Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 64152: 2003-017-00 EXP ISEMP - SO FORK RESEARCH
Project Number:
Title:
Integrated Status and Effectiveness Monitoring Program (ISEMP)
BPA PM:
Stage:
Complete
Area:
Province Subbasin %
Basinwide - 100.00%
Contract Number:
64152
Contract Title:
2003-017-00 EXP ISEMP - SO FORK RESEARCH
Contract Continuation:
Previous: Next:
59513: 2003-017-00 EXP ISEMP - SO FORK RESEARCH
  • 67443: 2003-017-00 EXP ISEMP - SO FORK RESEARCH
Contract Status:
Closed
Contract Description:
Note: This contract has no inventory, nothing carried over, and no equipment purchases planned.
Note2: All EC issues are covered by NMFS Section 7,  on the overall Bridge Creek Restoration and Monitoring Project, Wheeler County, OR.

Contract Description: The Integrated Status and Effectiveness Monitoring Program (ISEMP, 2003-017-00) is an ongoing collaborative effort to design, test, implement and evaluate Status and Trends Monitoring for salmon and steelhead populations and their habitat, and watershed-scale Effectiveness Monitoring for management actions impacting salmon and steelhead populations and habitat in the Interior Columbia River Basin.

ISEMP explicitly addresses work requirements of many 2008 FCRPS Biological Opinion RPAs (56.1, 56.2, 56.3, 57.1, 57.2, 57.3, 57.4, 57.5) and is directly related to additional 2008 FCRPS Biological Opinion implementation strategy requirements and recommendations. ISEMP takes a pilot-project approach to the research and development of monitoring by implementing experimental programs in several major subbasins of the Interior Columbia: the Wenatchee, Entiat, Methow, John Day, South Fork Salmon and Lemhi River basins. The overall goal of the project is to provide regional salmon management agencies with the data, information and tools necessary to design efficient and effective monitoring programs.

Specifically, ISEMP generates quantitative guidance on and examples of: the robustness and limitations of population and habitat monitoring protocols, indicators and metrics; sampling design approaches for the distribution of monitoring effort in time and space; analytical approaches to the evaluation of monitoring data, information and programs; effective data management and communication designs that support the use, standardization and compilation of implementation, compliance, status, trends and effectiveness monitoring data by regional data generators and decision makers; and finally the design and implementation of watershed-scale restoration actions to maximize both the biological impact and associated learning opportunities resulting from the design and implementation strategy.

Through its work to date, ISEMP has developed expertise in the coordination and implementation of large-scale monitoring data collection programs. Applying this experience, ISEMP coordinates the installation, maintenance and calibration of in-stream PIT tag arrays across the Snake River basin and is designing and coordinating the implementation of a Columbia River basin-wide stream habitat status and trends monitoring. These programmatic implementation facets of ISEMP leverage previous experience with logistics and social factors to effectively implement comprehensive, standardized monitoring research and development at an unprecedented scale.  

This contract is one of several contracts that will implement this project.  Each contract is responsible for an end of contract progress report.  Additionally, a project level "synthesis report" will also be produced under this project and data and analysis from this contract will be utilized in the production of that project level report.  The synthesis report is a deliverable under the Terraqua contract (not this contract) under this project.

SFR facilitates data flow, work flow and management (protocol development, data entry, data qa/qc, data delivery, GIS data management and database output) for the ISEMP pilot projects. SFR also participates as a project coordinator and data analyst within ISEMP.
Account Type(s):
Expense
Contract Start Date:
12/01/2013
Contract End Date:
11/30/2014
Current Contract Value:
$505,000
Expenditures:
$505,000

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract
Pricing Method:
Time and Materials
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Christopher Beasley Quantitative Consultants Inc Yes Interested Party chris@qcinc.org (360) 620-2883
Nick Bouwes Eco Logical Research Yes Interested Party nbouwes@gmail.com (435) 760-0771
David Byrnes Bonneville Power Administration Yes COR dmbyrnes@bpa.gov (503) 230-3171
Israel Duran Bonneville Power Administration Yes Env. Compliance Lead induran@bpa.gov (503) 230-3967
Chris Jordan National Oceanic and Atmospheric Administration Yes Supervisor chris.jordan@noaa.gov (541) 754-4629
Paul Krueger Bonneville Power Administration Yes F&W Approver pqkrueger@bpa.gov (503) 230-5723
Pamela Nelle Terraqua, Inc. Yes Interested Party pamela@terraqua.biz (509) 885-8143
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605
Carol Volk South Fork Research, Inc. Yes Contract Manager carol@southforkresearch.org (206) 240-0301
Jody White Quantitative Consultants Inc Yes Interested Party jody@qcinc.org (208) 860-5269


