Contract 63615: 1987-100-02 EXP UMATILLA ANAD FISH HABITAT - ODFW
Project Number:
Title:
Umatilla Anadromous Fish Habitat-Oregon Department of Fish and Wildlife (ODFW)
Stage:
Closed
Area:
Province Subbasin %
Columbia Plateau Umatilla 100.00%
Contract Number:
63615
Contract Title:
1987-100-02 EXP UMATILLA ANAD FISH HABITAT - ODFW
Contract Continuation:
Previous: Next:
60131: 1987-100-02 EXP UMATILLA ANAD FISH HABITAT - ODFW
  • 67546: 1987-100-02 EXP UMATILLA ANAD FISH HABITAT - ODFW
Contract Status:
Closed
Contract Description:
The Umatilla Anadromous Fish Habitat Program (UAFHP) is responsible for the protection, enhancement, and rehabilitation of stream ecosystems on private lands within the Umatilla River Subbasin.  Project activities are implemented under long-term agreements with landowners.  Past activities include the construction of grazing control fences and off-channel watering facilities, fish passage barrier remediation, channel rehabilitation, native plant enhancement on riparian areas and management of noxious weeds.

Proposed activities for FY 2013-2014 by the UAFHP include Phase I - Engineering surveys and designs and possibly Phase II - project Implementation (upon funding) to remove one abandon irrigation dam in Birch Creek at Hoeft property. These project will include stream channel rehabilitation, removal of noxious weeds, and planting of native vegetation. With  the inventory of fish passage obstructions in Birch Creek Watershed done in 2011, negotiations with landowners to remove concrete irrigation dams and stabilize stream banks and channel  on Birch Creek Watershed will continue in order to accomplish projects in Phase I -Technical Assistance for Engineering surveys and designs. The UAFHP also proposes to maintain 336.47 acres of riparian and stream habitat within the Umatilla River Subbasin.  Specifically, 14 miles of fence, 16 off-channel watering facilities, and 130 acres of native vegetation will be maintained to meet program objectives.  Also, two surface flow monitoring systems and 9 temperature probes will be operated and maintained throughout the contract period to monitor the status and trends of water temperature, stream flows and fish habitat in the Birch and Meacham Creek watersheds.
Account Type(s):
Expense
Contract Start Date:
10/01/2013
Contract End Date:
09/30/2014
Current Contract Value:
$295,703
Expenditures:
$295,703

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
All administrative tasks fulfilled with timely quality products B: 119. Umatilla Anadromous Fish Habitat Program management 09/30/2014 09/30/2014
Environmental Compliance for FY 2014 C: 165. Environmental Compliance for 2013-2014 09/30/2014 09/30/2014
Watershed and Habitat Restoration Outreach and Education D: 99. Watershed and Habitat Restoration Outreach and Education 09/30/2014 09/30/2014
Identify and Select Projects in the Umatilla River Subbasin E: 114. Identify and Select Projects in the Umatilla River Subbasin 09/30/2014 09/30/2014
Maintain Fences in Riparian Areas F: 186. Maintain Fences in Riparian Areas 09/30/2014 09/30/2014
Maintain Instream Structures G: 186. Maintain Instream Structures on 9 Birch Creek locations 09/30/2014 09/30/2014
Plant riparian native tree species at 9 properties in Birch Creek Watershed H: 47. Plant riparian tree species on 9 Properties along Main Stem, East and West Birch Creek 09/30/2014 12/12/2013
Operate and Maintain Flow Gauging Stations I: 157. Operate and Maintain Flow Gauging Stations 09/30/2014 09/30/2014
Effectiveness Monitoring J: 157. Effectiveness Monitoring 09/30/2014 09/30/2014
FY2013 (Oct 2012-Sept 2013) Annual Progress Report K: 132. Annual Progress Report for FY2013 activities (Oct 2012 - Sep 2013) 05/16/2014 05/16/2014
Removal of One Concrete Irrigation Dam in Birch Creek Main Stem L: 84. Hoeft Project in Birch Creek Main Stem One Concrete Irrigation Dam Removal 09/30/2014 09/30/2014
Maintain Riparian Vegetation along East, West and Main Stem Birch Creek M: 198. Maintain Riparian Vegetation along East, West and Main Stem Birch Creek 01/31/2014 01/31/2014
Plant Native Riparian Trees, Cutting Willows and Grasses in the Riparian Area of Hamby Project N: 47. Plant Riparian Vegetation at Hamby Project in West Birch Creek 01/31/2014 12/12/2013
Maintain Riparian Vegetation at the headwaters of Meacham Creek O: 186. Maintain Habitat Structure (fence) at headwaters of Meacham Creek 09/30/2014 09/30/2014

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 198 Maintain Vegetation
  • 3 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 47 Plant Vegetation
  • 1 instance of WE 84 Remove/Install Diversion
  • 1 instance of WE 114 Identify and Select Projects
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 10/01/2013
B 119 Umatilla Anadromous Fish Habitat Program management 10/01/2013
C 165 Environmental Compliance for 2013-2014 10/01/2013
D 99 Watershed and Habitat Restoration Outreach and Education 10/01/2013
E 114 Identify and Select Projects in the Umatilla River Subbasin 10/01/2013
F 186 Maintain Fences in Riparian Areas 09/20/2013
G 186 Maintain Instream Structures on 9 Birch Creek locations 09/20/2013
H 47 Plant riparian tree species on 9 Properties along Main Stem, East and West Birch Creek 09/20/2013
I 157 Operate and Maintain Flow Gauging Stations 09/20/2013
J 157 Effectiveness Monitoring 09/20/2013
K 132 Annual Progress Report for FY2013 activities (Oct 2012 - Sep 2013) 10/01/2013
L 84 Hoeft Project in Birch Creek Main Stem One Concrete Irrigation Dam Removal 05/30/2014
M 198 Maintain Riparian Vegetation along East, West and Main Stem Birch Creek 10/01/2013
N 47 Plant Riparian Vegetation at Hamby Project in West Birch Creek 10/01/2013
O 186 Maintain Habitat Structure (fence) at headwaters of Meacham Creek 10/01/2013