LWD AND BOULDERS
Project Number:
Title:
Tucannon River Programmatic Habitat Project
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Tucannon 100.00%
Contract Number:
62642
Contract Title:
2010-077-00 EXP TUCANNON (AREA 3) BUILD - ADD LWD AND BOULDERS
Contract Continuation:
Previous: Next:
n/a
Contract Status:
Closed
Contract Description:
Project spans two contract periods over a 24 - 30 month duration covering design (Year-1) and the subsequent construction of restoration features (design implementation) in Year-2.

This contract is to complete the Implementation Phase (Year 2):  
  -- any subsequent design modifications that may be required (following review), or as an adaptation in response to changes in channel geomorphology or site conditions (since completion of the design phase)
  -- permitting
  -- environmental and cultural resource clearances, and
  -- implementation of the design (construction of improved habitat features, and actions to restore ecological function).

Summary: This contract will be used to fund the implementation of restoration actions in the Tucannon River, at Project Area 3 (RM 46.8-48.3), including: environmental compliance as needed, materials acquisition & transport, and the placement of constructed features in the Tucannon River. The project implementation schedule targeted 2013, but potential permitting delays have extended construction through 2014.  

Enhancing and restoring instream habitat in this project area will be accomplished through a variety of treatment actions in the main channel, along the banks, and within the floodplain. These treatments include construction of instream habitat features such as engineered log jams (ELJs), removal of infrastructure such as spoils material and artificial embankment, and the installation of riparian plantings.  The principal benefits of project implementation will be restoration of historic spring Chinook spawning, rearing, and migration corridor habitats.  The associated treatment of riparian areas is expected to induce naturally occurring repair, restoration, and recovery of both floodplain and riparian zone function and processes.

The primary restoration objective identified for PA 3 is to increase habitat complexity and improve channel complexity through the placement of whole conifer trees as Large Woody Debris (LWD) restoration. Project designs will be a collaborative effort with landowners United States Forest Service (USFS) and the Washington Department of Fish and Wildlife (WDFW). Implementation strategies and materials shall be consistent with operational and sizing guidelines accepted by the cooperating partnership entities.  Designs will incorporate objectives set by the Tucannon Habitat Programmatic (2010-077-00) improvement for the Tucannon River core spring Chinook spawning and rearing area by approaching the target of having one piece of LWD per active channel width.  A total of 17 structures in the form of whole tree configurations consisting of a total of 175 trees with root-wads (primarily sourced through the USFS) and up to 25 boulders measuring 3' x 4' (and another 25 smaller boulders) shall be placed into designated areas. Selection of aerial placement of materials during implementation is well suited for the characteristics associated with PA 3 due to minimal impacts to the riparian zone and channel, and to minimize our footprint or exit wound .

Design Focus:  Emphasis is on increasing in-channel complexity through the placement of LWD to promote the reduction of channel confinement.  A description of the project area with respect to existing natural processes and habitat conditions is provided in the Design Report, along with the specific physical and biological objectives that the proposed restoration features are expected to address and achieve.  In addition, the project’s contribution to the overall watershed-scale restoration plan is described.  Construction considerations, implementation cost estimates, and best management practices are included for the treatment actions proposed in the restoration plan and Design Report for Area 3.

Expected Implementation Actions (from the Design Report):  Protect the existing spring channel in the right floodplain. Install ELJs and other LWD to initiate side channel development through the left floodplain, which was recently converted to public land.  Remove levees and spoils and modify existing wood and rock structures to improve their habitat benefits and reduce impediments to natural processes.  (Re)plant adjacent floodplain and riparian areas; re-vegetate and restore disturbed construction access sites and staging areas.  

Potential Challenges:  Some trees and other existing vegetation may be disturbed in the process of gaining access to and placing the LWD structures and removing the levee.  Project actions in the downstream end of the project area from RM [46.8 to 48.3] will involve cooperation of adjacent landowners.  Because this project area is located just upstream of public agency recreation sites and infrastructure, LWD will likely require stabilization under extreme high-flow conditions to prevent it from mobilizing.
_______________________________________________

Design Phase (provided here for context):  The Year-1 contract (#60445) will have encompassed:
- a final assessment, design report, and project design,
- any subsequent design modifications (following review), and
- the initiation of permitting requirements, and environmental and cultural resources clearances, if possible.

Background:  Under prior contracts, the Columbia Conservation District (CCD) coordinated the development of a habitat restoration plan for the Tucannon River from RM-30 upstream to RM-50; the District continues to work with the Snake River Salmon Recovery Board (SRSRB), through the Tucannon River Programmatic Habitat project, to extend the restoration plan from RM-30 downstream to the confluence of the Snake River.  This Conceptual Restoration Plan (Anchor QEA, 2011) has prioritized projects into three Tiers (1-3) based on the projected effects of implementation as a benefit to Snake River spring Chinook, cost-efficiency relative to those benefits, and the feasibility of construction.  Project Area 3 was identified as a high priority, level 2 reach in the Tucannon Geomorphic Assessment. The Tucannon Coordination Committee (TCC) assigned sponsorship of this particular project to Confederated Tribes of the Umatilla Indian Reservation (CTUIR) and the Regional technical team (RTT) concurred.  The CTUIR is responsible for surveying, developing the design, permitting, obtaining clearances, implementing the project, and monitoring the subsequent restoration response.

