Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 67262: 2010-086-00 EXP CROOKED/AMERICAN RIVER WATERSHED RESTORATION
Project Number:
Title:
Protect and Restore the Crooked and American River Watersheds
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Clearwater 100.00%
Contract Number:
67262
Contract Title:
2010-086-00 EXP CROOKED/AMERICAN RIVER WATERSHED RESTORATION
Contract Continuation:
Previous: Next:
64047: 2010-086-00 EXP CROOKED/AMERICAN RIVER WATERSHED RESTORATION
  • 70571: 2010-086-00 EXP CROOKED/AMERICAN RIVER WATERSHED RESTORATION
Contract Status:
Closed
Contract Description:
Contract History:

This project was originally proposed during the 2007 NPCC/BPA Provincial Review.  Although it did not receive funding during that process, it was recommended for funding as a FCRPS BiOp project.  This comprehensive watershed restoration effort focuses on mitigating and restoring limiting factors to fisheries production.  The primary limiting factors are excessive sedimentation in the spawning and rearing areas of streams, and the lack of available habitat and habitat connectivity.  These limiting factors are the result of past land management activities, including road construction, logging, and mining.  

The Nez Perce-Clearwater National Forest (NPCNF) has completed several surveys, assessments, and NEPA decision documents.  The first assessment, the South Fork Landscape Assessment, was completed in 1999.  This document provided the baseline conditions for each subwatershed as well as general recommendations for future restoration efforts.  The Crooked/American Environmental Impact Statement (EIS) evaluated a complex system of watersheds using a multidisciplinary approach.  The final product included a proposed list of specific watershed restoration projects, including the Crooked/American Watershed Restoration project.

This project is a part of the BPA, NPCNF, and Nez Perce Tribe (NPT) Watershed Restoration Partnership.  Since the NPT program’s inception, we have shared project planning and development, costs, and implementation responsibilities.  


Summary of FY 2015 Contract Implementation:
                                                                                                                                                                                                                                              
FY 2015  contract implementation will include implementing Elk Creek Culvert replacement and implementing Phase 1 bypass channel for the Crooked River Valley Rehabilitation project.   Periodic reports will be provided to BPA on the status of the contract and an annual report on accomplishments will be submitted.
Account Type(s):
Expense
Contract Start Date:
12/01/2014
Contract End Date:
11/30/2015
Current Contract Value:
$613,255
Expenditures:
$613,255

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Brenda Aguirre Bonneville Power Administration Yes Env. Compliance Lead baguirre@bpa.gov (503) 230-5928
Jenifer Harris Nez Perce Tribe Yes Contract Manager jeniferh@nezperce.org (208) 983-1290
Arleen Henry Nez Perce Tribe No Administrative Contact arleenh@nezperce.org (208) 621-3833
David Kaplowe Bonneville Power Administration Yes COR djkaplowe@bpa.gov (503) 230-5365
Amber MacLachlan Bonneville Power Administration Yes Contracting Officer almcmahon@bpa.gov (503) 230-3983
Heidi McRoberts Nez Perce Tribe Yes Supervisor heidim@nezperce.org (208) 621-3548
Emmit Taylor, Jr. Nez Perce Tribe No Supervisor emmitt@nezperce.org (208) 621-3544
Dorothy Welch Bonneville Power Administration Yes F&W Approver dwwelch@bpa.gov (503) 230-5479


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Environmental Compliance Documentation Submitted to BPA A: 165. Submit Environmental Compliance Documentation to BPA 06/14/2015 09/30/2015
Elk Creek Culvert Replaced C: 184. Elk Creek Culvert Replacement 10/30/2015 09/30/2015
Watershed Conditions Report Completed F: 115. Existing Watershed Conditions Assessment 11/30/2015
FY 2016 SOW package and FY 2015 accrual estimate G: 119. Management, Coordination, and Communication 09/11/2015 09/11/2015
Final FY 2015 annual report attached to this contract H: 132. Submit Annual Report for12/1/2014 - 11/30/15 11/30/2015 11/20/2015
Crooked River Valley Rehabilitation Project- Bypass Channel Phase 1 J: 84. Crooked River Valley Rehabilitation Bypass Channel - Phase 1 10/31/2015

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer (not listed)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 84 Remove/Install Diversion
  • 2 instances of WE 184 Install Fish Passage Structure
  • 1 instance of WE 115 Produce Inventory or Assessment
Coho (O. kisutch) - Unspecified Population
  • 1 instance of WE 84 Remove/Install Diversion
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 84 Remove/Install Diversion
  • 2 instances of WE 184 Install Fish Passage Structure
  • 1 instance of WE 115 Produce Inventory or Assessment
Lamprey, Pacific (Entosphenus tridentata)
  • 1 instance of WE 84 Remove/Install Diversion
  • 1 instance of WE 115 Produce Inventory or Assessment
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 84 Remove/Install Diversion

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Submit Environmental Compliance Documentation to BPA 12/01/2014
B 184 Big Elk Creek Culvert Replacement
C 184 Elk Creek Culvert Replacement 04/21/2015
D 180 Crooked River Valley Rehabilitation - Option 2 (Floodplain Restoration)
E 29 Crooked River Valley Rehabilitation - Option 2 (Structure Installation)
F 115 Existing Watershed Conditions Assessment 12/01/2014
G 119 Management, Coordination, and Communication 12/01/2014
H 132 Submit Annual Report for12/1/2014 - 11/30/15 12/01/2014
I 185 Periodic Status Reports for BPA 12/01/2014
J 84 Crooked River Valley Rehabilitation Bypass Channel - Phase 1 08/13/2015