Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 68666: 2000-039-00 EXP WALLA WALLA SALMONID PRODUCTION M&E
Project Number:
Title:
Walla Walla River Basin Monitoring and Evaluation (M&E)
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Walla Walla 100.00%
Contract Number:
68666
Contract Title:
2000-039-00 EXP WALLA WALLA SALMONID PRODUCTION M&E
Contract Continuation:
Previous: Next:
65224: 2000-039-00 EXP CTUIR WALLA WALLA SALMONID PRODUCTION M&E
  • 72135: 2000-039-00 EXP WALLA WALLA SALMONID PRODUCTION M&E
Contract Status:
Closed
Contract Description:
This research, monitoring and evaluation project was established in 2007 as a collaborative accord between the Confederated Tribes of the Umatilla Indian Reservation (CTUIR), Washington Department of Fish and Wildlife (WDFW), and Bonneville Power Administration (BPA).  In January 2007, BPA requested of this project an amended collaborative proposal; one that emphasized salmonid status and trend monitoring.  Tribal and state partners agreed to collaborate on the project proposal, budget, statement of work and annual report; but, retained their individual contracts with BPA.  Prior to this collaboration, the CTUIR and WDFW conducted separate studies under BPA project numbers 200003900 & 199802000; see http://data.umatilla.nsn.us/, http://wdfw.wa.gov/conservation/, and efw.bpa.gov.

The Walla Walla subbasin supports ESA listed populations of steelhead and bull trout, and a reintroduced population of spring Chinook. These populations are depressed relative to historic levels.  Spring Chinook were extirpated from the Walla Walla in the early 20th century.  For the past 25 years the CTUIR and others have implemented numerous passage, flow, and habitat  to improve salmonid  production in the Subbasin.  

The Tribes Walla Walla Spring Chinook program began in 2000 with the outplanting of hatchery adults collected from the Ringold Hatchery, Carson National Fish Hatchery, and the Umatilla River at Three Mile Falls Dam.  Direct stream release of hatchery reared juveniles began in 2005 using Carson stock from the Carson National Fish Hatchery. Monitoring & Evaluation of the Spring Chinook Program began in 2000.  The work included assessment of spring Chinook and steelhead natural production, and evaluation of fish passage based on adult steelhead and bull trout.  In 2007 CTUIR, WDFW, and BPA developed a collaborative M & E program in the Subbasin based on salmonid VSP Parameters of abundance, productivity, diversity, and spatial structure.  The expanded project was designed to provide high level indicators of fish population status and trends for spring Chinook, steelhead, and bull trout.  This information is used to inform the CTUIR first foods management, and to address BPA fish and wildlife program strategies.  

The purpose of this M & E project is to addresses the adaptive management requirements of the Spring Chinook Program, and to maintain the baseline monitoring needed by the existing management system. This effort includes an ecosystem-based scientific framework for adaptive management and performance evaluation based on measurements of success and monitors of risk to other species and populations.  The techniques and designs used for implementation and detailed methodology can be found online at www.monitoringmethods.org.  This collaborative effort is funded by the Columbia River Fish Accords.  Our M & E objectives were developed based on the requirements of the Walla Walla Spring Chinook Hatchery Master Plan (HMP), BPA’s Fish Management Sub-strategies, the Reasonable and Prudent Alternatives (RPA’s) of the Columbia Power System Biological Opinion, and the existing comprehensive fish restoration program.  Existing plans for the Umatilla River, Grande Ronde River, Johnson Creek, and the Okanogan River were reviewed to develop the structure and content requirements for the objectives and technical methodology.    


Project work emphasizes Mill Creek, Walla Walla and Touchet rivers, and is coordinated with local stakeholders whenever possible (e.g., ODFW, USFWS, USACE, USFS, the Walla Walla Subbasin Watershed Council, Snake River Salmon Recovery Board (SRSRB),  local irrigation districts and other public and private groups).  

