Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 67742: 2008-603-00 EXP PAHSIMEROI RIVER HABITAT - OSC
Project Number:
Title:
Pahsimeroi River Habitat
BPA PM:
Stage:
Complete
Area:
Province Subbasin %
Mountain Snake Salmon 100.00%
Contract Number:
67742
Contract Title:
2008-603-00 EXP PAHSIMEROI RIVER HABITAT - OSC
Contract Continuation:
Previous: Next:
63698: 2008-603-00 EXP PAHSIMEROI RIVER HABITAT - OSC
  • 73707: 2008-603-00 EXP PAHSIMEROI RIVER HABITAT - OSC
Contract Status:
Closed
Contract Description:
This originally contract covered BPA-funded work by Idaho Department of Fish and Game (IDFG) on four projects: Flying Joseph Fish Passage Final Design, Flying Joseph Diversion Replacement Final Design, Sulphur Creek Revegetation, and the Fury Lane Bridge Construction and Installation.  It also provides operating funds for the new habitat biologist to identify, develop, prioritize, and submit new projects for funding.  

Modification 1 included the addition of IDFG's Pahsimeroi River Restoration BLM near the P16 diversion, as well as two projects to be sponsored by Trout Unlimited (TU) and one by Lemhi  Soil and Water Conservation District (Lemhi SWCD).  TU will sponsor the Lower Pahsimeroi Channel Restoration and the Patterson Big Springs Creek 10 headgate and channel restoration.  Lemhi SWCD will sponsor vegetation management actions.

Modification 2 included the expansion of the Patterson Big Springs Creek headgate and channel restoration efforts.
Account Type(s):
Expense
Contract Start Date:
01/01/2015
Contract End Date:
09/30/2016
Current Contract Value:
$683,679
Expenditures:
$683,679

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Daniel Affonso Bonneville Power Administration No Interested Party dxaffonso@bpa.gov (503) 230-3893
Daniel Bertram Idaho Governor's Office of Species Conservation Yes Technical Contact daniel.bertram@osc.idaho.gov (208) 756-6322
Jessica Buelow Idaho Department of Fish and Game (IDFG) Yes Technical Contact jessica.buelow@idfg.idaho.gov (208) 756-2271
Art Butts Idaho Department of Fish and Game (IDFG) Yes Technical Contact art.butts@idfg.idaho.gov (208) 287-2798
Rossana Callejas Bonneville Power Administration No Interested Party rxcallejas@bpa.gov (503) 230-7558
Sharon Clark Idaho Department of Fish and Game (IDFG) Yes Technical Contact sharon.clark@idfg.idaho.gov (208) 287-2784
Mike Edmondson Idaho Governor's Office of Species Conservation Yes Supervisor mike.edmondson@osc.idaho.gov (208) 334-2189
Abbie Gongloff Idaho Governor's Office of Species Conservation Yes Technical Contact abbie.gongloff@osc.idaho.gov (208) 756-6322
Michelle Guay Bonneville Power Administration Yes Interested Party mxguay@bpa.gov (503) 230-3459
Amy Hines Idaho Governor's Office of Species Conservation Yes Contract Manager amy.hines@osc.idaho.gov (208) 332-1557
Paul Kline Idaho Department of Fish and Game (IDFG) Yes Technical Contact paul.kline@idfg.idaho.gov (208) 287-2788
Eric (IDFG) Leitzinger Idaho Department of Fish and Game (IDFG) Yes Technical Contact eric.leitzinger@idfg.idaho.gov (208) 287-2798
Jennifer Lord Bonneville Power Administration Yes COR jklord@bpa.gov (503) 230-5192
Solomonn Marsh Bonneville Power Administration Yes Contracting Officer spmarsh@bpa.gov (503) 230-3943
Stacey Meyer Idaho Department of Fish and Game (IDFG) Yes Technical Contact stacey.meyer@idfg.idaho.gov (208) 756-6022
Adair Muth Idaho Governor's Office of Species Conservation Yes Technical Contact adair.muth@osc.idaho.gov (208) 756-6322
Gregory Smith Bonneville Power Administration Yes Env. Compliance Lead gmsmith@bpa.gov (503) 230-5049
Dorothy Welch Bonneville Power Administration Yes F&W Approver dwwelch@bpa.gov (503) 230-5479
Breann Westfall Idaho Governor's Office of Species Conservation Yes Technical Contact breann.westfall@osc.idaho.gov (208) 756-6322


