| Province | Subbasin | % |
|---|---|---|
| Columbia Plateau | Deschutes | 100.00% |
* Expenditures data includes accruals and are based on data through 31-Oct-2025.
| Full Name | Organization | Write Permission | Contact Role | Work Phone | |
|---|---|---|---|---|---|
| Jamie Cleveland | Bonneville Power Administration | Yes | COR | jacleveland@bpa.gov | (503) 230-3160 |
| Israel Duran | Bonneville Power Administration | Yes | Env. Compliance Lead | induran@bpa.gov | (503) 230-3967 |
| Brad Houslet | Confederated Tribes of Warm Springs | Yes | Supervisor | brad.houslet@ctwsbnr.org | (541) 553-2039 |
| Dennis Johnson | Confederated Tribes of Warm Springs | No | Interested Party | dennis.johnson@wstribes.org | (541) 553-3479 |
| Solomonn Marsh | Bonneville Power Administration | Yes | Contracting Officer | spmarsh@bpa.gov | (503) 230-3943 |
| Arthur Mitchell | Confederated Tribes of Warm Springs | No | Administrative Contact | arthur.mitchell@wstribes.org | (541) 553-3219 |
| John Skidmore | Bonneville Power Administration | Yes | F&W Approver | jtskidmore@bpa.gov | (503) 230-5494 |
| Scott Turo | Confederated Tribes of Warm Springs | Yes | Contract Manager | scott.turo@ctwsbnr.org | (541) 553-2025 |
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| NEPA Compliance Requirements Complete for Habitat Restoration Projects To Be Implemented | A: 165. Obtain Environmental Compliance | 02/29/2016 | 09/30/2015 | |
| Riparian Fence Monitoring Report | B: 186. Maintain Riparian Fencing | 02/29/2016 | 02/22/2016 | |
| Riparian Fence Monitoring Report | C: 186. Maintain Water Developments | 02/29/2016 | 02/22/2016 | |
| Riparian Fence Monitoring Report | D: 40. Install Fence at Log Springs Meadow | 01/31/2016 | 02/22/2016 | |
| Mill Creek Habitat Restoration Project Completion Report | E: 30. Mill Creek Habitat Restoration Project | 02/29/2016 | 02/22/2016 | |
| Mill Creek Habitat Restoration Project Completion Report | F: 180. Mill Creek Habitat Restoration Project | 02/29/2016 | 02/22/2016 | |
| Mill Creek Habitat Restoration Project Completion Report | G: 29. Mill Creek Habitat Restoration Project | 01/31/2016 | 02/22/2016 | |
| Mill Creek Habitat Restoration Project Completion Report | H: 47. Mill Creek Habitat Restoration Project | 02/29/2016 | 02/22/2016 | |
| Riparian Fence Monitoring Report | I: 198. Treat Weeds at Mill Creek Project Site | 01/31/2016 | 03/31/2015 | |
| Indian Creek Culvert Removal Report | J: 85. Remove Culvert on Indian Creek | 02/29/2016 | 02/22/2016 | |
| AEM Monitoring Dataset Uploaded to AEMonitoring.org | K: 157. Collect Channel Modification Action Effectiveness Data in Mill Creek in the Upper Deschutes | 02/29/2016 | 02/22/2016 | |
| Out Year Planning Summary | L: 114. Identify & Select Projects for Future Implementation | 02/29/2016 | 02/22/2016 | |
| Education & Outreach Summary | M: 99. Communication with Tribal Public | 02/29/2016 | 02/22/2016 | |
| Progress Report has Been Published | N: 132. Submit Progress Report for the Period (January 2015) to (December 2015) | 02/29/2016 | 02/22/2016 | |
| Funding Package - Submit Package To COTR | P: 119. Manage Project | 11/30/2015 | 11/30/2015 | |
| Sediment Dataset and Metadata | Q: 157. Sediment Status and Trends in the Upper Deschutes | 02/29/2016 | 02/22/2016 | |
| Post Implementation Dataset and Metadata | R: 157. Collect Post Implmementation Monitoring in the Upper Deschutes | 02/29/2016 | 02/22/2016 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Chinook (O. tshawytscha) - Deschutes River Summer/Fall ESU |
|
| Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU |
|
| Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened) |
|
| Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
| Lamprey, Pacific (Entosphenus tridentata) |
|
| Trout, Bull (S. confluentus) (Threatened) |
|
| Trout, Interior Redband (O. mykiss gairdnerii) |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 165 | Obtain Environmental Compliance | 03/01/2015 | ||||||
| B | 186 | Maintain Riparian Fencing | 03/01/2015 | ||||||
| C | 186 | Maintain Water Developments | 03/01/2015 | ||||||
| D | 40 | Install Fence at Log Springs Meadow | 03/01/2015 | ||||||
| E | 30 | Mill Creek Habitat Restoration Project | 03/01/2015 | ||||||
| F | 180 | Mill Creek Habitat Restoration Project | 03/01/2015 | ||||||
| G | 29 | Mill Creek Habitat Restoration Project | 03/01/2015 | ||||||
| H | 47 | Mill Creek Habitat Restoration Project | 03/01/2015 | ||||||
| I | 198 | Treat Weeds at Mill Creek Project Site | 03/01/2015 | ||||||
| J | 85 | Remove Culvert on Indian Creek | 03/01/2015 | ||||||
| K | 157 | Collect Channel Modification Action Effectiveness Data in Mill Creek in the Upper Deschutes | 03/01/2015 | ||||||
| L | 114 | Identify & Select Projects for Future Implementation | 03/01/2015 | ||||||
| M | 99 | Communication with Tribal Public | 03/01/2015 | ||||||
| N | 132 | Submit Progress Report for the Period (January 2015) to (December 2015) | 03/01/2015 | ||||||
| O | 185 | Periodic Status Reports for BPA | 03/01/2015 | ||||||
| P | 119 | Manage Project | 03/01/2015 | ||||||
| Q | 157 | Sediment Status and Trends in the Upper Deschutes | 03/01/2015 | ||||||
| R | 157 | Collect Post Implmementation Monitoring in the Upper Deschutes | 03/01/2015 |