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Documentation of Environmental Compliance B: 165. Provide Environmental Compliance Documentation for Work Element M 11/30/2014 11/30/2014
EA for Bridge Creek IMW restoration planned for 2014 C: 165. NEPA Consultation for Bridge Creek IMW for 2014 11/30/2014 11/30/2014
Review documents produced by ISEMP personnel and meeting participation D: 174. Participate in RME planning process for pilot basins 11/15/2014 11/15/2014
QA report for each dataset reviewed E: 161. QA and Summary of ISEMP data 11/30/2014 11/30/2014
Data summary and QAQC support F: 161. QA and summary of Bridge Creek data 11/30/2014 10/30/2014
Field data in electronic format G: 157. Collect field data for monitoring vegetation in Bridge Creek 11/01/2014 11/01/2014
Summary of Bridge Creek 2013 data H: 162. Bridge Creek analysis of climate, groundwater, and riparian planting data 11/30/2014 11/30/2014
Data in Access databases and annual report of riparian planting activities I: 47. Plant and fence riparian stakes along Bridge Creek 06/01/2014 06/01/2014
Website updates and STEM website summary queries J: 161. ISEMP website development and updates 11/30/2014 11/30/2014
Completion of modeling projects K: 162. Modeling and analysis of ISEMP fish data 11/30/2014 11/30/2014
Summary of methods used to expand habitat data collection. L: 161. Development of GIS data for use in analytical models 11/30/2014 11/30/2014
Journal article documenting GIS tool development for habitat data collection M: 183. Article documenting GIS tool development for habitat monitoring 11/30/2014 11/30/2014
Produce article documenting riparian monitoring for Bridge Creek N: 183. Article documenting riparian monitoring methods for Bridge Creek 11/30/2014 11/30/2014
Summary of comparison of continuous habitat data along hydrographic networks O: 162. Analysis of continuous habitat data along hydrographic networks (GIS) 11/30/2014 11/30/2014
Summary of application of GIS contextual framework for ISEMP pilot subbasins P: 161. Contextual GIS data framework 11/30/2014 11/30/2014
All administrative tasks fulfilled with timely quality products Q: 119. Manage and Administer ISEMP tasks, contracts, and subcontracts for SFR 11/30/2014 11/30/2014
Attach Progress Report in Pisces R: 132. Annual report covering the contract performance period of 12/1/2012 to 11/30/2013 10/31/2014 10/31/2014
Attach Progress Report in Pisces U: 132. Submit Final Progress Report for 12/1/2011 to 11/30/2012 08/01/2014 08/01/2014

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (Oncorhynchus tshawytscha) - All Populations
  • 1 instance of WE 174 Produce Plan
  • 3 instances of WE 161 Disseminate Raw/Summary Data and Results
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 161 Disseminate Raw/Summary Data and Results
  • 2 instances of WE 162 Analyze/Interpret Data
Chinook (O. tshawytscha) - Snake River Fall ESU (Threatened)
  • 1 instance of WE 161 Disseminate Raw/Summary Data and Results
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 2 instances of WE 183 Produce Journal Article
  • 2 instances of WE 161 Disseminate Raw/Summary Data and Results
  • 2 instances of WE 162 Analyze/Interpret Data
Chinook (O. tshawytscha) - Snake River Spring/Summer (not listed)
  • 2 instances of WE 183 Produce Journal Article
  • 2 instances of WE 161 Disseminate Raw/Summary Data and Results
  • 1 instance of WE 162 Analyze/Interpret Data
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 2 instances of WE 183 Produce Journal Article
  • 1 instance of WE 161 Disseminate Raw/Summary Data and Results
  • 1 instance of WE 162 Analyze/Interpret Data
Chinook (O. tshawytscha) - Upper Columbia River Summer/Fall ESU
  • 2 instances of WE 183 Produce Journal Article
  • 1 instance of WE 161 Disseminate Raw/Summary Data and Results
  • 1 instance of WE 162 Analyze/Interpret Data
Steelhead (Oncorhynchus mykiss) - All Populations
  • 1 instance of WE 174 Produce Plan
  • 3 instances of WE 161 Disseminate Raw/Summary Data and Results
Steelhead (O. mykiss) - Lower Columbia River DPS (Threatened)
  • 1 instance of WE 162 Analyze/Interpret Data
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 47 Plant Vegetation
  • 2 instances of WE 183 Produce Journal Article
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 2 instances of WE 161 Disseminate Raw/Summary Data and Results
  • 3 instances of WE 162 Analyze/Interpret Data
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 2 instances of WE 183 Produce Journal Article
  • 2 instances of WE 161 Disseminate Raw/Summary Data and Results
  • 2 instances of WE 162 Analyze/Interpret Data
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 2 instances of WE 183 Produce Journal Article
  • 2 instances of WE 161 Disseminate Raw/Summary Data and Results
  • 2 instances of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 12/01/2013
B 165 Provide Environmental Compliance Documentation for Work Element M 12/01/2013
C 165 NEPA Consultation for Bridge Creek IMW for 2014 12/01/2013
D 174 Participate in RME planning process for pilot basins 10/21/2013
E 161 QA and Summary of ISEMP data 12/01/2013
F 161 QA and summary of Bridge Creek data 12/01/2013
G 157 Collect field data for monitoring vegetation in Bridge Creek 10/21/2013
H 162 Bridge Creek analysis of climate, groundwater, and riparian planting data 12/01/2013
I 47 Plant and fence riparian stakes along Bridge Creek 10/21/2013
J 161 ISEMP website development and updates 12/01/2013
K 162 Modeling and analysis of ISEMP fish data 12/01/2013
L 161 Development of GIS data for use in analytical models 12/01/2013
M 183 Article documenting GIS tool development for habitat monitoring 12/01/2013
N 183 Article documenting riparian monitoring methods for Bridge Creek 12/01/2013
O 162 Analysis of continuous habitat data along hydrographic networks (GIS) 12/01/2013
P 161 Contextual GIS data framework 12/01/2013
Q 119 Manage and Administer ISEMP tasks, contracts, and subcontracts for SFR 12/01/2013
R 132 Annual report covering the contract performance period of 12/1/2012 to 11/30/2013 12/01/2013
S 132 Special Report: Annual FCRPS BiOp RM&E reports covering the period January 2013 to March 2014. 12/01/2013
T 132 Update ISEMP Lessons Learned Synthesis Report 12/01/2013
U 132 Submit Final Progress Report for 12/1/2011 to 11/30/2012 12/01/2013