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
All administrative tasks fulfilled with timely quality products A: 119. Routine/daily administration of contract work elements 08/31/2016 09/30/2016
Confirmation of EC/permits to BPA B: 165. Environmental Compliance 08/31/2016 08/31/2016
Pahsimeroi Basin Fish Habitat Restoration Project Identification C: 114. IDFG: Pahsimeroi Drainage Fish Habitat Project Identification 08/31/2016 08/31/2016
Flying Joseph Fish Passage Alternatives D: 175. IDFG: Flying Joseph Fish Passage Alternatives 12/31/2015 07/31/2015
Diversion and fish screen design on the Flying Joseph Ranch E: 175. IDFG: Flying Joseph Diversion Replacement 08/31/2016
Revegetated Sulphur Creek Project Site F: 47. IDFG: Sulphur Creek Riparian Restoration 08/31/2016 08/31/2016
Fury Lane Bridge Installed G: 184. IDFG: Fury Lane Bridge Installation 07/15/2016 06/30/2016
Progress Report has been published I: 132. Submit Progress Report for the period (Jan 2014) to (Dec 2014) 04/22/2015 06/03/2015
Large Woody Structures Installed in the Pahsimeroi River J: 29. IDFG: Install LWD in the Pahsimeroi River on BLM Property near the P16 Diversion 08/31/2016
Plant native vegetation near the P-16 diversion as needed K: 47. IDFG: Plant riparian vegetation on the Pahsimeroi River Restoration Site near P16 Diversion 08/31/2016
Irrigated revegetated areas. L: 198. IDFG: Irrigate revegetation efforts in the Pahsimeroi Drainage (Suphur Cr, Pahsimeroi R- BLM, et al) 08/31/2016 08/31/2016
Flying Joe Fish Passage Alternatives M: 175. IDFG: Flying Joseph Fish Passage Alternatives 08/31/2016 08/15/2016
Final engineering designs for Lower Pahsimeroi River Restoration N: 175. TU: Lower Pahsimeroi River Restoration: Engineering Services 05/30/2016 05/31/2016
Install jack fence as part of the Lower Pahsimeroi River Restoration O: 40. TU: Lower Pahsimeroi River Restoration: Install Jack Fence 08/31/2016 08/26/2016
Increase bank stability for 0.05 miles of the Lower Pahsimeroi River P: 29. TU: Lower Pahsimeroi River Restoration: Channel stabilization 08/31/2016 08/11/2016
Develop alternative water source on lower Pahsimeroi River Q: 34. TU: Lower Pahsimeroi River Restoration: Stockwater 09/30/2016 09/30/2016
Develop a project plan for PBSC-10. R: 174. TU: Pahsimeroi Patterson-Big Springs Creek 10 Headgate and Channel Restoration: Planning 08/31/2016 08/02/2016
Manage vegetation through noxious weed treatments S: 199. SWCD: Pahsimeroi Noxious Weed Treatments 08/31/2016 08/31/2016
Rehabilitate project sites through hydroseeding T: 47. SWCD: Pahsimeroi Rehabilitate Project Sites 08/31/2016
Final engineering designs for the Pahsimeroi Patterson-Big Springs Creek Culvert Replacement U: 175. TU: Pahsimeroi Patterson-Big Springs Creek Culvert Replacement Access Project: Engineering Services 06/01/2016 05/23/2016
Install a pre-engineered modular steel bridge on Patterson-Big Springs Creek V: 184. TU: Pahsimeroi Patterson-Big Springs Creek Culvert Replacement Access Project 08/31/2016 08/18/2016
Completed Annual Report W: 132. Submit Progress Report for the period (Jan 2015) to (Dec 2015) 04/30/2016 06/10/2016

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 198 Maintain Vegetation
  • 1 instance of WE 199 Remove Vegetation
  • 2 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 34 Develop Alternative Water Source
  • 1 instance of WE 40 Install Fence
  • 3 instances of WE 47 Plant Vegetation
  • 2 instances of WE 184 Install Fish Passage Structure
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 174 Produce Plan
  • 5 instances of WE 175 Produce Design
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 198 Maintain Vegetation
  • 1 instance of WE 199 Remove Vegetation
  • 2 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 34 Develop Alternative Water Source
  • 1 instance of WE 40 Install Fence
  • 3 instances of WE 47 Plant Vegetation
  • 2 instances of WE 184 Install Fish Passage Structure
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 174 Produce Plan
  • 5 instances of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Routine/daily administration of contract work elements 01/01/2015
B 165 Environmental Compliance 01/01/2015
C 114 IDFG: Pahsimeroi Drainage Fish Habitat Project Identification 01/01/2015
D 175 IDFG: Flying Joseph Fish Passage Alternatives 04/06/2015
E 175 IDFG: Flying Joseph Diversion Replacement
F 47 IDFG: Sulphur Creek Riparian Restoration 01/01/2016
G 184 IDFG: Fury Lane Bridge Installation 09/02/2015
H 185 Periodic Status Reports for BPA 01/01/2015
I 132 Submit Progress Report for the period (Jan 2014) to (Dec 2014) 01/01/2015
J 29 IDFG: Install LWD in the Pahsimeroi River on BLM Property near the P16 Diversion 09/01/2016
K 47 IDFG: Plant riparian vegetation on the Pahsimeroi River Restoration Site near P16 Diversion 09/01/2016
L 198 IDFG: Irrigate revegetation efforts in the Pahsimeroi Drainage (Suphur Cr, Pahsimeroi R- BLM, et al)
M 175 IDFG: Flying Joseph Fish Passage Alternatives 01/01/2015
N 175 TU: Lower Pahsimeroi River Restoration: Engineering Services 01/01/2015
O 40 TU: Lower Pahsimeroi River Restoration: Install Jack Fence 07/01/2016
P 29 TU: Lower Pahsimeroi River Restoration: Channel stabilization 06/25/2016
Q 34 TU: Lower Pahsimeroi River Restoration: Stockwater 06/25/2016
R 174 TU: Pahsimeroi Patterson-Big Springs Creek 10 Headgate and Channel Restoration: Planning 01/01/2015
S 199 SWCD: Pahsimeroi Noxious Weed Treatments 05/23/2016
T 47 SWCD: Pahsimeroi Rehabilitate Project Sites 07/15/2016
U 175 TU: Pahsimeroi Patterson-Big Springs Creek Culvert Replacement Access Project: Engineering Services 01/01/2015
V 184 TU: Pahsimeroi Patterson-Big Springs Creek Culvert Replacement Access Project 08/01/2016
W 132 Submit Progress Report for the period (Jan 2015) to (Dec 2015) 01/01/2015