Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 64583: 1992-026-01 EXP BIOP UPPER GRANDE RONDE SMALL WOOD AND PODS
Project Number:
Title:
Grande Ronde Model Watershed
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Blue Mountain Grande Ronde 100.00%
Contract Number:
64583
Contract Title:
1992-026-01 EXP BIOP UPPER GRANDE RONDE SMALL WOOD AND PODS
Contract Continuation:
Previous: Next:
n/a
Contract Status:
Closed
Contract Description:
Introduction

The Upper Grande Ronde River is spawning and rearing habitat for Snake River Basin summer steelhead, Snake River Basin spring chinook salmon, bull trout and redband trout.  The summer steelhead, spring/summer chinook and bull trout are federally listed under ESA as threatened species. Redband trout are on the Regional Forester's Sensitive Species List.

Historic timber harvest and roading removed larger conifers from the valley bottom, reducing the future recruitment of large wood to the stream. This project will rehabilitate the floodplain and instream habitat through planting, large wood/boulder additions, streambottom road obliteration, and dispersed campground rehabilitation.

Location:  The Upper Grande Ronde River Small Wood and Plant Protection Project is located on the Grande Ronde River, a tributary to the Snake River. The project is located on 10.00 miles of the Grande Ronde River within the past Upper Grande Ronde River Woody Debris and Mine Tailing Project Areas (T 4S, R 35E, S 14, 23, 26, 35; T 5S, R 35E, S 1,2,12,13; T 5S, R 36E, S18; T 6S, R 36E, S 4, 9 & 10).  The project is located within the Upper Grande Ronde River (1706010401); Warm Springs Creek – Grande Ronde River (170601040109), Meadowbrook – Grande Ronde River (170601040103) & Tanner Gulch – Grande Ronde River (170601040101); Union County.  

Specific Actions:  The Upper Grande Ronde Small Woody Debris Project would place wood within 8.00 miles of the upper Grande Ronde River for a total of 80 dump truck loads.  Small wood would be placed around plantings within 2 miles of the mine tailings project.  Two small elk/deer exclosures will be constructed across the river within the mine tailings area.   Seeding and mulching would occur where disturbance and/or erosion potential occurs.

Project Objectives:  Improve spring/summer chinook habitat, summer steelhead habitat and bull trout, specifically through improving or increasing the following habitat elements.

•   Increase quantity and quality of pools within the Upper Grande Ronde River
•   Increase fish cover
•   Increase habitat complexity
•   Increase residual pool depth
•   Improve floodplain function
•   Improve riparian vegetation vigor

Benefits:  Increased quantity and quality of pools; increased fish cover; increased habitat complexity; increased forage availability; improved riparian/wetland communities; and increased spawning gravel recruitment.
Account Type(s):
Expense
Contract Start Date:
04/01/2014
Contract End Date:
05/31/2015
Current Contract Value:
$149,892
Expenditures:
$149,892

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Daniel Gambetta Bonneville Power Administration No Env. Compliance Lead dagambetta@bpa.gov (503) 230-3493
Bill Gamble US Forest Service (USFS) No Administrative Contact bgamble@fs.fed.us (541) 962-8582
Tracy Hauser Bonneville Power Administration Yes COR tlhauser@bpa.gov (503) 230-4296
Aric Johnson US Forest Service (USFS) No Supervisor ajjohnson@fs.fed.us (541) 962-8517
Khanida Mote Bonneville Power Administration Yes Contracting Officer kpmote@bpa.gov (503) 230-4599
Joe Platz US Department of Agriculture (USDA) Yes Contract Manager joe.platz@usda.gov (541) 962-8571
John Skidmore Bonneville Power Administration Yes F&W Approver jtskidmore@bpa.gov (503) 230-5494
Jesse Steele Grande Ronde Model Watershed Foundation No Interested Party jesse@grmw.org (541) 663-0570
Connar Stone Grande Ronde Model Watershed Foundation No Interested Party connar@grmw.org (541) 663-0570


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Environmental Compliance complete A: 165. Environmental Compliance 05/04/2015 05/04/2015
Wood structure placement B: 29. Wood structure construction # 1 05/04/2015 09/30/2014
Wood structure placement # 2 C: 29. Wood structure construction # 2 05/04/2015 09/30/2014
Wood structure placement # 3 D: 29. Wood structure construction # 3 05/04/2015 09/30/2014
Wood structure placement # 4 E: 29. Wood structure construction # 4 05/04/2015 09/30/2014
Small wood placement to protect plantings F: 47. Small wood placement to protect plantings 05/31/2015 09/17/2014
Exclosure #1 G: 47. Install exclosure fence #1 05/04/2015 10/31/2014
Exclosure #2 H: 47. Install exclosure fence #2 05/31/2015 10/31/2014
Seed and mulch disturbed areas I: 47. Seed/ mulch disturbed areas 05/04/2015 10/31/2014
Successful Project Administration J: 119. Project Administration 05/04/2015 05/04/2015
Attach Completion Report in Pisces L: 132. Submit Completion Report - April 2014 - May 2015 05/29/2015

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 4 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 4 instances of WE 47 Plant Vegetation
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 4 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 4 instances of WE 47 Plant Vegetation

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Environmental Compliance 04/01/2014
B 29 Wood structure construction # 1 05/21/2014
C 29 Wood structure construction # 2 05/21/2014
D 29 Wood structure construction # 3 05/21/2014
E 29 Wood structure construction # 4 05/21/2014
F 47 Small wood placement to protect plantings 05/21/2014
G 47 Install exclosure fence #1 05/21/2014
H 47 Install exclosure fence #2 05/21/2014
I 47 Seed/ mulch disturbed areas 05/21/2014
J 119 Project Administration 04/01/2014
K 185 Quarterly Status Reports 04/01/2014
L 132 Submit Completion Report - April 2014 - May 2015 04/01/2014