SOW Report
Contract 70143: 2010-001-00 CAP BARKLEY IRRIGATION - MVID
Project Number:
Title:
Upper Columbia Programmatic Habitat
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Cascade Entiat 25.00%
Methow 25.00%
Okanogan 25.00%
Wenatchee 25.00%
Contract Number:
70143
Contract Title:
2010-001-00 CAP BARKLEY IRRIGATION - MVID
Contract Continuation:
Previous: Next:
n/a
  • 76789: 2010-001-00 EXP BARKLEY IRRIGATION - MVID - EC - CR-SURVEY
  • 78279: 2010-001-00 CAP BARKLEY IRRIGATION - MVID
Contract Status:
Closed
Contract Description:
Trout Unlimited will be working with BPA and our partners on an extensive upgrade to the Barkley Irrigation Company Infrastructure.  BIC has been purveying water to users on the Barkley shareholders in the same way for the past 110 years. The ditch currently delivers water through a gravity system to users irrigating nearly 600 acres.  The proposed project would eliminate the present diversion and move it 1.5-2 miles downstream and convert the open ditch to an in river pump and pressurized pipe system. The existing ditch is estimated to be about 26,000 feet in length. Design and construction will include pipe type and sizes, route selection, road crossing details, turnouts, metering requirements, etc.

In the past construction of a wing-dam and cleaning of the intake channel to divert water into the Barkley Ditch has impacted important habitat for adult spring Chinook pre-spawning holding and rearing habitat for juvenile salmon and steelhead. These impacts have occurred at the diversion wing-dam, in over 1,000 feet of Methow River side channel and within 2,500 feet of the Barkley canal, upstream of the fish screen, where the Barkley cleans and clears the ditch for water delivery, prior to the fish screen approximately .5 miles downstream.  In addition to preventing the historic diversion activities the project will improve instream flow in this critical reach of the methow river and create a state of the art system, which will efficiently deliver water to the BIC share holders.

Specfic Metrics
2.3: Injury and Mortality: Mechanical Injury – 1 mile habitat access
1.1 Habitat Quality: Anthropogenic Barriers – 0.2 mile habitat accessed Bear Creek
9.2:  Decreased Water Quantity: Water Quantity – 8 miles alternate source and efficiency

In addition there is a direct link between the Barkley Porject and MVID, the share a long portion of ditch.  Trout Unlimited has already worked with MVID to pipe over 5 miles of their infrastructure. However the upper four miles remain unimproved and earthen.  The lower 2  miles of MVID are commingled with the end of the Barkley Ditch.  For numerous reasons it makes sense to pipe both under the same contract and will save money and will create efficiency.
Account Type(s):
Capital
Contract Start Date:
09/15/2015
Contract End Date:
12/14/2016
Current Contract Value:
$50,766
Expenditures:
$50,766

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Brenda Aguirre Bonneville Power Administration Yes Env. Compliance Lead baguirre@bpa.gov (503) 230-5928
Roy Beaty Bonneville Power Administration Yes F&W Approver rebeaty@bpa.gov (503) 230-5213
Joseph Connor Bonneville Power Administration Yes COR jwconnor@bpa.gov (503) 230-3172
Joy Juelson Upper Columbia Salmon Recovery Board Yes Interested Party joy.juelson@ucsrb.org (509) 433-2999
Melody Kreimes Upper Columbia Salmon Recovery Board No Interested Party melody.kreimes@ucsrb.org (509) 888-0321
Lisa Pelly Trout Unlimited (TU) Yes Supervisor lpelly@tu.org (509) 888-0970
Aaron Penvose Trout Unlimited (TU) Yes Contract Manager apenvose@tu.org (509) 888-0970
Karen Wolfe Bonneville Power Administration Yes Contracting Officer ktwolfe@bpa.gov (503) 230-3448


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Complete Environmental Compliance Permitting Processes A: 165. Obtain Required Permits, Authorizations, and Documentation for the Project 12/14/2016 06/30/2016
All administrative tasks fulfilled with timely quality products B: 119. Manage BPA Contracting Requirements 12/14/2016 09/30/2016
Pipeline Installed C: 203. Purchase Pipe for Barkley 12/14/2016
Ordered and installed functioning pipeline for MVID water conveyance. D: 203. Purchase Pipe for MVID 12/14/2016
Removed diversion and regraded for floodplain access E: 84. Remove Historic Barkley Irrigation Diversion 12/14/2016
Checklist Developed F: 154. Develop Checklist 12/14/2016 09/30/2016

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 1 instance of WE 203 Install Water Conservation Measure
  • 1 instance of WE 84 Remove/Install Diversion
  • 1 instance of WE 154 Develop and Negotiate Water Right Transaction
Chinook (O. tshawytscha) - Upper Columbia River Summer/Fall ESU
  • 1 instance of WE 203 Install Water Conservation Measure

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Obtain Required Permits, Authorizations, and Documentation for the Project 09/15/2015
B 119 Manage BPA Contracting Requirements 09/15/2015
C 203 Purchase Pipe for Barkley 10/11/2016
D 203 Purchase Pipe for MVID 10/11/2016
E 84 Remove Historic Barkley Irrigation Diversion 10/11/2016
F 154 Develop Checklist 09/15/2015
G 185 Periodic Status Reports for BPA 09/15/2015
H 132 Submit Progress Report for the period (Sep 2015) to (Sep 2016) - funded through a separate contract 09/15/2015