CTUIR project offices are located at the William A. Grant Water and Science Center at Walla Walla Community College, while the WDFW South East Washington District Offices are located in Dayton, Washington. Previously, CTUIR and WDFW conducted separate studies and reported to BPA in separate annual reports, under project numbers 199802000 and 200003900.  Previous project reports, data and metadata are found at the CTUIR website www.data.umatilla.nsn.us/fisheries/index.aspx, or WDFW website at www.wdfw.wa.gov, or the BPA website (efw.bpa.gov).
Account Type(s):
Expense
Contract Start Date:
03/01/2015
Contract End Date:
02/29/2016
Current Contract Value:
$594,748
Expenditures:
$594,748

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Compliance achieved and documented B: 165. Compliance for WEs C thru J 03/01/2015 03/01/2015
Fish salvage data C: 28. Fish Salvage 02/29/2016 02/29/2016
PIT- Array Monitoring and Data Distribution D: 70. Upgrade and maintain PIT arrays 02/29/2016 02/29/2016
PIT tagged outmigrants E: 158. PIT Tag smolts (out-migrant tagging) 02/29/2016 02/29/2016
PIT tag Hatchery smolts F: 158. PIT Tag smolts (hatchery tagging) 11/30/2015 11/30/2015
Adult fish count from Nursery Bridge Dam G: 157. Adult fish counts at Nursery Bridge Dam (video work) 02/29/2016 02/29/2016
Spring Chinook spawner/ carcass survey data H: 157. Spring Chinook Spawner / Carcass Surveys for run reconstruction estimates 10/31/2015 10/31/2015
Smolt monitoring and PIT-tagging data I: 157. Outmigrant monitoring for population estimates, survival, & migration 02/29/2016 02/29/2016
Walla Walla River Stream Gauge Monitoring and Data Distribution J: 157. Stream Gauge Monitoring and Data Distribution 02/29/2016 02/29/2016
Analyzed data K: 162. Analyze Data 02/29/2016
Progress Report has been published L: 132. RME Annual Technical Progress Report (1-1-2015 ) to (12-31-2015) 02/29/2016
Submit BiOp RPA Report in Taurus M: 202. BiOp RPA Report for Steelhead CY 2015 02/29/2016
All administrative tasks fulfilled with timely quality products N: 119. Manage & Administer Walla Walla Salmonid Monitoring and Evaluation Project 02/29/2016 02/29/2016
Provide Technical Review of M & E Implementation Plan O: 122. Quantitative Science and technical support for M & E plan implementation 02/29/2016 02/29/2016

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (Oncorhynchus tshawytscha) - All Populations
  • 1 instance of WE 122 Provide Technical Review and Recommendation
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 1 instance of WE 28 Trap and Haul
  • 1 instance of WE 70 Install Fish Monitoring Equipment
  • 3 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 2 instances of WE 158 Mark/Tag Animals
  • 1 instance of WE 162 Analyze/Interpret Data
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 28 Trap and Haul
  • 1 instance of WE 70 Install Fish Monitoring Equipment
  • 3 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 158 Mark/Tag Animals
  • 1 instance of WE 162 Analyze/Interpret Data
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 28 Trap and Haul

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 03/01/2015
B 165 Compliance for WEs C thru J 03/01/2015
C 28 Fish Salvage 06/26/2015
D 70 Upgrade and maintain PIT arrays 06/26/2015
E 158 PIT Tag smolts (out-migrant tagging) 06/26/2015
F 158 PIT Tag smolts (hatchery tagging) 06/26/2015
G 157 Adult fish counts at Nursery Bridge Dam (video work) 06/26/2015
H 157 Spring Chinook Spawner / Carcass Surveys for run reconstruction estimates 06/26/2015
I 157 Outmigrant monitoring for population estimates, survival, & migration 06/26/2015
J 157 Stream Gauge Monitoring and Data Distribution 06/26/2015
K 162 Analyze Data 03/01/2015
L 132 RME Annual Technical Progress Report (1-1-2015 ) to (12-31-2015) 03/01/2015
M 202 BiOp RPA Report for Steelhead CY 2015
N 119 Manage & Administer Walla Walla Salmonid Monitoring and Evaluation Project 03/01/2015
O 122 Quantitative Science and technical support for M & E plan implementation 03/01/2015