Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 65731: 2010-034-00 EXP UPPER COLUMBIA SPRING CHINOOK
Project Number:
Title:
Upper Columbia Spring Chinook and Steelhead Juvenile and Adult Abundance, Productivity and Spatial Structure Monitoring
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Cascade Entiat 5.00%
Methow 35.00%
Okanogan 25.00%
Wenatchee 35.00%
Contract Number:
65731
Contract Title:
2010-034-00 EXP UPPER COLUMBIA SPRING CHINOOK
Contract Continuation:
Previous: Next:
61740: 2010-034-00 EXP UPPER COLUMBIA SPRING CHINOOK
  • 69402: 2010-034-00 EXP UPPER COLUMBIA SPRING CHINOOK
Contract Status:
Closed
Contract Description:
CCR-35004

No Cost Time Extension.

++++++++++++++++++++++++++++++++++++


%  CCR-33756:

This contract amendment will fund the University of Idaho to assist WDFW in the set up and tuning of 10 fixed radio telemetry sites in the upper Columbia Basin.  Over the next two years, WDFW will be conducting a steelhead radio telemetry study in order to validate PIT tag based escapement estimates and estimate overwinter mortality in the Columbia River and tributaries.  During the study period, University of Idaho will be subcontracted to assist in the radio tracking, data analysis and reporting.  



+++++++++++++++++++++++++++++++++++

Studies focused on developing models to estimate spring Chinook redd observer efficiency in the Wenatchee and Methow Basins have been completed under this project and model development is ongoing and will be implemented in 2014.  A key component to all these activities is the steelhead stock assessment work at Priest Rapids Dam during which a random sample of steelhead are PIT tagged.  Escapement estimates of wild steelhead in 2011 and 2012 suggested that a greater tag rate at Priest Rapids Dam (PRD) is needed to reduce uncertainty.  In response, we increased our sampling rate from 2 day per week to 3 days per week in 2013, with the goal of obtaining a 15% tag rate.  A total of 2,308 adult steelhead were tagged at PRD in 2013, amounting to a 13.4% tag rate.  The three day a week sampling scheme will continue in 2014. By 2015, we expect to have the PIT tag array infrastructure installed and complete, except in the Okanogan, and fully develop spring Chinook and steelhead redd observer efficiency models.  

Beginning in 2015, the focus of the project will shift to radio telemetry monitoring, using fish radio and PIT tagged at Priest Rapids Dam to validate PIT tag based estimates and estimate prespawn mortality for fish that spawn in the mainstem of the Wenatchee, Entiat, Methow, and Okanogan Rivers.  Under this contract we will fully prepare to conduct the radio telemetry project.  An initial batch of radio tags will be purchased, telemetry equipment (transceivers, fixed antennas, portable antennas) will be upgraded and standardized to operate at the new recommended frequency, and all other equipment for stationary and mobile tracking will be purchased and prepared for tracking beginning in July 2015.  Upgrading and standardizing all the telemetry equipment will provide for opportunities to collaborate with other studies occurring in the Upper and Mid-Columbia River basins, providing efficiencies for multiple ongoing studies.

WDFW will be the research lead for the project and obtain all necessary environmental compliance permits for the project which includes FY14 contract requisition #'s: 272836 and 272835. Andrew Murdoch will be the point of contact for WDFW.  Colville Confederated Tribes (CCT) will be the primary contractor for the Okanogan Basin; FY14 CR #: 272836.  John Arterburn is the point of contact for the CCT.

Background on the project:

A unique, well-coordinated and standardized monitoring and evaluation program(s) exists in the Upper Columbia River Basin.  Monitoring and evaluation programs are funded by a combination of federal (BPA, BOR, USFWS), State, Tribal, and regional (PUDs) entities.    While all these various programs contribute data to estimate VSP parameters for steelhead and spring Chinook salmon, these programs also share common deficiencies related to precision and accuracy of the abundance estimates.  Existing M & E activities combined with recent advances in PIT tag technology provide an opportunity to improve the quality of the data generated in order to make proper management decisions concerning ESA listed species.  The overall objectives of the project are to: 1) estimate run escapement of hatchery and wild steelhead in each of the four primary populations, 2) estimate the precision of redd counts for both steelhead and spring Chinook and 3) evaluate the accuracy of the steelhead spawning ground survey design and determine the proportion of spawners outside the survey area.  WDFW will be the research lead for the project and obtain all necessary environmental compliance permits for the project.  Colville Confederated Tribes will be the primary contractor for the Okanogan Basin.  In 2015, we intend to initiate a steelhead radio telemetry study to independently validate estimates generated from PIT tags and to estimate steelhead population characteristics (overwinter survival, number of redds per female).  These tasks address in part or fully the critical uncertainties identified under Supplementation in the Columbia River Basin Research Plan (2006-03) and steelhead population characteristics (abundance, productivity, and ratio of hatchery fish) under the Fish and Wildlife Program.  Additionally, all of the studies in this proposal are directly consistent with RPAs for the FCRPS BiOp.

