| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Project permits and environmental compliance documents and authorizations. | A: 165. Environmental Compliance | 10/01/2014 | 10/01/2014 | |
| Submit 6-Ranch Project 2 drawings and specifications to BPA | B: 175. Survey and final design package | 07/11/2014 | 07/11/2014 | |
| 31 woody debris and habitat structures added to the Wallowa River channel | C: 29. Install large wood to the Wallowa River channel | 12/31/2015 | 12/21/2015 | |
| 6 meander bends added to the Wallowa River channel - 250 ft of river channel | D: 30. Restoration of 250 ft River Channel Construction - Re-meander | 12/31/2015 | 12/21/2015 | |
| Construct Side channel A - Wallowa River floodplain | E: 181. Side Channel and Wetland Enhancement - Side Channel A | 12/31/2015 | 12/21/2015 | |
| Construct Side channel D - Wallowa River floodplain | F: 181. Side Channel and Wetland Enhancement - Side Channel D | 12/31/2015 | 12/21/2015 | |
| Install Juniper revetments in 2 side channels | G: 55. Juniper revetments - Wetlands/2 Side Channels | 12/31/2015 | 12/21/2015 | |
| 3,950 plantings installed at the 6-Ranch 2 project site | H: 47. Riparian Plant Restoration | 12/31/2015 | 12/21/2015 | |
| Install 3 livestock watering troughs | I: 34. Livestock watering troughs | 12/31/2015 | ||
| Install fence on pasture 1 and implement livestock management plan. | J: 40. Livestock management plan and fencing - Pasture 1 | 12/31/2015 | 12/21/2015 | |
| Install fence on pasture 2 and implement livestock management plan. | K: 40. Fencing - Pasture 2 | 12/31/2015 | 12/21/2015 | |
| Install fence on riparian pasture, pasture #3 | L: 40. Fencing - Riparian Pasture 3 | 12/31/2015 | 12/31/2015 | |
| Successfully administer project | M: 119. Contract management & administration | 12/31/2015 | 12/21/2015 | |
| Attach Completion Report in Pisces | N: 132. Submit Completion Report - May 2014 - December 2015 | 12/15/2015 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened) |
|
| Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 165 | Environmental Compliance | 10/01/2013 | ||||||
| B | 175 | Survey and final design package | 05/01/2014 | ||||||
| C | 29 | Install large wood to the Wallowa River channel | 12/08/2014 | ||||||
| D | 30 | Restoration of 250 ft River Channel Construction - Re-meander | 12/08/2014 | ||||||
| E | 181 | Side Channel and Wetland Enhancement - Side Channel A | 12/08/2014 | ||||||
| F | 181 | Side Channel and Wetland Enhancement - Side Channel D | 12/08/2014 | ||||||
| G | 55 | Juniper revetments - Wetlands/2 Side Channels | 12/08/2014 | ||||||
| H | 47 | Riparian Plant Restoration | 12/08/2014 | ||||||
| I | 34 | Livestock watering troughs | 12/15/2014 | ||||||
| J | 40 | Livestock management plan and fencing - Pasture 1 | 12/15/2014 | ||||||
| K | 40 | Fencing - Pasture 2 | 12/15/2014 | ||||||
| L | 40 | Fencing - Riparian Pasture 3 | 12/15/2014 | ||||||
| M | 119 | Contract management & administration | 10/01/2013 | ||||||
| N | 132 | Submit Completion Report - May 2014 - December 2015 | 10/01/2013 | ||||||
| O | 185 | Quarterly Status Reports | 10/01/2013 |