Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 62978: 1995-009-00 EXP LAKE ROOSEVELT NET PENS
Project Number:
Title:
Lake Roosevelt Rainbow Trout Net Pens
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Intermountain Columbia Upper 100.00%
Contract Number:
62978
Contract Title:
1995-009-00 EXP LAKE ROOSEVELT NET PENS
Contract Continuation:
Previous: Next:
58769: 1995-009-00 EXP LAKE ROOSEVELT NET PENS
  • 66266: 1995-009-00 EXP LAKE ROOSEVELT NET PENS
Contract Status:
Closed
Contract Description:
The Lake Roosevelt Volunteer Net Pen Program has a primary objective of rearing and releasing 750,000 catchable rainbow trout annually with a target of approximately 200,000 fish harvested by anglers each year.  The program helps to mitigate for the loss of salmon in the blocked waters above Grand Coulee Dam.  Using volunteers for work, feeding, and construction of pens helps reduce the cost of this operation.
Account Type(s):
Expense
Contract Start Date:
10/01/2013
Contract End Date:
09/30/2014
Current Contract Value:
$182,644
Expenditures:
$182,644

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Grant
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Obtain Permits A: 165. Obtain Necessary Permits 09/30/2014 09/30/2014
Rear 750000 juvenile: fish B: 66. Transport Fish to Individual Net Pens 05/23/2014 06/02/2014
Release 750,000 rainbow trout C: 176. Rear fish in net pens 06/28/2014 06/02/2014
Maintain operation/safety of net pens D: 61. Insure Operational Net Pen Readiness 09/30/2014 09/30/2014
Attach guideline to Pisces report E: 174. Create Monthly Guideline 09/30/2014 09/30/2014
Coordinate with those in umbrella program F: 99. Lake Roosevelt Fisheries Coordination 09/30/2014 09/30/2014
All administrative tasks fulfilled with timely quality products G: 119. Project Execution 09/30/2014 09/30/2014
Attach Progress Report in Pisces H: 132. Submit Progress Report for the period (Oct. 2012)to (Sept.2013) 01/09/2014 12/31/2013

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Trout, Rainbow (Oncorhynchus mykiss)
  • 1 instance of WE 176 Produce Hatchery Fish
  • 1 instance of WE 66 Trap/Collect/Hold/Transport Fish - Hatchery
  • 1 instance of WE 61 Maintain Artificial Production Facility/Infrastructure
  • 1 instance of WE 174 Produce Plan

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Obtain Necessary Permits 10/01/2013
B 66 Transport Fish to Individual Net Pens 06/13/2013
C 176 Rear fish in net pens 10/01/2013
D 61 Insure Operational Net Pen Readiness 06/13/2013
E 174 Create Monthly Guideline 06/13/2013
F 99 Lake Roosevelt Fisheries Coordination 10/01/2013
G 119 Project Execution 10/01/2013
H 132 Submit Progress Report for the period (Oct. 2012)to (Sept.2013) 10/01/2013
I 185 Periodic Status Reports for BPA 10/01/2013