During the time period under this contract, WDFW will install a new permanent instream PIT tag detection site in the upper Chewuch River in the Methow Basin, the last permanent array in the Methow or Wenatchee River Basin to be installed under this project.  The upper Chewuch River site was scheduled to be installed under the previous contract; however, installation was delayed due to difficulties in obtaining the necessary USFS permits.  The remaining permit required to install the site should be obtained prior to initiation of this contract and the site will be installed as soon as river conditions allow. In addition, the Middle Wenatchee River instream PIT tag detection site was scheduled to be relocated under the previous contract.  The site was not relocated as the detection equipment available was not suitable for river conditions present at the proposed new site.  If further funding is obtained from outside sources a detection system may be installed at the proposed new site.  Also under this contract, WDFW will assume responsibility for the operation and maintenance of five permanent instream PIT tag detection sites in the Methow River basin.  These sites (Beaver Creek, Gold Creek, Libby Creek, Methow River at Winthrop and Chewuch River at Winthrop) were previously operated by USGS under contract with BOR.  WDFW will upgrade the exisiting monitoring equipment installed at Gold Creek and Libby Creek through funding obtained from other sources.  WDFW will also purchase multiple equipment items under this contract to serve as backups and/or replacements in the event of equipment malfunction of failure.  Having a stockpile of equipment on hand is crucial in maintaining instream PIT tag detection sites and will serve to limit any downtime due to equipment failure, thus maximizing operational time and data quality at all WDFW operated sites in the Upper Columbia River basin.
Account Type(s):
Expense
Contract Start Date:
07/01/2014
Contract End Date:
08/30/2015
Current Contract Value:
$667,158
Expenditures:
$667,158

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
EC documents obtained for this contract and for FY14 contract requisition #'s: 272835 and 272836 A: 165. Provide EC documentation to BPA 06/30/2015 06/30/2015
All administrative tasks fulfilled with timely quality products B: 119. Manage and administer project 06/30/2015 06/30/2015
Estimated number of hatchery and wild steelhead at Priest Rapids Dam C: 157. Upper Columbia steelhead stock assessment 03/31/2015 03/31/2015
Number of steelhead PIT tagged or recaptured. D: 158. PIT tag adult steelhead at Priest Rapids Dam 10/15/2014 10/15/2014
PIT tag mark and recapture data E: 159. Upload PIT tag data to PTAGIS database 06/30/2015 06/30/2015
Upper Chewuch PIT tag array F: 70. Install permanement PIT tag array 11/30/2014 09/15/2014
Operate and maintain PIT tag arrays in the Wenatchee and Methow subbasin G: 157. Operate and maintain PIT tag arrays 06/30/2015 06/30/2015
Install fixed radio telemetry sites H: 70. Install fixed radio telemetry sites at selected locations 06/30/2015 06/30/2015
Complete CY 2014 RPA Report J: 141. Other Reports for BPA 03/15/2015 03/15/2015
Produce annual technical report K: 132. Submit Progress Report 03/15/2015 03/15/2015
Submit manuscript on steelhead redd observer efficiency L: 183. Steelhead redd observer efficiency manuscript 06/30/2015 06/30/2015
Produce accessible, error-checked datasets M: 157. % Egg-to-fry survival study 06/30/2015 06/30/2015
Produce accessible, error-checked datasets N: 157. % Parr distribution and habitat utilization 06/30/2015 06/30/2015

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 1 instance of WE 183 Produce Journal Article
  • 2 instances of WE 70 Install Fish Monitoring Equipment
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 158 Mark/Tag Animals
  • 1 instance of WE 159 Transfer/Consolidate Regionally Standardized Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Provide EC documentation to BPA 07/01/2014
B 119 Manage and administer project 07/01/2014
C 157 Upper Columbia steelhead stock assessment 07/01/2014
D 158 PIT tag adult steelhead at Priest Rapids Dam 07/01/2014
E 159 Upload PIT tag data to PTAGIS database 07/01/2014
F 70 Install permanement PIT tag array 07/01/2014
G 157 Operate and maintain PIT tag arrays 07/01/2014
H 70 Install fixed radio telemetry sites at selected locations 07/01/2014
I 185 Periodic Status Reports for BPA 07/01/2014
J 141 Other Reports for BPA 07/01/2014
K 132 Submit Progress Report 07/01/2014
L 183 Steelhead redd observer efficiency manuscript 07/01/2014
M 157 % Egg-to-fry survival study 07/01/2014
N 157 % Parr distribution and habitat utilization 07/01/2014