Walla Walla Community College (WWCC) and the SRSRB received state Salmon Recovery Funding Board (SRFB) money to advance priority projects (from the Conceptual Restoration Plan) to a 30% design-stage during the 2012 field season.  The design of the Area-3 project, identified as aTier-2 priority project in the restoration plan, was advanced to a roughly 30% conceptual- level by the CTUIR project leader in the Tucannon, using Accord dollars,

The preliminary Design Plan for Project Area 3 began to describe the purpose, function, design, and construction of restoration treatments proposed for implementation in this river segment.  Between September 2012 and through the summer of 2013 the CTUIR staff (and implementation partners) advanced the development of the restoration designs to a near-final (80%) Plan and Report, pursuant to the 2013 design contract]

Status:  The prior contract will produce the engineering design report, construction specifications, and estimate of probable costs required to permit and implement the Project Area-3 Tucannon River project.  Contract staff also began to initiate and coordinate permitting requirements and environmental clearances in anticipation of design implementation and project construction in the summer of 2014.  Cultural Resource protection investigations associated with planned materials staging areas, equipment mobilization, and work-site access in particular have required immediate attention and deliberate scheduling to initiate compliance actions such as surveys, and other requirements, in order for clearances to be timely during the expected construction period.  
_______________________________________________

Future Management Considerations

Background:  The Tucannon River basin is located in Southeast Washington State in Columbia and Garfield counties.  The system-wide restoration objective for the Tucannon River is to improve habitat conditions for Endangered Species Act (ESA) listed species (Snake River Spring Chinook and Steelhead) for all life history stages.  It is expected that improved habitat conditions will lead to an increase in the abundance of listed species returning to the river.  Increasing abundance will lead to de-listing of the species, which is the overall recovery goal for the system.  Previous efforts (CCD 2004; SRSRB 2006) have identified the habitat-limiting factors associated with the decline of ESA-listed populations.

Geomorphic Implications:  LWD placement throughout the stream reach will force pools and hydraulic variability in the plane-bed channel sections, decrease instream velocities, and provide additional hydraulic complexity in the deep, incised sections. Placing ELJs in strategic locations along the left bank will promote side channel development through the former Russell property, developing a more complex channel network. Throughout the LWD placement areas, the structures will promote retention of additional LWD and bed-load that will promote building up the bed elevation over time and increasing floodplain connectivity to ease channel confinement and allow for better floodplain connectivity during high flows.

Biological Benefits:  Adding complexity to the project area via LWD will address habitat limiting factors in the mainstem by diversifying the channel and initiating side channel development. In the short term, the pools that form at the structures will increase the available area for holding in the project area. The hydraulic diversity created by the structures will provide high-flow refuge and low-flow cover for juveniles. The structures also sort bed-load sediment, leading to the formation of spawning areas. In the long term, ELJs will promote channel complexity by splitting flow and encouraging the natural processes that drive the formation of habitat elements such as pools and side channels. The availability of diverse habitats will increase the carrying capacity for juvenile salmonids and increase the number of pools for holding adults. Levee removal and modifying the existing revetment structures will increase floodplain connectivity and the ability for the channel to migrate throughout the valley. In the long term, increased floodplain connectivity will lead to better riparian conditions that drive many ecosystem processes that are beneficial to both aquatic and non-aquatic species.
Account Type(s):
Expense
Contract Start Date:
09/16/2013
Contract End Date:
12/31/2014
Current Contract Value:
$494,440
Expenditures:
$494,440

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Kris Buelow Snake River Salmon Recovery Board Yes Contract Manager kris@snakeriverboard.org (509) 392-3858
Julie Burke Umatilla Confederated Tribes (CTUIR) Yes Administrative Contact julieburke@ctuir.org (541) 429-7292
Daniel Gambetta Bonneville Power Administration Yes Env. Compliance Lead dagambetta@bpa.gov (503) 230-3493
Brenda Heister Bonneville Power Administration Yes Contracting Officer bsheister@bpa.gov (503) 230-3531
Eric Hoverson Umatilla Confederated Tribes (CTUIR) Yes Contract Manager erichoverson@ctuir.org (541) 429-7555
Andre L'Heureux Bonneville Power Administration Yes COR allheureux@bpa.gov (503) 230-4482
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Steve Martin Snake River Salmon Recovery Board No Supervisor steve@snakeriverboard.org (509) 386-4748
Sean Welch Bonneville Power Administration Yes Technical Contact spwelch@bpa.gov (503) 230-7691


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Provide effective implementation of restoration design, and administration of the contract A: 119. Management of Project Implementation and Administration of the Contract 12/31/2014 12/30/2014
Environmental and Cultural Resource compliance assistance and clearance documentation B: 165. Environmental and cultural resource clearance and permitting 12/31/2014 06/19/2014
Review and adjustment to design report; produce revised/final construction or site plan C: 175. Design Specifications and Engineering (Completion & Adjustments): Area-03 06/30/2014 12/31/2013
Add LWD & boulders habitat to the Tucannon River, RM 46.8-48.3 D: 29. Add LWD & boulders habitat to the Tucannon River, RM 46.8-48.3 09/30/2014 08/25/2014
Side Channel Development E: 30. Perennial and Ephemeral Side Channel Development 09/30/2014 08/25/2014

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 175 Produce Design
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Management of Project Implementation and Administration of the Contract 09/01/2013
B 165 Environmental and cultural resource clearance and permitting 04/01/2013
C 175 Design Specifications and Engineering (Completion & Adjustments): Area-03 09/01/2013
D 29 Add LWD & boulders habitat to the Tucannon River, RM 46.8-48.3 06/15/2014
E 30 Perennial and Ephemeral Side Channel Development 06/15/2014
F 132 Report encompassed in yearly Programmatic reporting for the Tucannon (#2010-077-00) 09/16/2013
G 185 Periodic Status Reports for BPA 05/01/2013